| Mitigation Action Plan for Lyle Falls Fishway |
B: 165. Address Lyle Falls EIS Mitigation Action Measures |
|
09/30/2012 |
09/30/2012 |
| Programmatic/Contractual Requirements - year one |
C: 119. Manage and Administer Klickitat Capital Project |
|
08/31/2010 |
08/31/2010 |
| Public Information & Outreach |
D: 99. Update BPA, NPCC, and YKFP websites w/ Project information |
|
09/30/2012 |
09/30/2012 |
| Lyle Falls Fishway - Step 3 submittals |
E: 170. Lyle Falls Fishway - Step 3 Submittals |
|
08/03/2009 |
10/30/2009 |
| Lyle Falls Fishway Improvement - non-construction elements |
F: 175. Lyle Falls Fishway Final Design - Design Engineers |
|
12/31/2009 |
12/07/2009 |
| Year One Lyle Falls Fishway Construction Management |
G: 100. Year one - Lyle Falls Fishway Contract Administration and Construction Observation |
|
08/31/2011 |
11/01/2010 |
| Lyle Falls Fishway Construction |
H: 184. Year one - Upgrade Lyle Falls Fishway - Construction subcontractor |
|
09/23/2011 |
09/23/2011 |
| Castile Falls Fishway - Step 3 submittals |
I: 170. Castile Falls Monitoring Facility - Step 3 Submittals |
|
07/01/2009 |
10/30/2009 |
| 100 % Design Bid Documents |
J: 175. Castile Falls Monitoring Facility Final Design - Design Engineers |
|
12/15/2009 |
12/15/2009 |
| Castile Falls Fishway Construction Management |
K: 100. Castile Falls Monitoring Facility Contract Administration and Construction Observation |
|
08/17/2011 |
08/17/2011 |
| Castile Falls Monitoring Facility Construction |
L: 70. Castile Falls Monitoring Facility Construction - Construction Subcontractor |
|
01/31/2013 |
01/31/2013 |
| 100 % Design Bid Documents |
M: 175. Klickitat Hatchery Vehicle Bridge and Spur Road Final Design - Design Engineers |
|
06/15/2009 |
07/30/2009 |
| Construction Management - Klickitat Hatchery Bridge & Spur Road |
N: 100. Klickitat Hatchery Bridge & Spur Road Contract Administration and Construction Observation. |
|
02/28/2011 |
10/29/2010 |
| Klickitat Hatchery Bridge and Spur Road Construction - Construction Subcontractor |
O: 38. Klickitat Hatchery Bridge & Spur Road Construction - Construction Subcontractor |
|
02/28/2011 |
01/27/2011 |
| Programmatic/Contractual Requirements |
P: 119. Year 2/3/4 - Manage and Administer Klickitat Capital Project - YN |
|
08/31/2016 |
08/31/2016 |
| Public Information & Outreach |
Q: 161. Year 2/3/4 - Update BPA, NPCC, and YKFP web sites w/ Project information |
|
03/31/2013 |
03/31/2013 |
| Lyle Falls Fishway Construction Management |
R: 100. Year 2/3/4 - Lyle Falls Contr Admin & Constr Observation |
|
09/30/2013 |
12/01/2013 |
| Lyle Falls Fishway Construction - Year two/three |
S: 184. Year Two/Three - Lyle Falls Fishway Construction |
|
09/30/2012 |
09/30/2012 |
| Public Information & Outreach |
U: 99. Year Two/Three - Update BPA, NPCC, and YKFP websites w/ Project information |
|
02/28/2013 |
02/28/2013 |
| Capital Equipment Items Lyle Fall Monitoring Facility |
V: 70. Equipment to be capitalized for Lyle Falls Monitoring Facility |
|
02/28/2013 |
02/28/2013 |
| Ecology Report of Examination for Certificate No. 04802 |
W: 154. Increase and change in point of diversion for reconstructed Lyle Falls Fishway facility |
|
02/10/2012 |
02/10/2012 |
| 3-phase power design, permitting and installation for Lyle Falls Fishway Facility. |
X: 98. 3-phase power design, permitting, and installation for Lyle Falls Fishway Facility |
|
10/31/2011 |
10/31/2011 |
| Purchase/carry Builders Risk Insurance for construction Lyle/Castile Falls Facilities. |
Y: 98. Lyle Falls/Castile Falls Facilities Builders All- Risk Insurance for Construction |
|
10/31/2011 |
10/31/2011 |
| Capital Equipment Items Castile Fall Monitoring Facility |
Z: 70. Equipment to be capitalized for Castile Falls Monitoring Facility |
|
09/30/2012 |
09/30/2012 |
| Revegetate Lyle Falls Project per EIS - Mitigation Action Plan |
AA: 47. Revegetate Lyle Falls Project area post-construction |
|
04/30/2012 |
06/30/2012 |
| Install high speed internet and voice over IP to Lyle Falls Facility. |
AB: 98. Install high speed internet and voice over IP to Lyle Falls Facility. |
|
06/30/2011 |
06/30/2011 |
| Lyle Change Order #1 and #2 |
AC: 98. Change Order at Lyle Falls - Unforseen geotechnical conditions |
|
09/30/2010 |
09/30/2010 |
| Klickitat Hatchery Road Bridge Change Orders |
AD: 98. Change Order at Klickitat Hatchery Road & Br. - Unforeseen underground hydrologic condition |
|
01/31/2011 |
01/31/2011 |
| Engineering services fee schedule |
AE: 98. Engineering Services Change Order |
|
02/28/2011 |
02/28/2011 |
| AIA G701-2001 |
AF: 98. Lyle Falls Change Order 002A Final payment of pre approved Change Order #002 |
|
12/17/2010 |
12/17/2010 |
| AIA G701-2001 |
AG: 98. Lyle Falls Change Order 003A Final payment of pre approved Change Order #003 |
|
12/17/2010 |
12/17/2010 |
| AIA G701-2001 |
AH: 98. Castile Falls Change Orders |
|
02/28/2011 |
02/28/2011 |
| Trailer delivered to Lyle Falls Fishway |
AI: 98. Lyle Falls Workup trailer procurement and delivery |
|
12/07/2011 |
12/13/2011 |
| Lyle Work Station - interior fixtures procurement |
AJ: 98. Lyle Falls Workup trailer interior fixtures (i.e. tanks, tables, electro anesthesia tank) |
|
05/31/2012 |
06/30/2012 |
| AIA G701-2001 |
AK: 98. Lyle Falls Underwater Demolition CO #4 |
|
02/28/2011 |
02/28/2011 |
| AIA G701-2001 |
AL: 98. Lyle Falls Fish Entrance Sill CO #5 |
|
02/28/2011 |
02/28/2011 |
| AIA G701-2001 |
AM: 98. Lyle Falls Weir Reconstruction CO #6 |
|
02/28/2011 |
02/28/2011 |
| Compensation to YN Tribal Fisher |
AN: 98. YN Tribal Fishers Claim Compensation |
|
04/30/2012 |
04/30/2012 |
| Engineering Services Change Order - Hatchery Bridge |
AO: 98. Engineering Services Change Order - Hatchery Bridge |
|
07/31/2010 |
07/31/2010 |
| Construction Management Complete |
AP: 100. Lyle Falls and Castile Falls Contract Administration and Construction Observation. |
|
08/31/2016 |
06/30/2013 |
| Construction Management Complete |
AQ: 100. Lyle Falls and Castile Falls Contract Administration and Construction Observation. |
|
08/31/2016 |
06/30/2013 |
| Lyle & Castile - Advanced Safety Training |
AR: 98. Lyle & Castile - Advanced Safety Training |
|
01/31/2013 |
01/31/2013 |
| Safety and project equipment required to operate Castile Falls and Lyle Fall Facilities. |
AS: 98. Safety and Project Equipment: Castile & Lyle |
|
02/28/2013 |
12/31/2012 |
| Design Changes at Castile and Lyle |
AT: 70. Lyle Falls and Castile Falls - design changes |
|
12/31/2012 |
12/31/2012 |