Contract 37080: 2003-017-00 EXP ISEMP / WDFW SMOLT TRAPPING /STEELHEAD SURVERYS
Project Number:
Title:
Integrated Status and Effectiveness Monitoring Program (ISEMP)
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
37080
Contract Title:
2003-017-00 EXP ISEMP / WDFW SMOLT TRAPPING /STEELHEAD SURVERYS
Contract Continuation:
Previous: Next:
31661: 2003-017-00 EXP WDFW - SMOLT TRAPPING/STEELHEAD SPAWNER SURVEYS
  • 41349: 2003-017-00 EXP ISEMP / WDFW SMOLT TRAPPING /STEELHEAD SURVEYS
Contract Status:
Closed
Contract Description:
Project #2003-017-00 (Project) seeks to develop two novel monitoring and evaluation programs: (i) subbasin-scale pilot status and trend monitoring efforts for anadromous salmonids and their habitat in the Wenatchee, John Day and South Fork Salmon River subbasins, and (ii) effectiveness monitoring for suites of habitat restoration projects in selected watersheds within the three target subbasins.  This work – critical for implementing the 2000 NMFS FCRPS Biological Opinion (RPA Actions 180, 181, and 183) (BiOp) – builds on current status and trend monitoring programs within each of these subbasins.  Several regional and local organizations are funding and implementing these programs.  In short, this project will integrate existing and new monitoring and evaluation activities in three pilot subbasins to help ensure that provisions of the BiOp are satisfied.

This contract is one of several contracts that will implement this project.  The FINAL REPORT for this contract will contain data that will 1) be submitted to NOAA FISHERIES (also a contractor under this project) for use in a  project level integrated Annual Report and 2) be submitted to BPA as a contract final report according to the terms of this contract.


This Scope of Work (SOW) will enable the Bonneville Power Administration (Bonneville) to implement the Project in the Wenatchee Subbasin with the objectives of (1) quantifying the number of adult steelhead redds, (2) spring Chinook salmon and steelhead smolt production, and (3) estimating life history parameters of spring Chinook and steelhead.  Specifically, within this SOW, Washington Department of Fish and Wildlife (WDFW) will achieve these objectives by 1) estimate the total number of steelhead redds in selected streams within the Wenatchee Subbasin by conducting index spawning ground counts, 2) estimate the smolt production of spring Chinook salmon and steelhead for the Wenatchee Subbasin and will 3) capture juvenile spring Chinook and steelhead in natal summer rearing areas that will subsequently be PIT tagged by Chelan County PUD.  

Technical methodologies for all work conducted under this SOW will follow protocols specified in the following document unless Upper Columbia Regional Technical Team and WDFW mutually agree to changes to these methodologies:

Hillman, T.W.  2004.  Monitoring strategy for the Upper Columbia Basin: Draft report February 1, 2004.  Prepared for Upper Columbia Regional Technical Team, Wenatchee, Washington.
Account Type(s):
Expense
Contract Start Date:
03/01/2008
Contract End Date:
02/28/2009
Current Contract Value:
$176,801
Expenditures:
$176,801

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
David Byrnes Bonneville Power Administration Yes COR dmbyrnes@bpa.gov (503) 230-3171
Sheri Combs Washington Department of Fish and Wildlife (WDFW) No Administrative Contact sheri.combs@dfw.wa.gov (360) 664-4993
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Janice Jackson Washington Department of Fish and Wildlife (WDFW) Yes Administrative Contact janice.jackson@dfw.wa.gov (360) 902-2444
Chris Jordan National Oceanic and Atmospheric Administration Yes Technical Contact chris.jordan@noaa.gov (541) 754-4629
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Todd Miller Washington Department of Fish and Wildlife (WDFW) Yes Contract Manager todd.miller@dfw.wa.gov (509) 382-1710
Andrew Murdoch Washington Department of Fish and Wildlife (WDFW) Yes Technical Contact andrew.murdoch@dfw.wa.gov (509) 664-3148x15
Pamela Nelle Terraqua, Inc. Yes Technical Contact pamela@terraqua.biz (509) 885-8143
Marla Page Washington Department of Fish and Wildlife (WDFW) Yes Supervisor pagemep@dfw.wa.gov (360) 902-2748
Holiday Sloan Terraqua, Inc. No Administrative Contact holidaze@wildblue.net (509) 486-2426
Carol (NOAA) Volk National Oceanic and Atmospheric Administration Yes Interested Party carol.volk@noaa.gov (206) 302-2465
Michael Ward Terraqua, Inc. Yes Technical Contact mike@terraqua.biz (509) 486-2426
Nancy Weintraub Bonneville Power Administration Yes Env. Compliance Lead nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Sign-off from BPA's Environmental Compliance Group that EC requirements are complete A: 165. Environmental compliance for data collection 03/03/2008 03/03/2008
Steelhead spawning surveys B: 157. Steelhead spawning ground surveys 09/30/2008 09/30/2008
Capture juvenile steelhead and Chinook for PIT tagging C: 158. Capture juvenile steelhead and spring Chinook 10/17/2008 10/17/2008
Daily emigration estimates D: 157. Smolt production monitoring 02/02/2009 01/30/2009
Funding Package - Sign contract E: 119. Overall Project Management 02/28/2009 01/30/2009
Final Annual Report submitted to NOAA Fisheries F: 132. Annual Report 02/28/2009 01/30/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental compliance for data collection 02/09/2007
B 157 Steelhead spawning ground surveys 02/09/2007
C 158 Capture juvenile steelhead and spring Chinook 02/09/2007
D 157 Smolt production monitoring 02/09/2007
E 119 Overall Project Management 02/09/2007
F 132 Annual Report 02/09/2007
G 185 Periodic Status Reports for BPA 02/09/2007