Contract 49234: 2007-268-00 EXP RESTORE 12 MILE REACH OF UPPER SALMON RIVER
Project Number:
Title:
Idaho Watershed Habitat Restoration-Custer District
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
49234
Contract Title:
2007-268-00 EXP RESTORE 12 MILE REACH OF UPPER SALMON RIVER
Contract Continuation:
Previous: Next:
n/a
  • 54224: 2007-268-00 EXP RESTORE 12 MILE REACH OF UPPER SALMON RIVER
Contract Status:
Closed
Contract Description:
Due to funding issues, the original Restore 12-mile Reach Upper Salmon has been put on hold indefinitely.  However, the restoration work proposed under that project (to have been performed by the Corps and reimbursed at 35% by the District) will now be conducted by the District (under subcontract) as a part of this existing habitat restoration project.  Work under this contract will cover the development of engineering designs and specifications as well as cost estimates that will be used for the awarding of the construction work (to be done under a separate contract under this project).

Additionally, the District will continue to monitor usage of the Stark easement for compliance with the Terms & Conditions of the acquisition.
Account Type(s):
Expense
Contract Start Date:
09/01/2010
Contract End Date:
08/31/2011
Current Contract Value:
$68,571
Expenditures:
$68,571

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

Description: Cost-share project with IDFG and PCSRF to reconnect a side-channel of the upper Salmon River near Challis.

Contract(s):

49234

Dimensions: 990 x 1206


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Visitation Log A: 26. Investigate Trespass on Easement Property 08/31/2011 08/11/2011
BPA required administrative documents B: 119. Manage and Administer Projects 05/31/2011 07/29/2011
Final Habitat Restoration Specification for Site 3 D: 175. Develop engineering designs for Site 3 (subcontractor TBD) 06/15/2011
Write Conservation Plan including grazing plan for Salmon River/Slough Fence project E: 174. Conservation Planning Provided by NRCS 08/29/2011 08/22/2011
Obtain required permits (404, etc.) allowing restoration activities F: 165. Permits, etc. needed for restoration activities 08/01/2011
Install 6500 feet of jack post and pole fence along a Slough and the Salmon River G: 40. Install Fence on Main Stem Salmon River 08/31/2011 08/29/2011
Reconnected side-channel of the Salmon River near Challis, ID I: 30. Cost-share to IDFG for 12-mile side channel reconnect near Hannah Slough 08/15/2011 08/15/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 174 Produce Plan
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 174 Produce Plan
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 26 Investigate Trespass on Easement Property 09/01/2010
B 119 Manage and Administer Projects 09/01/2010
C 132 Submit Annual Report for the period (October 2009 thru September 2010) 09/01/2010
D 175 Develop engineering designs for Site 3 (subcontractor TBD) 09/01/2010
E 174 Conservation Planning Provided by NRCS 09/01/2010
F 165 Permits, etc. needed for restoration activities 09/01/2010
G 40 Install Fence on Main Stem Salmon River 02/14/2011
H 185 Periodic Status Reports for BPA 09/01/2010
I 30 Cost-share to IDFG for 12-mile side channel reconnect near Hannah Slough 02/14/2011