SOW Report
Contract 42025: 1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
Project Number:
Title:
Umatilla Anadromous Fish Habitat-Umatilla Tribe
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
42025
Contract Title:
1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
Contract Continuation:
Previous: Next:
36848: 1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
  • 46159: 1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
Contract Status:
Closed
Contract Description:
Agreement between BPA and CTUIR to provide funds for implementing habitat enhancement actions in the Umatilla River Basin.
Account Type(s):
Expense
Contract Start Date:
02/01/2009
Contract End Date:
01/31/2010
Current Contract Value:
$983,711
Expenditures:
$983,711

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Official acceptance and approval of BA's by applicable compliance representatives B: 165. Prepare Biological Assessments for applicable projects 01/31/2010
Obtain DSL/USACE approval on JPA permits C: 165. Submit JPA to state and federal entities 01/31/2010
Obtain official approval from Tribal & state cultural resource preservation agency representation D: 165. Cultural Resource protection & preservation 09/30/2009 07/28/2009
Active participation with co-managerial interests in the Umatilla Basin E: 189. Coordinate with other entities planning & implementing habitat improvements in the Umatilla Basin 01/31/2010 01/31/2010
Develop and utilize applicable and effective monitoring techniques F: 157. Collect various forms of professional, scientific data for project potential analysis 01/31/2010 01/31/2010
Summarized data in the format of professional scientific reports G: 162. Analyze/interpret scientific data 01/31/2010 01/31/2010
Delivery of engineered implementation designs/drawings with specifications H: 175. Preparation & submittal of engineering designs/specifications for Meacham Creek project 01/31/2010 11/30/2009
Improve riverine process via levee setback on Meacham Creek I: 180. Enhance floodplain connectivity and function via levee setback at Meacham Creek 12/31/2009 12/31/2009
Improve instream habitat conditions on Meacham Creek J: 29. Improve habitat quality and quantity of floodplain habitat features and channel in lower Meacham Cr 01/31/2010
Installation of fence at Cunningham property K: 40. Install riparian fence at West Birch Creek RM 2.7-3.0 and Meacham Creek 03/31/2009 03/31/2009
Vegetative planting in existing and new project areas L: 47. Supplement riparian areas of existing and new projects with additional vegetation 01/31/2010 11/30/2009
Maximize survival of vegetation plantings in CTUIR project areas M: 22. Maintain vegetation plantings at all CTUIR habitat implementation project areas 01/31/2010 11/30/2009
Removal of non-preferred species of vegetative growth from project areas N: 53. Control of noxious weeds in project areas by physical and chemical means 01/31/2010 12/31/2009
Maintaining proper operation of instream habitat structures O: 186. Monitor & troubleshoot issues that interfere w/ proper function of instream improvement structures 01/31/2010 01/31/2010
Maintenance of conservation easements P: 186. Secure & adhere to details of conservation easements assoc. w/ habitat projects 01/31/2010 01/31/2010
Development of additional water sources to supplement the low annual precipitation of 11" Q: 34. Develop additional water sources & strategies to improve survival of riparian vegetation on B&G 01/31/2010 11/30/2009
Utilize area farming practice methods to till established weed areas at the B&G property R: 48. Tillage strategies at B & G project to improve vegetative planting survival of preferred species 01/31/2010 11/30/2009
Produce methods for use as monitoring project effectiveness S: 156. Develop strategic and scientifically accepted monitoring methods for application 01/31/2010 01/31/2010
Summarized data in the format of professional scientific reports T: 174. Produce Umatilla River and Willow Creek watershed habitat assessment plans 01/31/2010
Review and provide technical input on issues that may adversely affect natural resources U: 122. Review and provide technical input on issues and topics that affect the areas natural resource 01/31/2010 01/31/2010
Attach 2007 Progress Report in Pisces V: 132. Submit Annual Progress Report for the FY 2009 period (Feb 2009) to (Jan 2010) 01/31/2010 01/31/2009
2010 draft SOW and accrual reports W: 119. Manage and Administer Project 11/02/2009 11/16/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 22 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 48 Practice No-till and Conservation Tillage Systems
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 48 Practice No-till and Conservation Tillage Systems
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 165 Prepare Biological Assessments for applicable projects 02/09/2007
C 165 Submit JPA to state and federal entities 02/09/2007
D 165 Cultural Resource protection & preservation 02/09/2007
E 189 Coordinate with other entities planning & implementing habitat improvements in the Umatilla Basin 02/09/2007
F 157 Collect various forms of professional, scientific data for project potential analysis 04/23/2009
G 162 Analyze/interpret scientific data 02/09/2007
H 175 Preparation & submittal of engineering designs/specifications for Meacham Creek project 02/09/2007
I 180 Enhance floodplain connectivity and function via levee setback at Meacham Creek 04/23/2009
J 29 Improve habitat quality and quantity of floodplain habitat features and channel in lower Meacham Cr 04/23/2009
K 40 Install riparian fence at West Birch Creek RM 2.7-3.0 and Meacham Creek 08/03/2007
L 47 Supplement riparian areas of existing and new projects with additional vegetation 04/23/2009
M 22 Maintain vegetation plantings at all CTUIR habitat implementation project areas 04/23/2009
N 53 Control of noxious weeds in project areas by physical and chemical means 04/23/2009
O 186 Monitor & troubleshoot issues that interfere w/ proper function of instream improvement structures 08/03/2007
P 186 Secure & adhere to details of conservation easements assoc. w/ habitat projects 08/03/2007
Q 34 Develop additional water sources & strategies to improve survival of riparian vegetation on B&G 08/03/2007
R 48 Tillage strategies at B & G project to improve vegetative planting survival of preferred species 08/03/2007
S 156 Develop strategic and scientifically accepted monitoring methods for application 02/09/2007
T 174 Produce Umatilla River and Willow Creek watershed habitat assessment plans 02/09/2007
U 122 Review and provide technical input on issues and topics that affect the areas natural resource 02/09/2007
V 132 Submit Annual Progress Report for the FY 2009 period (Feb 2009) to (Jan 2010) 02/09/2007
W 119 Manage and Administer Project 02/09/2007