Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 27871: 1995-063-25 EXP YKFP YAKIMA R MONITORING AND EVALUATION (WDFW)
Project Number:
Title:
Yakima River Monitoring and Evaluation-Yakima/Klickitat Fisheries Project (YKFP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
27871
Contract Title:
1995-063-25 EXP YKFP YAKIMA R MONITORING AND EVALUATION (WDFW)
Contract Continuation:
Previous: Next:
22370: 1995-063-25 YKFP MONITORING & EVALUATION
  • 34450: 1995-063-25 EXP YKFP YAKIMA R MONITORING & EVALUATION (WDFW)
Contract Status:
Closed
Contract Description:
Preface and Background
The monitoring and evaluation activities supported by this agreement were determined by consensus of the scientists from the Yakama Nation (YN) and the Washington Department of Fish and Wildlife (WDFW).  Project M & E activities have been subjected to rigorous scientific and technical review by the YKFP's Science/Technical Advisory Committee (STAC) and the Monitoring Implementation Planning Team (MIPT).  STAC is responsible for the conceptual design of the project's M & E program, and MIPT must transform the conceptual design into the tasks identified in this agreement.
The process used by STAC and MIPT to verify the usefulness of these activities and the timing of their implementation involves consideration of the following principles:
1. YKFP monitoring should evaluate the success (or lack of it) of project supplementation efforts and its impacts, including juvenile survival, natural production and reproductive success, ecological interactions, and genetics;  
2. YKFP monitoring should be comprehensive; and,
3. YKFP monitoring should be done in such a way that results are of use to salmon production efforts throughout the Columbia basin and the region.
With the above principles as a backdrop, STAC and MIPT developed the M & E action plan in three phases. The first phase was primarily conceptual. STAC and MIPT defined critical issues and problems, and identified associated response variables.  The second phase was quantitative, which determined the scale and size of an effective monitoring effort. A critical element of the quantitative phase was an assessment of the precision with which response variables can be measured, the probability of detecting real impacts, and the sample sizes required for a given level of statistical precision and power.  The third and final phase was logistical.  At this point the feasibility of monitoring measures was evaluated as to practicality and cost. The YKFP Policy Group, representing the policy leads for both the YN and WDFW, has determined that the M & E activities covered by this agreement are necessary, effective, and cost-efficient.
This statement of work covers the share of the monitoring and evaluation activities under this project for the Yakima River Subbasin assigned to the WDFW staff.
For additional information on the overall YKFP projects and the linkage between work elements (M&E, Production, and Management), please see the following annual report at BPA's publication web site:  DOE # 6215.3, "Short Project Overview of Spring Chinook Salmon Supplementation in the Upper Yakima Basin: Yakima/Klickitat Fisheries Project."
Account Type(s):
Expense
Contract Start Date:
05/01/2006
Contract End Date:
04/30/2007
Current Contract Value:
$940,428
Expenditures:
$940,428

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All data collected, validated and appropriately stored in WDFW Olympia & Ellensburg computers. A: 157. Natural Production Monitoring and Evaluation in the Yakima River Basin 04/30/2007 04/30/2007
All data collected, validated and appropriately stored in WDFW Olympia computers. B: 157. Genetic Monitoring and Evaluation in the Yakima River Basin 04/30/2007 04/30/2007
All data collected, validated and appropriately stored in WDFW Olympia and Ellensburg computers. C: 157. Ecological Interactions Monitoring and Evaluation in the Yakima River Basin 04/30/2007 04/30/2007
EC coordination completed. D: 165. Participate in ESA/NEPA Compliance for Yakima Basin Monitoring and Evaluation 04/30/2007 04/30/2007
Reports completed. E: 132. Yakima Basin Monitoring and Evaluation Annual Report 04/30/2007 04/30/2007
Peer reviewed publications completed. F: 183. Yakima Basin Monitoring and Evaluation Peer-Reviewed Publications 04/30/2007 04/30/2007
Management and administrative requirements are complete. G: 119. Manage and Administer Yakima Basin Monitoring and Evaluation 04/30/2007 04/30/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 183 Produce Journal Article
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 157 Natural Production Monitoring and Evaluation in the Yakima River Basin
B 157 Genetic Monitoring and Evaluation in the Yakima River Basin
C 157 Ecological Interactions Monitoring and Evaluation in the Yakima River Basin
D 165 Participate in ESA/NEPA Compliance for Yakima Basin Monitoring and Evaluation
E 132 Yakima Basin Monitoring and Evaluation Annual Report
F 183 Yakima Basin Monitoring and Evaluation Peer-Reviewed Publications
G 119 Manage and Administer Yakima Basin Monitoring and Evaluation
H 185 Periodic Status Reports for BPA