| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Crab | 100.00% |
| Previous: | Next: |
|---|---|
| n/a |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Douglas Corkran | Bonneville Power Administration | No | Env. Compliance Lead | dfcorkran@bpa.gov | (503) 230-7646 |
| Joe Deherrera | Bonneville Power Administration | Yes | COR | jldeherrera@bpa.gov | (503) 230-3442 |
| Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
| Ted Nelson | Washington Department of Fish and Wildlife (WDFW) | No | Contract Manager | nelsotfn@dfw.wa.gov | (360) 902-2401 |
| Karen Southwell | Washington Department of Fish and Wildlife (WDFW) | No | Administrative Contact | southkjs@dfw.wa.gov | (360) 664-4993 |
| Jim Tabor | Washington Department of Fish and Wildlife (WDFW) | Yes | Interested Party | taborjet@dfw.wa.gov | (509) 754-4624 |
| Benjamin Zelinsky | Bonneville Power Administration | Yes | F&W Approver | bdzelinsky@bpa.gov | (503) 230-4737 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Dam Safety Permit Exclusion | A: 165. Obtain Dam Safety Exclusion | 06/15/2006 | 03/27/2006 | |
| Provide information for EC | B: 165. Provide Information to Permitting Agencies for Environmental Compliance Documentation | 05/31/2006 | 03/15/2006 | |
| ESA Compliance for TD-2 project | C: 165. Obtain ESA Compliance for TD-2 Sub-project | 07/15/2006 | 03/08/2006 | |
| Water Use Documentation | D: 118. Coordinate with BOR and Quincy Irr. District for project operation | 06/15/2006 | 06/15/2006 | |
| Water Delivery Ditch | E: 181. Excavate Water Delivery Ditch at TD-1 | 11/30/2005 | 11/30/2005 | |
| Water Delivery Ditch Levees | F: 181. Construct Levees Adjacent to the Primary Water Delivery Ditch at the TD-1 project site | 03/31/2006 | 01/02/2006 | |
| Primary Water Control Structure | G: 181. Install Water Control Structure in Delivery Ditch at TD-1 project site | 11/30/2005 | 11/30/2005 | |
| Early Successional-stage Wetlands | H: 181. Excavate 19 Wetland Basins at the TD-2 project Site | 09/30/2006 | ||
| Annual Report | I: 132. Produce Annual Report | 09/30/2006 | ||
| BPA Administrative requirements | K: 119. BPA Administrative requirements | 09/30/2006 | ||
| Wildlife Area Administrative duties | L: 119. WDFW Administrative Requirements | 09/30/2006 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Obtain Dam Safety Exclusion | |||||||
| B | 165 | Provide Information to Permitting Agencies for Environmental Compliance Documentation | |||||||
| C | 165 | Obtain ESA Compliance for TD-2 Sub-project | |||||||
| D | 118 | Coordinate with BOR and Quincy Irr. District for project operation | |||||||
| E | 181 | Excavate Water Delivery Ditch at TD-1 | |||||||
| F | 181 | Construct Levees Adjacent to the Primary Water Delivery Ditch at the TD-1 project site | |||||||
| G | 181 | Install Water Control Structure in Delivery Ditch at TD-1 project site | |||||||
| H | 181 | Excavate 19 Wetland Basins at the TD-2 project Site | |||||||
| I | 132 | Produce Annual Report | |||||||
| J | 185 | Quarterly Reports | |||||||
| K | 119 | BPA Administrative requirements | |||||||
| L | 119 | WDFW Administrative Requirements |