| Funding Package - Submit draft to COTR |
B: 119. Admin oversight for Cap Activities |
|
07/01/2011 |
09/30/2011 |
| 2-year Report submitted |
C: 132. Submit 2-year report for September 2008 through August 2010 |
|
10/31/2012 |
10/31/2012 |
| Environmental Compliance complete |
D: 165. Environmental Compliance Documentation for all cap actions |
|
01/31/2011 |
06/04/2011 |
| Trumbull Recharge Project Constructed |
E: 98. Trumbull Recharge Site |
|
10/31/2012 |
10/31/2012 |
| Anspach Recharge Project Constructed |
F: 98. Anspach Recharge Project |
|
10/31/2012 |
10/31/2012 |
| On farm pond constructed on Morris property |
G: 151. Morris Bulge |
|
08/19/2011 |
11/07/2011 |
| Flow measuring device installed at Spence Ditch |
H: 148. Spence Ditch Measurement Devices |
|
02/29/2012 |
03/24/2012 |
| Flow measuring device installed at Zell Ditch |
I: 148. Zell Ditch Measurement Devices |
|
10/31/2012 |
10/31/2012 |
| Flow measuring device installed at Perkins Ditch |
J: 148. Perkins Ditch Measurement Devices |
|
10/31/2012 |
10/31/2012 |
| West Little Walla Walla North Piped |
K: 149. West Little Walla Walla Project - North Piping |
|
10/31/2012 |
10/31/2012 |
| West Little Walla Walla South Piped |
L: 149. Cancelled: West Little Walla Walla Project - South Piping |
|
10/31/2012 |
|
| West Little Walla Walla Diversions Installed |
M: 84. West Little Walla Walla Project - Diversion Installations |
|
10/28/2011 |
10/13/2011 |
| Young Weir Installed |
N: 84. Young Weir & Pond Project |
|
01/31/2012 |
12/30/2011 |
| Boyd Weir Replacement and Pond Enlargement |
O: 84. Boyd Replace Weir and Enlarge Pond |
|
12/31/2011 |
12/30/2011 |
| Brooks Weir Installed |
P: 84. Brooks Weir |
|
08/30/2011 |
04/30/2011 |
| Underwood Weir Installed |
Q: 84. Underwood Weir |
|
08/30/2011 |
12/30/2011 |
| Negotiate In-stream Water Right Transactions |
R: 154. In-stream Water Right Transactions |
|
10/31/2012 |
10/31/2012 |
| Designs for above projects complete |
S: 175. Produce Designs for BPA Projects |
|
03/31/2012 |
03/31/2012 |
| Pre-Acquisition Activities Completed |
T: 172. Pre-acquisition activities for purchase or easement of recharge site |
|
10/31/2012 |
|
| Drain Fields for Recharge Expansion Installed |
U: 98. Complete Hudson Bay Recharge Expansion |
|
08/31/2011 |
06/30/2011 |
| Recharge Design |
V: 175. Recharge Design |
|
08/31/2012 |
08/31/2012 |
| Frog Designs |
W: 175. Frog Design |
|
01/31/2012 |
01/31/2012 |
| Flow measuring device installed |
X: 148. Little Walla Walla Measuring Devices |
|
10/31/2012 |
10/31/2012 |
| Funding Package - Submit draft to COTR |
Y: 119. Year 2 Admin oversight for Cap Activities |
|
08/31/2012 |
08/31/2012 |
| Environmental Compliance complete |
Z: 165. Environmental Compliance Documentation for all cap actions |
|
03/31/2012 |
03/31/2012 |
| 7730 feet of pipeline installed during this phase |
AA: 149. Hyline - Install Final phase of pipeline |
|
10/31/2012 |
10/31/2012 |
| Replaced, Automated and tested Frog Headgates |
AB: 84. Frog Diversion Headgate and Automation |
|
10/31/2012 |
10/31/2012 |
| Zell Ditch Diversion |
AC: 84. Zell Ditch Diversion |
|
10/31/2012 |
10/31/2012 |
| White Ditch Piping Project Designs |
AD: 175. Produce Final Designs for White Ditch Piping |
|
10/31/2012 |
10/31/2012 |
| 1-year Report submitted |
AE: 132. Submit 1-year report for September 2010 through August 2011 |
|
10/31/2012 |
10/31/2012 |
| Stillman Ditch Piping |
AF: 149. Stillman Ditch Piping |
|
10/31/2012 |
10/31/2012 |
| Finalized Smith Sill Engineered Drawings |
AG: 175. Smith Fish Passage Barrier Modification Engineered Designs |
|
09/10/2012 |
09/10/2012 |
| Construction Management Complete |
AH: 100. Project Oversight for Smith Sill on mainstem Walla Walla River |
|
10/31/2012 |
10/01/2012 |