Contract 24855: 200500800 EXP CHEWUCH DIVERSION
Project Number:
Title:
Chewuch Diversion
Stage:
Closed
Area:
Province Subbasin %
Columbia Cascade Methow 100.00%
Contract Number:
24855
Contract Title:
200500800 EXP CHEWUCH DIVERSION
Contract Continuation:
Previous: Next:
n/a
Contract Status:
History
Contract Description:
Contractor:
Chewuch Basin Council
P.O. Box 1608
Okanogan, WA  98840

Project Manager:
Chris Johnson
Phone - (509) 4220300

Environmental Compliance on this project was produced by Bureau of Reclamation in coordination with BPA staff therefore no Environmental compliance work element appears in this scope of work.


Existing Condition
The Diversions are made through a tunnel that was blasted into a bedrock cliff on the left bank.  There is no headgate or screen at the head of the intake tunnel, and the result, this exposes the first 300 feet of the canal to erosion and potential for failure from overtopping during high flow periods.  In addition, excessive sediment accumulations at the fish screens for both the acclimation pond and the irrigation canal have occurred during periods of high sediment transport because of a lack of headgate control.

Proposed Improvements
This project involves construction of a new upstream fish passage structure to improve passage, renovation of the dam to prevent failure, and constructing a new ditch headworks to eliminate winter redd-stranding and sediment accumulation.  For upstream passage, the fish ladder will be replaced with a roughened channel.  The channel is designed to provide passage at all potential flow regimes.  The existing concrete dam will be modified by increasing the elevation of the dam 6 inches to increase operator safety when placing flash boards in addition to reconstructing the downstream splash apron to stabilize the structure.  An operable headgate with sediment retention capability and a removable adult fish barrier at the head of the ditch will alleviate sediment and redd-stranding.

A  no cost time extension was requested due to weather preventing completion of the HIP BO report to BPA.  This work should be completed by April 30, 2007.
Account Type(s):
Expense
Contract Start Date:
10/10/2005
Contract End Date:
01/31/2007
Current Contract Value:
$149,380
Expenditures:
$149,380

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Chris Eliassen Methow Salmon Recovery Foundation Yes Administrative Contact chrise@methowsalmon.org (509) 996-2787
Linda Hermeston Bonneville Power Administration Yes COR llhermeston@bpa.gov (503) 230-4764
Chris Johnson Chewuch Basin Council No Supervisor johnson_plan@communitynet.org (509) 422-0300
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jenifer Mccune Bonneville Power Administration Yes Contracting Officer jamccune@bpa.gov (503) 230-7429
Colleen Spiering Bonneville Power Administration No Env. Compliance Lead caspiering@bpa.gov (503) 230-5756


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Provided budget and metric information to BPA A: 119. Provide BPA programmatic information 09/15/2006 10/13/2006
Provided budget and metric information to BPA B: 85. Isolate work area, remove and Install new diversion 09/15/2006 10/13/2006
Install headgate control and construct new fish passage roughned channel C: 184. Install Headgate Control on Chewuch Diversion 12/19/2005 12/30/2005
Produce project completion report D: 132. Project Completion Report 01/31/2007 04/10/2007
Provide BPA HIP BO Monitoring Report F: 165. Provide BPA HIP BO Monitoring Report 01/31/2007 03/31/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 184 Install Fish Passage Structure
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 184 Install Fish Passage Structure
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 184 Install Fish Passage Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Provide BPA programmatic information
B 85 Isolate work area, remove and Install new diversion
C 184 Install Headgate Control on Chewuch Diversion
D 132 Project Completion Report
E 185 Periodic Status Reports for BPA
F 165 Provide BPA HIP BO Monitoring Report