| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Walla Walla | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Project list developed and submitted | A: 114. Identify and select projects in Walla Walla Basin | 12/30/2006 | 02/10/2007 | |
| Project summaries complete | B: 115. Inventory project areas | 03/30/2007 | 07/30/2006 | |
| Environmental clearance complete | D: 165. For Gose Street | 08/14/2006 | 09/15/2006 | |
| Design oversight accomplished | E: 119. Manage Design at Gose Street | 08/15/2006 | 10/23/2006 | |
| Construction process overseen | F: 119. Manage Construction at Gose Street | 10/31/2006 | 02/10/2007 | |
| Environmental compliance complete | H: 165. Compliance for WEs B, I, J, K, L, M, N, P, Q, and R | 01/31/2007 | 01/31/2007 | |
| 4 acres planted | I: 47. WW River Mile 32 | 12/29/2006 | 10/23/2006 | |
| Revegetation of of upland/riparian corridor | J: 47. WW River Mile 49 | 12/22/2006 | 10/23/2006 | |
| @ 5 acres planted | K: 47. WW River Mile 50 | 03/31/2006 | 05/04/2006 | |
| Approximately 13 acres reestablished with native plants | L: 47. SFWW River Mile 5 | 03/31/2007 | 03/31/2007 | |
| Noxious species controlled | M: 22. Control invasive species at Various Project Sites | 05/01/2007 | 05/01/2007 | |
| Completion of livestock exclusion fence | N: 40. Build livestock fence on Cottonwood Creek | 03/30/2007 | 03/30/2007 | |
| Completed design for instream work at RM 50 | O: 175. Develop instream design for RM 50 | 03/30/2007 | 02/10/2007 | |
| fences returned to full functionality | R: 186. Maintain Fences | 05/01/2007 | 05/10/2007 | |
| Data collection process complete | S: 157. Field Data Collection | 12/29/2006 | 02/10/2007 | |
| written documentation of understanding between parties. | T: 118. EXPIRED: Landowner/Agency Coordination | 01/31/2007 | 02/10/2007 | |
| 2005 and 20006 Annual reports submitted | U: 132. Produce 2005 annual report | 01/31/2007 | ||
| administrative tasks completed | V: 119. Conduct all management activities | 03/30/2007 | 02/10/2007 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| All Anadromous Fish |
|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 114 | Identify and select projects in Walla Walla Basin | |||||||
| B | 115 | Inventory project areas | |||||||
| C | 118 | EXPIRED: Seek cost-share funding | |||||||
| D | 165 | For Gose Street | |||||||
| E | 119 | Manage Design at Gose Street | |||||||
| F | 119 | Manage Construction at Gose Street | |||||||
| G | 119 | Manage Project at Rainwater | |||||||
| H | 165 | Compliance for WEs B, I, J, K, L, M, N, P, Q, and R | |||||||
| I | 47 | WW River Mile 32 | |||||||
| J | 47 | WW River Mile 49 | |||||||
| K | 47 | WW River Mile 50 | |||||||
| L | 47 | SFWW River Mile 5 | |||||||
| M | 22 | Control invasive species at Various Project Sites | |||||||
| N | 40 | Build livestock fence on Cottonwood Creek | |||||||
| O | 175 | Develop instream design for RM 50 | |||||||
| P | 119 | Manage instream work at RM 50 | |||||||
| Q | 29 | Improve instream habitat | |||||||
| R | 186 | Maintain Fences | |||||||
| S | 157 | Field Data Collection | |||||||
| T | 118 | EXPIRED: Landowner/Agency Coordination | |||||||
| U | 132 | Produce 2005 annual report | |||||||
| V | 119 | Conduct all management activities | |||||||
| W | 185 | Periodic Status Reports for BPA |