Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 32944: 1996 077 02 EXP USFS LOLO CREEK WATERSHED RESTORATION
Project Number:
Title:
Lolo/Selway River Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
32944
Contract Title:
1996 077 02 EXP USFS LOLO CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
n/a
  • 36691: 1996-077-02 EXP USFS LOLO CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Project/Contract History:  
The Lolo Creek Watershed Restoration project (1996-07-02) has been an on-going project of the Nez Perce Tribe Fisheries Watershed Program and BPA since 1996.  The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural and economic practices of the Nez Perce Tribe.  The Lolo Creek watershed contains proposed critical habitat for listed species steelhead trout and potential critical habitat for bull trout; it has moderate habitat potential for spring Chinook salmon.  Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing affects, fish passage issues, and noxious weed infestations.  The project addresses passage problems, primarily at road/stream crossings, on both private and federal land, and addresses riparian planting and riparian protection program management. Completed contract work includes culvert prioritization and assessment, installation of an off-site watering site, 16 culvert replacements, 8 culvert removals, 1100 ft. of stream bank stabilization, 62 miles of road decommissioning, 16 miles of fence installation, over 12,000 riparian trees planted, and continued monitoring and evaluation.
    
Summary of FY 07 contract work:
This project is a part of the Clearwater National Forest-Nez Perce Tribe Watershed Restoration Partnership with in-kind contributions from the Clearwater National Forest.  Since the project's inception, we have shared project planning, costs, and implementation responsibilities.  There are two contracts under this project.  The primary contract is with the Nez Perce Tribe.  This contract with the Clearwater National Forest includes only the funding for specific subcontracts.


A) Replace 2 barrier culverts-
The Rat Creek culvert has been identified as a high priority for replacement as it is undersized and does not pass all life stages of fish.  This culvert will be replaced by the Forest Service (Clearwater National Forest) under this contract with BPA, and the Nez Perce Tribe will assist in bid package preparation, contractor selection, technical oversight and final inspection. The existing culvert will be replaced, located at T33N/R6E/Sec.33, with a new culvert that is designed for streambank simulation and to endure the 100 year flood event.  This replacement will return fish passage to 4.3 miles of stream for all life stages of aquatic species including juvenile spring Chinook and steelhead.

The Snowshoe Creek culvert has been identified as a high priority for replacement as it is undersized and does not pass all life stages of fish.  This culvert will be replaced by the Forest Service (Clearwater National Forest) under this contract with BPA, and the Nez Perce Tribe will assist in bid package preparation, contractor selection, technical oversight and final inspection. The existing culvert will be replaced, located at T34N/R6E/Sec.8, with a new culvert that is designed for streambank simulation and to endure the 100 year flood event.  This replacement will return fish passage to 0.9 miles of stream for all life stages of aquatic species including juvenile spring Chinook and steelhead.  All associated implementation/project effectiveness monitoring and evaluation for culvert replacements and road decommissioning and improvement will be conducted by the Nez Perce Tribe in their contract with BPA under this project.
Account Type(s):
Expense
Contract Start Date:
03/01/2007
Contract End Date:
02/29/2008
Current Contract Value:
$69,958
Expenditures:
$69,958

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Anne Connor US Forest Service (USFS) Yes Contract Manager aconnor@fs.fed.us (208) 476-8235
Lois Geary US Forest Service (USFS) No Administrative Contact lgeary@fs.fed.us (208) 983-7008
Mark Johnson Nez Perce Tribe Yes Technical Contact markj@nezperce.org (208) 621-3561
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Rebecca Lloyd Nez Perce Tribe No Technical Contact rebeccal@nezperce.org (202) 621-3544
Heidi McRoberts Nez Perce Tribe Yes Technical Contact heidim@nezperce.org (208) 621-3548
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Tom Reilly US Forest Service (USFS) No Supervisor treilly@fs.fed.us (208) 476-8273


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Provide environmental compliance information to BPA for projects on Forest Service Lands 05/31/2007 07/16/2007
Culvert replacement complete B: 184. Replace Rat Creek Culvert 09/30/2007 09/04/2007
Culvert replacement complete C: 184. Replace Snowshoe Creek Culvert 09/30/2007 09/04/2007
FY 08 SOW package and accrual estimate D: 119. Management, Coordination and Communication 01/31/2008 01/31/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 184 Install Fish Passage Structure
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 184 Install Fish Passage Structure
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 184 Install Fish Passage Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide environmental compliance information to BPA for projects on Forest Service Lands 02/09/2007
B 184 Replace Rat Creek Culvert 05/26/2004
C 184 Replace Snowshoe Creek Culvert 05/26/2004
D 119 Management, Coordination and Communication 02/09/2007
E 185 Periodic Status Reports for BPA 02/09/2007