SOW Report
Contract 46101: 198812025 EXP YKFP MANAGEMENT, DATA, HABITAT
Project Number:
Title:
Yakima River Management & Data -Yakima/Klickitat Fisheries Project (YKFP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
46101
Contract Title:
198812025 EXP YKFP MANAGEMENT, DATA, HABITAT
Contract Continuation:
Previous: Next:
41037: 1988-120-25 EXP YKFP MANAGEMENT, DATA, HABITAT
  • 55125: 1988-120-25 EXP YKFP MANAGEMENT, DATA, HABITAT
Contract Status:
Closed
Contract Description:
YKFP MANAGEMENT, DATA AND HABITAT  (MDH)
BPA Project Number:  1988-120-25
Statement of Work and Budget FY2010-2011

BPA Project Title:  Yakima Fisheries Project Management, Data & Habitat
Contract Number:  ________________
(Replaces Contract Number 41037)
Contract Title:  YKFP Management, Data and Habitat  (MDH)
Performance/Budget Period:  10/01/09 - 09/30/11

This project provides for all YN management and coordination functions associated with the Yakima/Klickitat Fisheries Project (YKFP or Project) in the Yakima Subbasin.  The YKFP was established in a 1994 Memorandum of Agreement with WDFW (project co-manager) to implement and evaluate artificial propagation methods used to restore and rebuild anadromous fish populations in the subbasin.  The YKFP was subsequently expanded to include the Klickitat Subbasin.  However, Klickitat Subbasin management and coordination activities are covered under a separate BPA project, 1988-120-35.

Principal YKFP activities include the use of artificial propagation of juveniles derived from natural origin broodstock to supplement the natural populations of spring Chinook, fall Chinook and coho.  Research, monitoring and evaluation is performed to address, among other issues, (1) the effects of supplementation on the natural populations, (2) the effectiveness of juvenile rearing methods and acclimation in achieving juvenile survival and supplementation objectives, (3) ecological impacts from supplementation, and (4) the development of data to allow adjustments to hatchery and acclimation operations to meet project objectives according to adaptive management principles. Supplementation activities must be coordinated with habitat availability to manage ecological risks and optimize natural production and adult recruitment.  

The YKFP is a complex and comprehensive project that requires significant management and administrative resources. It includes fish production and research facilities and numerous research programs. The Yakama Nation serves as the YKFP “Lead Agency” and is responsible for implementation of all YKFP programs; including managing and directing YKFP project employees, associated project budgets, and ensuring the quality and efficiency of project activities.  

Implementation is coordinated with WDFW, which participates in project planning and performs certain research activities related to ecological interactions, genetics research and analysis, and reproductive success of supplementation fish.   In broad categories, the Yakama Nation is responsible to implement and coordinate:

1. Project planning activities, including those pertaining to facility construction and modifications;
2. Operation and maintenance activities at all YKFP facilities;
3. Project research activities including production of scientific reports and publications;
4. Design and development of a centralized database for Project use and dissemination to others;
5. Habitat restoration and protection projects within the target ecosystem;
6. Development and submittal of funding proposals that ensure consistency with the 2008 MOA between the Three Treaty Tribes and the FCRPS Action Agencies,  and sufficient funding for YKFP operations

To meet its lead agency responsibilities, the Yakama Nation employs approximately 99 people, including managers, scientists, technicians, fish culturists, laborers and office support personnel. Project management personnel work out of the YKFP’s Central Office in Toppenish, Washington, the Nelson Springs Office and Research Facility northeast of Yakima, Washington and a satellite office in Ellensburg, Washington.  The Wahkiacus Field Office houses scientists and technicians engaged in monitoring and evaluation, habitat management and data management activities for the Klickitat Subbasin.  The YKFP also operates passage and hatchery facilities in the Klickitat.  Part of YKFP management requires coordination of Klickitat and Yakima research and data management activities.

This Management Data and Habitat contract funds the activities of YKFP executive management, project coordination and administrative staff necessary for discharging these responsibilities, including administrative support for day to day YKFP operations in the Yakima Subbasin.  Management services funded by this contract include oversight and support of the following YKFP programs:

1. O&M Lower Yakima River Supplementation & Research Complex,
2. O&M Upper Yakima River Supplementation & Research Complex
3. Yakima Basin Monitoring & Evaluation
4. Klickitat Basin Monitoring and Evaluation,
5. Klickitat Watershed Enhancement Project
6. Design and Construction
7. Klickitat Management, Data and Habitat project.

The success of all YKFP projects depends on the administrative structure funding by this contract. The Yakama Nation's management and coordination responsibilities (identified herein) are expected to continue through and beyond the contract performance period. This umbrella management approach was developed through discussions with BPA and the Northwest Power and Conservation Council. WDFW participates in YKFP management through BPA Project 1995-064-25, YKFP Policy/Technical Involvement/Planning.

This contract has eight primary objectives:

1. Provide comprehensive management oversight of the implementation of YKFP activities.
2. Support YN policy development related to YKFP activities in the Yakima and Klickitat Subbasins.
3. Coordinate and/or perform all tasks necessary to the development of project planning documents.
4. Provide required administrative support for Project operations, including financial management and accountability and realty services coordination and technical review.
5. Design, develop and manage YKFP's Data and Information System.
6. Schedule and conduct the YKFP's Science & Management Conference (incorporates Project Annual Review), which includes presentations by project scientists and provides for peer review of research activities.
7. Participate in watershed planning, protection and restoration initiatives by various agencies, groups and committees.
8. Coordinate, plan and implement habitat protection and restoration projects in the Yakima Subbasin.

This is a two year contract and budget.  Budget estimates from the Habitat construction activities are based on YKFP Management's experience in budgeting for previous work done at other locations.  
Most activities involve Year 1 as construction design activities and Year 2 as project implementation.  Contract Amendments and budget modifications may be required as construction development occurs.
Account Type(s):
Expense
Contract Start Date:
10/01/2009
Contract End Date:
09/30/2011
Current Contract Value:
$3,323,623
Expenditures:
$3,323,623

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Rachel Castilleja Yakama Confederated Tribes Yes Administrative Contact casr@yakamafish-nsn.gov (509) 865-5121x6337
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Henry Fraser Yakama Confederated Tribes No Technical Contact hankfraser@fairpoint.net (509) 933-1210
Mary Haight Bonneville Power Administration Yes COR mthaight@bpa.gov (503) 230-3112
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Rosemary Mazaika Bonneville Power Administration No Interested Party rxmazaika@bpa.gov (503) 230-5869
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Scott Nicolai Yakama Confederated Tribes Yes Technical Contact nics@yakamafish-nsn.gov
Phil Rigdon Yakama Confederated Tribes No Supervisor prigdon@yakama.com (509) 865-5121x4655
Mel Sampson Yakama Confederated Tribes Yes Contract Manager mel@yakama.com (509) 865-5121x6303
Adrienne Wilson Yakama Confederated Tribes Yes Administrative Contact Adrienne_Wilson@Yakama.com (509) 865-5121x6306


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Data sharing / internet access to project data A: 161. Yakama Nation YKFP Data and Information Dissemination YR 2 09/30/2011 09/30/2011
Produce Design for Road 1900 Relocation B: 175. Produce Design for Road 1900 Relocation Yr 1 06/01/2011 11/15/2010
Produce Restoration Designs for Lower Swauk Creek C: 175. Produce Restoration Designs for Lower Swauk Creek Yr 1 09/30/2010 09/30/2010
Science and Management Conference (or Project Annual Review) D: 99. Yakama Nation YKFP Scientific & Mgmt Conf (PAR) YR 2 09/30/2011 09/30/2011
Management and maintenance of project data systems E: 160. Yakama Nation YKFP Data and Information Management YR 2 09/30/2011 09/30/2011
Updated Information System Management Plan F: 174. Maintain Yakama Nation YKFP Information System Management Planning YR 2 09/30/2011 09/30/2011
Project database maintenance, security, and quality control G: 159. Yakama Nation YKFP Data Acquisition YR 2 09/30/2011 09/30/2011
Quarterly status reports H: 141. Yakama Nation YKFP Project Status Report YR 2 09/30/2011 09/30/2011
Technical review I: 122. YN YKFP Habitat, Water and Passage Technical Review Activities YR 2 09/30/2011 09/30/2011
Prepare Annual Reports J: 132. Yakama Nation YKFP Project Annual Report YR 2 09/30/2011
All contract related documentation submitted by due dates. K: 119. Yakama Nation YKFP Project Management and Implementation Year 2 09/30/2011 09/30/2011
Environmental compliance documentation and support L: 165. Participate in ESA/NEPA Compliance for Yakima Basin Monitoring, Evaluation and Fisheries Manag YR 2 09/30/2011 09/30/2011
Produce Fish Passage Designs M: 175. Produce Fish Passage Designs 08/13/2010 09/30/2010
Middle Swauk Creek Restoration Yr 1 N: 175. Middle Swauk Creek Restoration Cost-Share 09/30/2010 09/30/2010
Project proposals for cost-share O: 114. Identify and seek funding for habitat, passage, and instream flow projects YR 2 09/30/2011 09/30/2011
Scientific publications P: 183. Yakama Nation YKFP Produce Scientific Publications YR 2 09/30/2011 09/30/2011
Produce Habitat Management Plans Q: 174. Produce Habitat Management Plans YR 2 09/30/2011 06/30/2011
Scientific publications R: 183. Yakama Nation YKFP Produce Scientific Publications 09/30/2010 09/30/2010
Project proposals for cost-share S: 114. Identify and seek funding for habitat, passage, and instream flow projects 09/30/2010 09/30/2010
Science and Management Conference (or Project Annual Review) U: 99. Yakama Nation YKFP Scientific & Mgmt Conf (PAR) 09/30/2010 09/30/2010
Environmental compliance documentation and support V: 165. Participate in ESA/NEPA Compliance for Yakima Basin Monitoring, Evaluation and Fisheries Manag 09/30/2010 09/30/2010
All contract related documentation submitted by due dates. W: 119. Yakama Nation YKFP Project Management and Implementation 09/30/2010 09/30/2010
Prepare Annual Reports X: 132. Yakama Nation YKFP Project Annual Report 03/31/2010 06/30/2010
Technical review Y: 122. YN YKFP Habitat, Water and Passage Technical Review Activities 09/30/2010 09/30/2010
Coordination Z: 189. Yakama Nation YKFP Policy Coordination and Analysis 09/30/2010 09/30/2010
Coordination AA: 189. Yakama Nation YKFP Policy Coordination and Analysis YR 2 09/30/2011 09/30/2011
Data sharing / internet access to project data AB: 161. Yakama Nation YKFP Data and Information Dissemination 09/30/2010 09/30/2010
Updated Information System Management Plan AC: 174. Maintain Yakama Nation YKFP Information System Management Planning 09/30/2010 09/30/2010
Quarterly status reports AD: 141. Yakama Nation YKFP Project Status Report 06/15/2011 12/15/2010
Project database maintenance, security, and quality control AE: 159. Yakama Nation YKFP Data Acquisition 09/30/2010 09/30/2010
Management and maintenance of project data systems AF: 160. Yakama Nation YKFP Data and Information Management 09/30/2010 09/30/2010
Riparian restoration at the Habitat Properties AG: 47. Install native vegetation at the Habitat Parcels YR 2 09/30/2011 09/30/2011
Place Large Wood Instream AH: 29. Place Large Wood at many locations in the Yakima Watershed YR 2 09/30/2011 09/30/2011
Finish Swauk Creek Install of Fish Passage structures AI: 184. Fish Passage Construction- Swauk Creek YR 2 (CANCELLED-See BM 29) 09/30/2011 10/31/2010
Finish South Naches Side Channel Install of Fish Passage structures AJ: 184. Fish Passage Construction- South Naches Side Channel YR 2 09/30/2011
Finish Reecer Creek Install of Fish Passage structures AK: 184. Fish Passage Construction- Reecer Creek YR 2 09/30/2011
Lower Swauk Creek Restoration Yr 2 AL: 180. Lower Swauk Restoration YR2 09/30/2011
Middle Swauk Stream Habitat Restoration AM: 29. Middle Swauk Creek - YR 2 (this replaces BH-184) 09/30/2011 09/30/2011
Purchase Materials for Taneum Canal Fish Passage Project AN: 98. Cost-Share Materials for Taneum Canal Fish Passage Project 01/31/2011 01/31/2011
Place Large Wood Instream - Year 2 AO: 29. Enhance in channel habitat after assessments are complete YR 2 09/30/2011 09/30/2011
Remove undesirable vegetation at the Harris habitat parcel AP: 53. Remove vegetation at the Harris habitat property YR 2 09/30/2011 09/30/2011
Remove undesirable vegetation at the Henne habitat parcel AQ: 53. Remove vegetation at the Henne habitat property YR 2 09/30/2011 09/30/2011
Remove undesirable vegetation at the Fortune habitat parcel AR: 53. Remove vegetation at the Fortune habitat property YR 2 09/30/2011 09/30/2011
Remove undesirable vegetation at the Holmes habitat parcel AS: 53. Remove vegetation at the Holmes habitat property YR 2 09/30/2011 09/30/2011
Finish Upper Taneum Creek Restoration Activities AT: 180. Implement Restoration Designs for Upper Taneum Creek Yr 2 09/30/2011
Maintain vegetation AU: 22. Maintain vegetation at the Harris and Holmes habitat properties YR 2 09/30/2011 09/30/2011
Remove undesirable vegetation at the Dixon habitat parcel AV: 53. Remove vegetation at Dixon property YR 2 09/30/2011 09/30/2011
Install Fish Passage structures AW: 184. Fish Passage Construction- South Naches Side Channel YR 1 09/30/2011
Install Fish Passage structures AX: 184. Fish Passage Construction- Reecer Creek YR 1 09/30/2011
Road 1900 Relocation and Habitat Restoration AY: 33. Implement Design for Road 1900 Relocation YR2 09/30/2011
Remove undesirable vegetation at the Fortune habitat parcel AZ: 53. Remove vegetation at the Fortune habitat property 09/30/2010 09/30/2010
Remove undesirable vegetation at the Henne habitat parcel BA: 53. Remove vegetation at the Henne habitat property 09/30/2010 09/30/2010
Remove undesirable vegetation at the Harris habitat parcel BB: 53. Remove vegetation at the Harris habitat property 09/30/2010 09/30/2010
Riparian restoration at the Habitat Properties BC: 47. Install native vegetation at the Habitat Parcels 09/30/2010 09/30/2010
Manage Habitat Parcels BD: 186. Manage Habitat Parcels 09/30/2010 09/30/2010
Reecer Creek Floodplain Restoration Cost-Share BE: 180. Reecer Creek Floodplain Restoration Cost-Share 09/30/2011 09/30/2011
Place Large Wood Instream BF: 29. Place Large Wood at many locations in the Yakima Watershed 09/30/2010 09/30/2010
Obtain LIDAR maps in priority stream reaches BG: 115. Obtain LIDAR Maps in priority stream Reaches 09/30/2010 09/30/2010
Install Fish Passage structures BH: 184. Fish Passage Construction- Swauk Creek YR 1 09/30/2010 09/30/2010
Manage Habitat Parcels BI: 186. Manage Habitat Parcels YR 2 09/30/2011 09/30/2011
Finalize & Implement Taneum Creek Restoration Designs BJ: 180. Finalize & Implement Restoration Designs for Upper Taneum Creek Yr 1 09/30/2010 09/30/2010
Remove undesirable vegetation at the Holmes habitat parcel BK: 53. Remove vegetation at the Holmes habitat property 09/30/2010 09/30/2010
Removal of vegetation at the Dixon Habitat Property BL: 53. Remove vegetation at Dixon property 09/30/2010 09/30/2010
Replace existing fence & add new fence BM: 40. Replace existing fence at Harris Habitat Parcel 09/30/2010 09/30/2010
Install Wold Ditch Fish Structure BN: 184. Fish Passage Construction - Wold Ditch 09/15/2011 09/22/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 174 Produce Plan
  • 2 instances of WE 183 Produce Journal Article
  • 2 instances of WE 159 Transfer/Consolidate Regionally Standardized Data
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 98 Other
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 184 Install Fish Passage Structure
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 184 Install Fish Passage Structure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 174 Produce Plan
  • 2 instances of WE 183 Produce Journal Article
  • 2 instances of WE 159 Transfer/Consolidate Regionally Standardized Data
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 4 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 10 instances of WE 53 Remove Vegetation
  • 4 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 6 instances of WE 184 Install Fish Passage Structure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 174 Produce Plan
  • 4 instances of WE 175 Produce Design
  • 2 instances of WE 183 Produce Journal Article
  • 2 instances of WE 159 Transfer/Consolidate Regionally Standardized Data
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 161 Yakama Nation YKFP Data and Information Dissemination YR 2 02/09/2007
B 175 Produce Design for Road 1900 Relocation Yr 1 02/09/2007
C 175 Produce Restoration Designs for Lower Swauk Creek Yr 1 10/01/2009
D 99 Yakama Nation YKFP Scientific & Mgmt Conf (PAR) YR 2 10/01/2009
E 160 Yakama Nation YKFP Data and Information Management YR 2 02/09/2007
F 174 Maintain Yakama Nation YKFP Information System Management Planning YR 2 10/01/2009
G 159 Yakama Nation YKFP Data Acquisition YR 2 02/09/2007
H 141 Yakama Nation YKFP Project Status Report YR 2 02/09/2007
I 122 YN YKFP Habitat, Water and Passage Technical Review Activities YR 2 02/09/2007
J 132 Yakama Nation YKFP Project Annual Report YR 2 02/09/2007
K 119 Yakama Nation YKFP Project Management and Implementation Year 2 02/09/2007
L 165 Participate in ESA/NEPA Compliance for Yakima Basin Monitoring, Evaluation and Fisheries Manag YR 2 02/09/2007
M 175 Produce Fish Passage Designs 02/09/2007
N 175 Middle Swauk Creek Restoration Cost-Share 10/01/2009
O 114 Identify and seek funding for habitat, passage, and instream flow projects YR 2 02/09/2007
P 183 Yakama Nation YKFP Produce Scientific Publications YR 2 02/09/2007
Q 174 Produce Habitat Management Plans YR 2 02/09/2007
R 183 Yakama Nation YKFP Produce Scientific Publications 02/09/2007
S 114 Identify and seek funding for habitat, passage, and instream flow projects 02/09/2007
T 185 Periodic Status Reports for BPA 02/09/2007
U 99 Yakama Nation YKFP Scientific & Mgmt Conf (PAR) 02/09/2007
V 165 Participate in ESA/NEPA Compliance for Yakima Basin Monitoring, Evaluation and Fisheries Manag 02/09/2007
W 119 Yakama Nation YKFP Project Management and Implementation 02/09/2007
X 132 Yakama Nation YKFP Project Annual Report 02/09/2007
Y 122 YN YKFP Habitat, Water and Passage Technical Review Activities 02/09/2007
Z 189 Yakama Nation YKFP Policy Coordination and Analysis 02/09/2007
AA 189 Yakama Nation YKFP Policy Coordination and Analysis YR 2 02/09/2007
AB 161 Yakama Nation YKFP Data and Information Dissemination 02/09/2007
AC 174 Maintain Yakama Nation YKFP Information System Management Planning 02/09/2007
AD 141 Yakama Nation YKFP Project Status Report 02/09/2007
AE 159 Yakama Nation YKFP Data Acquisition 02/09/2007
AF 160 Yakama Nation YKFP Data and Information Management 02/09/2007
AG 47 Install native vegetation at the Habitat Parcels YR 2 08/30/2011
AH 29 Place Large Wood at many locations in the Yakima Watershed YR 2 07/29/2011
AI 184 Fish Passage Construction- Swauk Creek YR 2 (CANCELLED-See BM 29)
AJ 184 Fish Passage Construction- South Naches Side Channel YR 2 10/01/2009
AK 184 Fish Passage Construction- Reecer Creek YR 2 10/01/2009
AL 180 Lower Swauk Restoration YR2 10/01/2009
AM 29 Middle Swauk Creek - YR 2 (this replaces BH-184) 10/01/2009
AN 98 Cost-Share Materials for Taneum Canal Fish Passage Project 10/31/2011
AO 29 Enhance in channel habitat after assessments are complete YR 2 02/16/2011
AP 53 Remove vegetation at the Harris habitat property YR 2 08/30/2011
AQ 53 Remove vegetation at the Henne habitat property YR 2 08/30/2011
AR 53 Remove vegetation at the Fortune habitat property YR 2 08/30/2011
AS 53 Remove vegetation at the Holmes habitat property YR 2 08/30/2011
AT 180 Implement Restoration Designs for Upper Taneum Creek Yr 2 10/01/2009
AU 22 Maintain vegetation at the Harris and Holmes habitat properties YR 2 08/30/2011
AV 53 Remove vegetation at Dixon property YR 2 08/30/2011
AW 184 Fish Passage Construction- South Naches Side Channel YR 1 10/24/2011
AX 184 Fish Passage Construction- Reecer Creek YR 1 10/01/2009
AY 33 Implement Design for Road 1900 Relocation YR2 10/01/2009
AZ 53 Remove vegetation at the Fortune habitat property 08/06/2010
BA 53 Remove vegetation at the Henne habitat property 08/06/2010
BB 53 Remove vegetation at the Harris habitat property 08/06/2010
BC 47 Install native vegetation at the Habitat Parcels 08/06/2010
BD 186 Manage Habitat Parcels 02/09/2007
BE 180 Reecer Creek Floodplain Restoration Cost-Share 10/01/2009
BF 29 Place Large Wood at many locations in the Yakima Watershed 08/06/2010
BG 115 Obtain LIDAR Maps in priority stream Reaches 10/01/2009
BH 184 Fish Passage Construction- Swauk Creek YR 1 09/13/2010
BI 186 Manage Habitat Parcels YR 2 02/09/2007
BJ 180 Finalize & Implement Restoration Designs for Upper Taneum Creek Yr 1 10/01/2009
BK 53 Remove vegetation at the Holmes habitat property 08/06/2010
BL 53 Remove vegetation at Dixon property 08/06/2010
BM 40 Replace existing fence at Harris Habitat Parcel 08/06/2010
BN 184 Fish Passage Construction - Wold Ditch 10/01/2009