| Completed documentation of environmental compliance to BPA |
B: 165. Complete Permit Applications and Provide Documentation to Obtain Compliance. |
|
06/01/2009 |
06/01/2009 |
| Completed hazardous waste surveys |
C: 172. Complete hazardous waste assessments as a part of the pre-acquisition process. |
|
02/28/2010 |
|
| Completed cultural resource surveys |
D: 172. Complete cultural resource surveys. |
|
02/28/2010 |
|
| Completed land surveys |
E: 172. Complete surveys for properties where boundaries are in question. |
|
02/28/2010 |
|
| Completed Property Appraisals |
F: 172. Conduct appraisals for prospective acquisitions |
|
02/28/2010 |
02/28/2010 |
| Completed title search |
G: 172. Conduct title search as part of pre-acquisition process. |
|
02/28/2010 |
02/28/2010 |
| Legal Descriptions |
H: 172. Obtain Legal Description of Acquisitions. |
|
02/28/2010 |
|
| HU report to BPA |
I: 172. Identify Minimum HUs From Land Purchase |
|
02/28/2010 |
|
| Completed Acquisition and Easement Agreements |
J: 172. Land Owner Coordination |
|
02/28/2010 |
02/28/2010 |
| Completed Designs for Construction/Implementation |
K: 122. Review Designs and Details for Habitat Enhancements. |
|
02/28/2010 |
02/28/2010 |
| Completed Operations, Maintenance and Enhancement plan for Big Meadows acquisition. |
L: 174. Complete Management Plan for Big Meadows Acquisition. |
|
02/28/2010 |
|
| Create 20 Wetland Ponds |
M: 181. Create Wetland Ponds on Tacoma/Trimble Management Area. |
|
11/28/2009 |
11/28/2009 |
| Bank stabilization through LWD placement |
N: 29. Add LWD to Shoreline Stabilization on Tacoma/Trimble Management area |
|
11/28/2009 |
11/28/2009 |
| Boundary Fence Installed |
O: 40. Install Boundary Fencing Along Calispell Creek Management Area. |
|
09/28/2009 |
09/28/2009 |
| Tree Stand Thinning |
P: 53. Removal of Undesired Plant Species |
|
11/28/2009 |
11/28/2009 |
| Pend Oreille River Shoreline Stabilization Areas Seeded |
Q: 47. Seed Shoreline Stabilization Site. |
|
11/28/2009 |
11/28/2009 |
| Wetland Shorelines Seeded |
R: 47. Seed Newly Created Wetland Pond Shorelines. |
|
11/16/2009 |
11/16/2009 |
| Planted Riparian Areas on Enhancement Sites |
S: 47. Plant Native Trees and Shrubs in the Tacoma/Trimble Management Area. |
|
11/01/2009 |
11/01/2009 |
| Completed Spring and Fall Burns |
T: 31. Conduct Spring and Fall Controlled Burns in the Tacoma/Trimble Management Area |
|
11/28/2009 |
11/28/2009 |
| Properties Secured From Trespass |
U: 26. Secure 16 Properties and Provide Enforcement Management. |
|
02/28/2010 |
02/28/2010 |
| RM&E Data Used for Future Recommendations |
V: 162. Analysis of RM&E data to determine management actions |
|
02/28/2010 |
02/28/2010 |
| Maintained database |
W: 160. Maintain Database |
|
02/28/2010 |
02/28/2010 |
| Maintain Established Vegetation |
X: 22. Maintain Previously Planted Materials within the Tacoma/Trimble Management Area. |
|
09/28/2009 |
09/28/2009 |
| Maintain Established Vegetation |
Y: 22. Maintain Previously Planted Materials within the Idaho Management Area. |
|
09/28/2009 |
09/28/2009 |
| Management of Vegetation |
Z: 22. Vegetation Management within Flying Goose Property |
|
08/01/2009 |
08/01/2009 |
| Fence Maintained |
AA: 186. Maintain Fence |
|
02/28/2010 |
02/28/2010 |
| Fence maintained |
AB: 186. Maintain Fence |
|
02/28/2010 |
02/28/2010 |
| Water Control Structures Maintained and Functioning |
AC: 186. Maintain Existing Water Control Structures on Wetland Enhancement Sites. |
|
02/28/2010 |
02/28/2010 |
| Buildings Maintained |
AD: 186. Manage and Maintain Facility to Maximal Standards |
|
02/28/2010 |
02/28/2010 |
| Shoreline Stabilization |
AE: 186. Maintain Integrity of Shoreline Stabilization Structures |
|
02/28/2010 |
02/28/2010 |
| Completion of Required Project Reporting to BPA |
AF: 119. Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies |
|
02/28/2010 |
02/28/2010 |
| Completed FY09 Annual Report to BPA |
AG: 132. Annual Report for 2009 Contract Cycle |
|
02/28/2010 |
02/28/2010 |