SOW Report
Contract 53815: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED REST-MOA
Project Number:
Title:
Lower Clearwater and Potlatch Watersheds Habitat Improvements
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
53815
Contract Title:
2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED REST-MOA
Contract Continuation:
Previous: Next:
48121: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHEDS HABITAT-MOA
  • 61571: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED-ACCORD LATAH
Contract Status:
Closed
Contract Description:
This contract continues restoration planning and implementation efforts initiated under Project #2008-604-00/Contract #43283.

This contract supplements work undertaken by BPA and Latah Soil and Water Conservation District (Latah SWCD) through Project #2002-061-00 and associated contracts.  Consistent with Project #2002-061-00, this contract will undertake practices designed to effectively implement the Latah SWCD's Potlatch River Watershed Management Plan.  The 377,776-acre Potlatch River watershed is located in north-central Idaho and is the largest tributary in the lower Clearwater River.  The Potlatch River is critical to wild Snake River steelhead.

Supported by the Accord between BPA and the State of Idaho, this contract seeks to complement the work currently on-going by the Latah SWCD to restore wild Snake River Steelhead to a robust, self-sustaining population within the Potlatch River through coordinated implementation of best management practices on private agricultural and range lands, coordination of interagency watershed planning efforts, continuation of watershed monitoring and development of outreach programs to landowners and agricultural producers.  Latah SWCD habitat restoration efforts are outlined in the Potlatch River Watershed Management Plan.      

This proposal is consistent with the NWPCC Fish and Wildlife Program’s goal to develop habitat-based programs designed to rebuild healthy, naturally producing fish and wildlife populations by protecting, mitigating, and restoring habitats. This project is consistent with the objectives and strategies of the Clearwater Subbasin Management Plan.

In an effort to lower stream temperatures, increase summer flows, decrease surface and channel erosion (and associated nutrient loading), and increase riparian habitat complexities, this contract will focus on erosion control and riparian restoration on private agricultural, forest, and range lands through the implementation of livestock exclusion fencing, native plantings of riparian areas, passage barrier removal, and protection of functional riparian areas.  Priority tributaries for restoration work within this contract include:  Big Bear Creek, Little Bear Creek, Corral Creek, and East Fork Potlatch River.

Latah SWCD staff will continue implementing riparian restoration and related projects throughout the Potlatch River watershed.  In addition, project staff will continue developing conservation plans with private landowners and seeking additional BPA and non-BPA funds to implement best management practices designed for the improvement of steelhead spawning and rearing habitat.  Project staff will also continue coordination efforts with other watershed planning efforts throughout the region to improve fish habitat.
Account Type(s):
Expense
Contract Start Date:
07/01/2011
Contract End Date:
06/30/2013
Current Contract Value:
$486,193
Expenditures:
$486,193

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Funding Package - Submit draft to COTR A: 119. Manage and Administer BPA Contracts 04/30/2013 04/30/2013
Environmental Compliance & Consultation Review B: 165. Verify all NEPA Environmental Compliance has been completed 06/30/2013 06/30/2013
Attach Progress Report in Pisces C: 132. Submit Progress Report for the period (July 2011) to (June 2013) 06/30/2013 06/30/2013
Provide general outreach to 100 landowners and direct contact with 30 landowners. D: 99. Outreach and Education/Solicit Landowner Participation 05/31/2013 05/31/2013
Undertaken initial site reviews on 15 potential restoration sites. E: 114. Identify and Review Potential Restoration Sites 06/30/2013 06/30/2013
Develop 6 landowner initial conservation plans for project implementation. F: 174. Develop Initial Conservation Plans 05/31/2013 05/31/2013
Develop Final Engineering Design, Conservation Plans, and Funding Agreements - Dutch Flat Dam G: 174. Develop Final Engineering Design, Conservation Plans, and Funding Agreements - Dutch Flat Dam 05/15/2013 05/15/2013
Dutch Flat Dam Removed as Passage Barrier H: 85. Passage Barrier Removal - Dutch Flat Dam 06/30/2013
Corral Creek Meadow Restoration - Racetrack I: 30. Corral Creek Meadow Restoration - Racetrack 06/30/2013
Big Bear Creek Riparian Restoration/IDL J: 30. Riparian Restoration - Big Bear Creek/IDL 06/30/2013
Bear Creek Riparian Restoration Initiated K: 30. Riparian Restoration - Big Bear Creek/Swanstrom 06/30/2013 06/30/2013
Evaluate plantings, replant, and perform light maintenance as required L: 22. Replant and Maintain Riparian Plantings - Potlatch River 06/30/2013 06/30/2013
Restoration Proposal Development for State Endowment Lands M: 114. Project Identification and Proposal Development - Idaho Department of Lands 06/30/2013 06/30/2013
Develop Conservation Plans and Funding Agreements - East Fork Potlatch River N: 174. Develop Final Conservation Plans and Funding Agreements - East Fork Potlatch River 05/31/2013 05/31/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 3 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 2 instances of WE 114 Identify and Select Projects
  • 3 instances of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer BPA Contracts 07/01/2011
B 165 Verify all NEPA Environmental Compliance has been completed 07/01/2011
C 132 Submit Progress Report for the period (July 2011) to (June 2013) 07/01/2011
D 99 Outreach and Education/Solicit Landowner Participation 07/01/2011
E 114 Identify and Review Potential Restoration Sites 07/01/2011
F 174 Develop Initial Conservation Plans 07/01/2011
G 174 Develop Final Engineering Design, Conservation Plans, and Funding Agreements - Dutch Flat Dam 07/01/2011
H 85 Passage Barrier Removal - Dutch Flat Dam 09/10/2013
I 30 Corral Creek Meadow Restoration - Racetrack 06/30/2013
J 30 Riparian Restoration - Big Bear Creek/IDL 07/01/2011
K 30 Riparian Restoration - Big Bear Creek/Swanstrom 06/30/2013
L 22 Replant and Maintain Riparian Plantings - Potlatch River 07/01/2011
M 114 Project Identification and Proposal Development - Idaho Department of Lands 07/01/2011
N 174 Develop Final Conservation Plans and Funding Agreements - East Fork Potlatch River 07/01/2011
O 185 Periodic Status Reports for BPA 07/01/2011