Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 32331: 2007-397-00 CAP JOHN DAY TRIB/PASS & FLOW - WATERSHED RESTORATION
Project Number:
Title:
John Day Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
32331
Contract Title:
2007-397-00 CAP JOHN DAY TRIB/PASS & FLOW - WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
n/a
  • 37186: 2007-397-00 CAP JOHN DAY TRIB/PASS & FLOW-CAP
Contract Status:
Closed
Contract Description:
The John Day is the nation’s second longest free-flowing river in the contiguous United States and the longest containing entirely unsupplemented runs of anadromous fish.  Located in eastern Oregon, the basin drains over 8,000 square miles, Oregon’s fourth largest drainage basin, and incorporates portions of eleven counties.  Originating in the Strawberry Mountains near Prairie City, the John Day River flows 284 miles in a northwesterly direction, entering the Columbia River approximately four miles upstream of the John Day dam.  With wild runs of spring Chinook salmon and summer steelhead, westslope cutthroat, and redband and bull trout, the John Day system is truly a basin with national significance.

The majority of the John Day basin was ceded to the Federal government in 1855 by the Confederated Tribes of the Warm Springs Reservation of Oregon (Tribes).  In 1997, the Tribes established an office in the basin to coordinate restoration projects, monitoring, planning and other watershed activities on private and public lands.  Once established, the John Day Basin Office (JDBO) formed a partnership with the Grant Soil and Water Conservation District (GSWCD) and the Wheeler Soil and Water Conservation Districts(WSWCD), which subcontract the majority of the construction implementation activities for these projects from the JDBO.  

The GSWCD/WSWCD completes the landowner contact, preliminary planning, engineering design, permitting, construction contracting, and construction implementation phases of most projects.  The JDBO completes the planning, grant solicitation/defense, environmental compliance, administrative contracting, monitoring, and reporting portion of the program.  Most phases of project planning, implementation, and monitoring are coordinated with the private landowners and basin agencies, such as the Oregon Department of Fish and Wildlife and Oregon Water Resources Department.
Account Type(s):
Capital
Contract Start Date:
02/01/2007
Contract End Date:
01/31/2008
Current Contract Value:
$1,376,763
Expenditures:
$1,233,819

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Produce all required NEPA documents A: 165. Produce Environmental Compliance Documentation 06/30/2007 06/30/2007
BPA Project Administration Requirements B: 119. Manage Administer Projects 01/31/2008 01/31/2008
Data for Matrix of pathways used in NEPA Documents C: 157. ESA Data Collection for NEPA Documents 01/31/2008 09/18/2007
Data for NEPA Compliance D: 157. North Fork Watershed Council ESA Monitoring on Wheeler,NFJDR projects 09/01/2007 09/01/2007
Greenhouse and Nursery Maintained E: 186. Native Plants Nursery Maintenance and operation 01/31/2008 01/10/2008
Maintain native Plants Nursery F: 22. Maintain Vegetation 12/28/2007 07/28/2007
4,000 cuttings and plants planted at construction sites. G: 47. Plant Vegetation 06/30/2007 06/19/2007
Project Designs for 2007 Construction Projects H: 175. Produce Design and/or Specifications - GSWCD 01/31/2008 06/19/2007
Blue Mountain Ditch Diversion I: 84. Blue Mountain Ditch Diversion fish passage structure 09/08/2007 09/08/2007
Upper Clear Creek Diversion J: 84. Replace Existing Push-up at Upper Clear Creek Diversion 09/08/2007 09/08/2007
Vinegar Diversion K: 84. Replace Existing Push-up atVinegar Creek Diversion 09/08/2007 09/08/2007
City of Fossil Culvert L: 184. Replace Existing culvert obstruction at City of Fossil Culvert 09/30/2007 06/30/2007
Canyon Creek Culvert #1 M: 184. Replace Existing culvert obstruction at Canyon Creek Culvert #1 Malheur N.F. 10/01/2007 10/01/2007
Canyon Creek Culvert #2 N: 184. Replace Existing culvert obstruction at Canyon Creek Culvert #2 Malheur N.F. 10/01/2007 10/01/2007
North Ditch Diversion Middle Fork O: 84. Replace Existing Push-up at North Ditch Diversion Middle Fork 09/08/2007 09/08/2007
South Ditch Diversion Middle Fork P: 84. Replace Existing Push-up at South Ditch Diversion Middle Fork 09/08/2007 09/08/2007
Wilson Diversion Q: 84. Replace Existing Push-up at Wilson Diversion 09/08/2007 09/08/2007
Forestry Diversion R: 84. Replace Existing Push-up at Forestry Diversion 09/08/2007 09/08/2007
Bear Creek Diversion S: 84. Replace Existing Push-up at Bear Creek Diversion 09/08/2007 09/08/2007
Osborn Diversion T: 84. Replace Existing Push-up at Osborn Diversion 09/08/2007 09/06/2007
Upper Cottonwood Diversion U: 84. Replace Existing Push-up at Upper Cottonwood Diversion 09/08/2007 09/08/2005
Dead Cow Culvert and fish passage structure V: 184. Dead Cow Gulch Culvert Removal and Fish Passage 12/01/2007 10/01/2007
Hashknife Phase 1 W: 184. Hashknife Phase #1 09/08/2007 09/08/2007
Osborn Pipeline X: 184. Osborn Pipeline Phase #1 09/08/2007 09/08/2004
Beech Creek Crossing - Tier Two Y: 80. Replace Existing Push-up at Beech Creek Crossing - Tier Two 01/31/2008
North Diversion Reynolds Creek Z: 84. Replace Existing Push-up at North Diversion Reynolds Creek 09/08/2007 09/08/2006
Bear Creek Diversion - Tier Two AA: 84. Replace Existing Push-up at Bear Creek Diversion - Tier Two 01/31/2008
Bauer Lemons Ditch Diversion- Tier Two AB: 84. Replace Existing Push-up at Bauer Lemons Ditch Diversion - Tier Two 01/31/2008
Panama Ditch Diversion - Tier Two AC: 84. Replace Existing Push-up at Panama Ditch Diversion - Tier Two 01/31/2008
Long Box Diversion AD: 84. Replace Existing Push-up at Long Box Diversion -Tier Two 01/31/2008
Morgan Ditch Diversion AE: 84. Replace Existing Push-up at Morgan Ditch Diversion 09/08/2007 09/08/2007
Kinzua Diversion AF: 84. Replace Existing Push-up at Kinzua Diversion @ G. C. 09/08/2007 09/08/2007
Dayville Pump Station - Tier Two AG: 84. Dayville Pump Station - Tier Two 01/31/2008
Smith/Holms Ditch Diversion - Tier Two AH: 84. Replace Existing Push-up at Smith/Holmes Ditch Diversion - Tier Two 01/31/2008
Axe Ditch Diversion AI: 84. Replace Existing Push-up at Axe Ditch Diversion 09/08/2007 09/08/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
All Anadromous Fish
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 80 Install Siphon
  • 20 instances of WE 84 Remove/Install Diversion
  • 6 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
All Anadromous Salmonids
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Environmental Compliance Documentation 02/09/2007
B 119 Manage Administer Projects 02/09/2007
C 157 ESA Data Collection for NEPA Documents 02/09/2007
D 157 North Fork Watershed Council ESA Monitoring on Wheeler,NFJDR projects
E 186 Native Plants Nursery Maintenance and operation 03/30/2007
F 22 Maintain Vegetation 04/11/2007
G 47 Plant Vegetation 04/16/2007
H 175 Produce Design and/or Specifications - GSWCD 02/09/2007
I 84 Blue Mountain Ditch Diversion fish passage structure 08/09/2007
J 84 Replace Existing Push-up at Upper Clear Creek Diversion 08/09/2007
K 84 Replace Existing Push-up atVinegar Creek Diversion 08/09/2007
L 184 Replace Existing culvert obstruction at City of Fossil Culvert 06/04/2007
M 184 Replace Existing culvert obstruction at Canyon Creek Culvert #1 Malheur N.F. 05/01/2007
N 184 Replace Existing culvert obstruction at Canyon Creek Culvert #2 Malheur N.F. 05/01/2007
O 84 Replace Existing Push-up at North Ditch Diversion Middle Fork 08/09/2007
P 84 Replace Existing Push-up at South Ditch Diversion Middle Fork 08/09/2007
Q 84 Replace Existing Push-up at Wilson Diversion 04/16/2007
R 84 Replace Existing Push-up at Forestry Diversion 08/09/2007
S 84 Replace Existing Push-up at Bear Creek Diversion 08/09/2007
T 84 Replace Existing Push-up at Osborn Diversion 08/09/2007
U 84 Replace Existing Push-up at Upper Cottonwood Diversion 08/09/2007
V 184 Dead Cow Gulch Culvert Removal and Fish Passage 08/07/2007
W 184 Hashknife Phase #1 07/13/2007
X 184 Osborn Pipeline Phase #1 07/13/2007
Y 80 Replace Existing Push-up at Beech Creek Crossing - Tier Two
Z 84 Replace Existing Push-up at North Diversion Reynolds Creek 08/09/2007
AA 84 Replace Existing Push-up at Bear Creek Diversion - Tier Two
AB 84 Replace Existing Push-up at Bauer Lemons Ditch Diversion - Tier Two
AC 84 Replace Existing Push-up at Panama Ditch Diversion - Tier Two
AD 84 Replace Existing Push-up at Long Box Diversion -Tier Two
AE 84 Replace Existing Push-up at Morgan Ditch Diversion 08/09/2007
AF 84 Replace Existing Push-up at Kinzua Diversion @ G. C. 08/09/2007
AG 84 Dayville Pump Station - Tier Two 02/09/2007
AH 84 Replace Existing Push-up at Smith/Holmes Ditch Diversion - Tier Two
AI 84 Replace Existing Push-up at Axe Ditch Diversion 08/09/2007
AJ 185 Periodic Status Reports for BPA 02/09/2007