Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 48121: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHEDS HABITAT-MOA
Project Number:
Title:
Lower Clearwater and Potlatch Watersheds Habitat Improvements
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
48121
Contract Title:
2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHEDS HABITAT-MOA
Contract Continuation:
Previous: Next:
43283: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHEDS HABITAT-MOA
  • 53815: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED REST-MOA
Contract Status:
Closed
Contract Description:
This contract continues restoration planning and implementation efforts initiated under Project #2008-604-00/Contract #43283.

This contract supplements work undertaken by BPA and Latah Soil and Water Conservation District (Latah SWCD) through Project #2002-061-00 and associated contracts.  Consistent with Project #2002-061-00, this contract will undertake practices designed to effectively implement the Latah SWCD's Potlatch River Watershed Management Plan.  The 377,776-acre Potlatch River watershed is located in north-central Idaho and is the largest tributary in the lower Clearwater River.  The Potlatch River is critical to wild Snake River steelhead.

Supported by the Accord between BPA and the State of Idaho, this contract seeks to complement the work currently on-going by the Latah SWCD to restore wild Snake River Steelhead to a robust, self-sustaining population within the Potlatch River through coordinated implementation of best management practices on private agricultural and range lands, coordination of interagency watershed planning efforts, continuation of watershed monitoring and development of outreach programs to landowners and agricultural producers.  Latah SWCD habitat restoration efforts are outlined in the Potlatch River Watershed Management Plan.      

This proposal is consistent with the NWPCC Fish and Wildlife Program’s goal to develop habitat-based programs designed to rebuild healthy, naturally producing fish and wildlife populations by protecting, mitigating, and restoring habitats. This project is consistent with the objectives and strategies of the Clearwater Subbasin Management Plan.

In an effort to lower stream temperatures, increase summer flows, decrease surface and channel erosion (and associated nutrient loading), and increase riparian habitat complexities, this contract will focus on erosion control and riparian restoration on private agricultural, forest, and range lands through the implementation of livestock exclusion fencing, native plantings of riparian areas, passage barrier removal, and protection of functional riparian areas.  Priority tributaries for restoration work within this contract include:  Big Bear Creek, Little Bear Creek, Corral Creek, and East Fork Potlatch River.

Latah SWCD staff will continue implementing riparian restoration and related projects throughout the Potlatch River watershed.  In addition, project staff will continue developing conservation plans with private landowners and seeking additional BPA and non-BPA funds to implement best management practices designed for the improvement of steelhead spawning and rearing habitat.  Project staff will also continue coordination efforts with other watershed planning efforts throughout the region to improve fish habitat.
Account Type(s):
Expense
Contract Start Date:
07/01/2010
Contract End Date:
06/30/2011
Current Contract Value:
$230,287
Expenditures:
$230,287

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR A: 119. Manage and Administer BPA Contracts 04/30/2011 06/30/2011
Environmental Compliance & Consultation Review B: 165. Verify all NEPA Environmental Compliance has been completed 09/30/2010 09/30/2010
Provide general outreach to 100 landowners and direct contact with 20 landowners. C: 99. Solicit Landowner Participation 05/31/2011 05/31/2011
Undertaken initial site reviews on 10 potential restoration sites. D: 114. Initial Site Review of Potential Restoration Sites 06/30/2011 06/30/2011
Develop 3 landowner initial conservation concept plans for project implementation. E: 174. Develop Initial Conservation Concept Plans 05/31/2011 03/31/2011
Provide Design and/or Specifications for 1 project F: 175. Provide Design and/or Specifications 05/31/2011 05/31/2011
Evaluate plantings, replant, and perform light maintenance as required G: 22. Replant and Maintain Riparian Plantings - Potlatch River 06/30/2011 06/30/2011
Complete installation of approximately 10,560 feet of exclusion fencing. H: 40. Livestock Exclusion Fencing - Corral Creek/IDL Property (Grazing Allotment) 06/30/2011 06/30/2011
Provide Design and/or Specifications - East Fork Potlatch River I: 175. Provide Design and Specifications - East Fork Potlatch River 05/31/2011 05/31/2011
Develop Conservation Plans and Funding Agreements - East Fork Potlatch River J: 174. Develop Final Conservation Plans and Funding Agreements - East Fork Potlatch River 05/31/2011
Provide Design and Specifications - Troy Dam K: 175. Provide Design and Specifications - Troy Dam 05/31/2011 05/31/2011
Develop Final Conservation Plans and Funding Agreements - Troy Dam L: 174. Develop Final Conservation Plans and Funding Agreements - Troy Dam 06/30/2011
Big Bear Riparian Restoration - Agreements and Contracts M: 175. Provide Design and Specifications - Big Bear Riparian Restoration 05/01/2011 05/01/2011
Develop Final Conservation Plans, Funding Agreement, and Contracts - Big Bear Riparian Restoration N: 174. Develop Final Conservation Plans, Funding Agreement, and Contracts - Big Bear Riparian Restoration 05/31/2011
Attach Progress Report in Pisces O: 132. Submit Progress Report for the period (July 2010) to (June 2011) 06/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 40 Install Fence
  • 4 instances of WE 174 Produce Plan
  • 4 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer BPA Contracts 07/01/2010
B 165 Verify all NEPA Environmental Compliance has been completed 07/01/2010
C 99 Solicit Landowner Participation 07/01/2010
D 114 Initial Site Review of Potential Restoration Sites 07/01/2010
E 174 Develop Initial Conservation Concept Plans 07/01/2010
F 175 Provide Design and/or Specifications 07/01/2010
G 22 Replant and Maintain Riparian Plantings - Potlatch River 07/01/2010
H 40 Livestock Exclusion Fencing - Corral Creek/IDL Property (Grazing Allotment) 07/01/2010
I 175 Provide Design and Specifications - East Fork Potlatch River 07/01/2010
J 174 Develop Final Conservation Plans and Funding Agreements - East Fork Potlatch River 07/01/2010
K 175 Provide Design and Specifications - Troy Dam 07/01/2010
L 174 Develop Final Conservation Plans and Funding Agreements - Troy Dam 07/01/2010
M 175 Provide Design and Specifications - Big Bear Riparian Restoration 07/01/2010
N 174 Develop Final Conservation Plans, Funding Agreement, and Contracts - Big Bear Riparian Restoration 07/01/2010
O 132 Submit Progress Report for the period (July 2010) to (June 2011) 07/01/2010
P 185 Periodic Status Reports for BPA 07/01/2010