| Environmental Compliance Documents |
A: 165. Produce Environmental Compliance Documentation |
|
06/30/2007 |
|
| Environmental Surveys |
B: 165. Environmental Surveys |
|
04/30/2007 |
|
| Presentation Materials |
C: 99. Program Presentations/Information Sessions |
|
08/31/2007 |
09/30/2007 |
| List of potential Habitat Improvement Projects, Landowner Contacts |
D: 114. Initiate Landowner Contacts/Identify and Select Projects |
|
08/31/2007 |
09/30/2007 |
| Long-Term Agreements |
E: 92. Prepare Cooperative Agreements/Leases/Easements |
|
08/31/2007 |
08/31/2007 |
| Project Plans |
F: 174. Prepare Project Plans |
|
03/31/2007 |
03/31/2007 |
| Inter-Agency Coordination |
G: 189. Inter-Agency Coordination |
|
09/30/2007 |
09/30/2007 |
| Willow Installation Review |
H: 122. Provide On-Site Technical Review |
|
09/30/2007 |
09/30/2007 |
| Project Designs |
I: 175. Develop Project Designs |
|
09/30/2007 |
|
| Riparian Fence |
J: 40. Install Fence |
|
09/30/2007 |
|
| Off-Site Livestock Watering Developments |
K: 34. Develop Alternative Water Sources |
|
09/30/2007 |
|
| Riparian Vegetation |
L: 47. Plant Riparian Vegetation |
|
09/30/2007 |
09/30/2007 |
| Fence Maintenance |
M: 186. Maintain Livestock Exclusion Fences - Birch Creek |
|
09/30/2007 |
09/30/2007 |
| Fence Maintenance |
N: 186. Maintain Livestock Exclusion Fences - Meacham Creek |
|
09/30/2007 |
09/30/2007 |
| Barrier Remediation Projects |
O: 85. Implement Barrier Remediation Projects |
|
09/30/2007 |
|
| Stable Channel Design Projects |
P: 30. Implement Stable Channel Design Projects |
|
09/30/2007 |
|
| Installed, operational sprinkler system |
Q: 150. Upgrade Gambill/Weinke Irrigation System to Pressurized Sprinklers |
|
09/30/2007 |
09/30/2007 |
| Instream Structure Maintenance |
R: 186. Maintain Bank Stability Structures and Stable Channel Design Projects |
|
09/30/2007 |
09/30/2007 |
| Weed Control treatments - 117.4 acres |
S: 22. Weed Control (ODFW) |
|
09/30/2007 |
09/30/2007 |
| Weed Control Treatment Contracts |
T: 22. Weed Control (Contracts) |
|
07/15/2007 |
07/15/2007 |
| Riparian Plantings |
U: 22. Maintain and Irrigate Riparian Planting Sites |
|
09/30/2007 |
09/30/2007 |
| Stream Flow/Temperature Data |
V: 157. Collect Stream Flow/Temperature Data |
|
09/30/2007 |
09/30/2007 |
| Temperature Data |
W: 157. Collect and Summarize Temperature Data |
|
09/30/2007 |
09/30/2007 |
| Channel/Habitat Surveys |
X: 157. Reconnaissance and Pre-Work Channel/Habitat Surveys |
|
08/31/2007 |
09/30/2007 |
| Follow-Up Channel/Habitat Surveys |
Y: 157. Follow-up Channel/Habitat Surveys |
|
09/30/2007 |
09/30/2007 |
| Program Administration Documents, Project Contracts |
Z: 119. Manage and Administer Project Activities |
|
09/30/2007 |
09/30/2007 |
| Annual Report |
AA: 132. Produce Annual Report |
|
03/15/2007 |
03/31/2007 |