Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 46219: 1992-061-02 EXP ALBENI FALLS WL KALISPEL
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Kalispel Tribe
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
46219
Contract Title:
1992-061-02 EXP ALBENI FALLS WL KALISPEL
Contract Continuation:
Previous: Next:
41277: 1992-061-02 EXP ALBENI FALLS WL KALISPEL
  • 51417: 1992-061-02 EXP ALBENI FALLS WL KALISPEL
Contract Status:
Closed
Contract Description:
The Idaho Department of Fish and Game formed the Albeni Falls Interagency Work Group in 1985 for the purpose of determining wildlife impacts associated with the construction of the Albeni Falls Hydroelectric Project. Workgroup members include the IDFG, the Kalispel Tribe, the Coeur D'Alene Tribe, the Kootenai Tribe of Idaho and the U. S. Army Corps of Engineers. Once the loss assessments were completed, the group worked collectively to protect, enhance and partially mitigate wildlife impacts in the Pend Oreille Subbasin. The construction of Albeni Falls Dam resulted in the loss of over 20,000 Habitat Units in wetland and riparian habitat types. These losses occurred exclusively within The Kalispel Ceded Lands. Through the acquisition of property rights (fee title to management agreements], property protection and habitat enhancement, The Kalispel Tribe is continuing to mitigate for these losses. This contract provides for enhancement, operation & maintenance and monitoring & evaluation for all properties managed by The Kalispel Tribe in this mitigation project.
The properties acquired to date by The Kalispel Tribe fall into two general categories. Those that are conservation type with limited enhancement work necessary in the Idaho management area [ Beaver Lake, Gamlin Lake and West Branch Priest River] and those that have high potential habitat value but require active enhancement activities to realize their potential [the Flying Goose Ranch, two Tacoma Creek properties, three Trimble Creek properties and two Calispell Creek properties]. Active enhancement work for this contract period will take place in the Tacoma/Trimble Management Area. This Management Area is located 5 miles North of Cusick WA along Highway 20 in Township 34N Range 43E Section 36 and Township 33N Range 43E Sections 1,2,11and 12. Management activities include hydraulic restoration, wetland enhancement, shoreline protection and vegetation restoration.
Along with active enhancement activities, this contract will provide for data collection to provide scientific support for the continuation of these types of enhancement activities on additional properties as they become part of this project. This contract will also cover the operation and maintenance of existing habitat value and previously installed structures.
Account Type(s):
Expense
Contract Start Date:
03/01/2010
Contract End Date:
02/28/2011
Current Contract Value:
$558,568
Expenditures:
$558,568

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Matthew Berger Kalispel Tribe Yes Technical Contact mberger@knrd.org (509) 447-7244
Ray Entz Kalispel Tribe Yes Supervisor rentz@knrd.org (509) 445-1147
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Neil Lockwood Kalispel Tribe Yes Contract Manager nlockwood@knrd.org (509) 445-1147x1274
Jenna Peterson Bonneville Power Administration No Env. Compliance Lead jepeterson@bpa.gov (503) 230-3018
Jolene Seymour Kalispel Tribe No Administrative Contact jseymour@kalispeltribe.com (509) 445-1147
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Completed documentation of environmental compliance to BPA B: 165. Complete Permit Applications and Provide Documentation to Obtain Compliance. 02/28/2011 02/22/2011
Completed hazardous waste surveys C: 172. Complete hazardous waste assessments as a part of the pre-acquisition process. 02/28/2011 02/22/2011
Completed cultural resource surveys D: 172. Complete cultural resource surveys. 02/28/2011 02/22/2011
Completed land surveys E: 172. Complete surveys for properties where boundaries are in question. 02/28/2011 02/22/2011
Completed Property Appraisals F: 172. Conduct appraisals for prospective acquisitions 02/28/2011 02/22/2011
Completed title search G: 172. Conduct title search as part of pre-acquisition process. 02/28/2011 02/22/2011
Legal Descriptions H: 172. Obtain Legal Description of Acquisitions. 02/28/2011 02/22/2011
HU report to BPA I: 172. Identify Minimum HUs From Land Purchase 02/28/2011 02/22/2011
Completed Acquisition and Easement Agreements J: 172. Land Owner Coordination 02/28/2011 02/22/2011
Completed Designs for Construction/Implementation K: 122. Review Designs and Details for Habitat Enhancements. 02/28/2011 01/22/2011
Completed Operations, Maintenance and Enhancement plan for Big Meadows acquisition. L: 174. Complete Management Plan for Big Meadows Acquisition. 02/28/2011 02/22/2011
Create 20 Wetland Ponds M: 181. Create Wetland Ponds on Tacoma/Trimble Management Area 11/28/2010 11/28/2010
Gate valve installation N: 181. Install 3 gate valves in the Tacoma/Trimble Management Area 07/15/2010 09/30/2010
Bank stabilization through LWD placement O: 29. Add LWD to Shoreline Stabilization on Tacoma/Trimble Management area 11/28/2010 11/28/2010
Tree Stand Thinning P: 53. Removal of Undesired Plant Species 11/28/2010 11/28/2010
Pend Oreille River Shoreline Stabilization Areas Seeded Q: 47. Seed Shoreline Stabilization Site 11/28/2010 11/28/2010
Wetland Shorelines Seeded R: 47. Seed Newly Created Wetland Pond Shorelines 11/16/2010 11/16/2010
Planted Riparian Areas on Enhancement Sites S: 47. Plant Native Trees and Shrubs in the Tacoma/Trimble Management Area 11/01/2010 11/01/2010
Completed Spring and Fall Burns T: 31. Conduct Spring and Fall Controlled Burns in the Tacoma/Trimble Management Area 11/28/2010 11/26/2010
Properties Secured From Trespass U: 26. Secure 18 Properties and Provide Enforcement Management. 02/28/2011 02/22/2011
Maintain access to water control structures. V: 38. Maintain access to water control structures. 09/01/2010 09/01/2010
RM&E Data Used for Future Recommendations W: 162. Analysis of RM&E data to determine management actions 02/28/2011 02/22/2011
Maintained database X: 160. Maintain Database 02/28/2011 01/22/2011
Maintain Established Vegetation Y: 22. Maintain Previously Planted Materials within the Tacoma/Trimble Management Area. 09/28/2010 09/15/2010
Maintain Established Vegetation Z: 22. Maintain Previously Planted Materials within the Idaho Management Area. 09/28/2010 09/28/2010
Management of Vegetation AA: 22. Vegetation Management within Flying Goose Property 08/01/2010 08/01/2010
Fence Maintained AB: 186. Maintain Fence 02/28/2011 02/22/2011
Fence maintained AC: 186. Maintain Fence 02/28/2011 02/22/2011
Water Control Structures Maintained and Functioning AD: 186. Maintain Existing Water Control Structures on Wetland Enhancement Sites. 02/28/2011 02/22/2011
Buildings Maintained AE: 186. Manage and Maintain Facility to Maximal Standards 02/28/2011 02/22/2011
Shoreline Stabilization AF: 186. Maintain Integrity of Shoreline Stabilization Structures 02/28/2011 02/22/2011
Completion of Required Project Reporting to BPA AG: 119. Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies 02/28/2011 02/22/2011
Completed FY10 Annual Report to BPA AH: 132. Annual Report for 2010 Contract Cycle 02/28/2011 02/22/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 3 instances of WE 22 Maintain Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 5 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 31 Conduct Controlled Burn
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 165 Complete Permit Applications and Provide Documentation to Obtain Compliance. 02/09/2007
C 172 Complete hazardous waste assessments as a part of the pre-acquisition process. 02/09/2007
D 172 Complete cultural resource surveys. 02/09/2007
E 172 Complete surveys for properties where boundaries are in question. 02/09/2007
F 172 Conduct appraisals for prospective acquisitions 02/09/2007
G 172 Conduct title search as part of pre-acquisition process. 02/09/2007
H 172 Obtain Legal Description of Acquisitions. 02/09/2007
I 172 Identify Minimum HUs From Land Purchase 02/09/2007
J 172 Land Owner Coordination 02/09/2007
K 122 Review Designs and Details for Habitat Enhancements. 02/09/2007
L 174 Complete Management Plan for Big Meadows Acquisition. 02/09/2007
M 181 Create Wetland Ponds on Tacoma/Trimble Management Area
N 181 Install 3 gate valves in the Tacoma/Trimble Management Area 03/01/2010
O 29 Add LWD to Shoreline Stabilization on Tacoma/Trimble Management area
P 53 Removal of Undesired Plant Species 04/26/2010
Q 47 Seed Shoreline Stabilization Site 02/09/2007
R 47 Seed Newly Created Wetland Pond Shorelines 02/09/2007
S 47 Plant Native Trees and Shrubs in the Tacoma/Trimble Management Area
T 31 Conduct Spring and Fall Controlled Burns in the Tacoma/Trimble Management Area
U 26 Secure 18 Properties and Provide Enforcement Management. 02/09/2007
V 38 Maintain access to water control structures. 03/01/2010
W 162 Analysis of RM&E data to determine management actions 02/09/2007
X 160 Maintain Database 02/09/2007
Y 22 Maintain Previously Planted Materials within the Tacoma/Trimble Management Area. 05/04/2010
Z 22 Maintain Previously Planted Materials within the Idaho Management Area. 02/09/2007
AA 22 Vegetation Management within Flying Goose Property 02/09/2007
AB 186 Maintain Fence 02/09/2007
AC 186 Maintain Fence 02/09/2007
AD 186 Maintain Existing Water Control Structures on Wetland Enhancement Sites. 02/09/2007
AE 186 Manage and Maintain Facility to Maximal Standards 02/09/2007
AF 186 Maintain Integrity of Shoreline Stabilization Structures
AG 119 Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies 02/09/2007
AH 132 Annual Report for 2010 Contract Cycle 02/09/2007