Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 50037: 1989-035-00 EXP UMATILLA HATCHERY O&M
Project Number:
Title:
Umatilla Hatchery Operations and Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
50037
Contract Title:
1989-035-00 EXP UMATILLA HATCHERY O&M
Contract Continuation:
Previous: Next:
44449: 1989-035-00 EXP UMATILLA HATCHERY O&M
  • 55040: 1989-035-00 EXP UMATILLA HATCHERY O&M
Contract Status:
Closed
Contract Description:
The Northwest Power Planning Council (Council) adopted the Master Plan in 1990 as part of its Fish and Wildlife Program. The Oregon Department of Fish and Wildlife (ODFW), Confederated Tribes of the Umatilla Indian Reservation (CTUIR), and others federal partners designed the Umatilla Hatchery as an experimental tool to achieve adult returns goals (hatchery-origin and natural-origin).  The adult goals include:
·Steelhead (5,500)
·Spring Chinook (8,000)
·Fall Chinook-upriver bright (12,000)
·Coho (6,000)

Maintaining artificial propagation, at its current level, was a recommended action from the Umatilla/Willow Subbasin Planning Team to Northwest Power and Conversation Council to achieve anadromous adult return goals (memo September 27, 2005).  

Fish production has changed in the program due to Umatilla water flow limitations and adaptive management.  Generally, these changes have resulted in reduced production at Umatilla Hatchery and additional fish production in other Columbia Basin hatcheries. Current fish production for the Umatilla Hatchery include:
·Summer Steelhead (150,000 smolts)
·Spring Chinook (810,000 smolts)
·Fall Chinook (600,000 sub-yearling smolts)

Other fish produced and transferred to the Umatilla Subbasin include:
·Fall Chinook (480,000 yearling smolts) from Bonneville Hatchery (John Day mitigation)
·Coho (1,000,000 smolts) from Cascade Hatchery (Mitchell Act)

This proposal would fund all Umatilla Hatchery fish production, hatchery maintenance, and fish transfers into the Umatilla River Subbasin.
Account Type(s):
Expense
Contract Start Date:
10/01/2010
Contract End Date:
09/30/2011
Current Contract Value:
$1,067,360
Expenditures:
$1,067,360

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Assure environmental compliance B: 165. Assurance of Environmental Compliance 10/01/2010 10/01/2010
Steelhead production for release in 2011 C: 176. Produced Steelhead (BY10) 05/31/2011 05/31/2011
Steelhead Production for release in 2012 D: 176. Produce Steelhead (BY11) 09/30/2011 09/30/2011
Spring Chinook production for release in 2010-11 E: 176. Produced Spring Chinook (BY09) 04/30/2011 04/30/2011
Spring Chinook harvest production (BY) for release in 2011-12 F: 176. Produce Harvest group Spring Chinook (BY10) 09/30/2011 09/30/2011
Spring Chinook conservation production (BY10) for release in 2012 G: 176. Produce Conservation group Spring Chinook (BY10) 09/30/2011 09/30/2011
Fall Chinook harvest production for release in 2012 H: 176. Produced Umatilla River fall Chinook eyed eggs (BY10) for harvest 03/10/2011 03/10/2011
Fall Chinook Conservation production for release in 2012 I: 176. Produce Umatilla River fall Chinook eyed eggs (BY10) for conservation 04/15/2011 04/15/2011
Fall Chinook production for release in 2011 J: 176. Produce fall Chinook sub-yearlings (BY10) 05/31/2011 05/31/2011
Fish Transfers K: 66. Fish Transport 05/31/2011 05/31/2011
Hatchery Maintenance L: 61. Maintain Umatilla Hatchery 09/30/2011 09/30/2011
2012 Annual Operation Plan (AOP) M: 174. Produce 2012 Annual Operating Plan 08/31/2011 09/16/2011
Monthly Status Reports Complete N: 141. Status Reporting 09/30/2011 09/30/2011
2010-2011 Annual Report (FY11) O: 132. Annual Report 09/30/2011 09/30/2011
Scope of work/budget/property inventory/FY12 year end accruals P: 119. Manage and Administer Projects 09/30/2011 09/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 3 instances of WE 176 Produce Hatchery Fish
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 3 instances of WE 176 Produce Hatchery Fish
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2010
B 165 Assurance of Environmental Compliance 10/01/2010
C 176 Produced Steelhead (BY10) 10/01/2010
D 176 Produce Steelhead (BY11) 10/01/2010
E 176 Produced Spring Chinook (BY09) 10/01/2010
F 176 Produce Harvest group Spring Chinook (BY10) 10/01/2010
G 176 Produce Conservation group Spring Chinook (BY10) 10/01/2010
H 176 Produced Umatilla River fall Chinook eyed eggs (BY10) for harvest 10/01/2010
I 176 Produce Umatilla River fall Chinook eyed eggs (BY10) for conservation 10/01/2010
J 176 Produce fall Chinook sub-yearlings (BY10) 10/01/2010
K 66 Fish Transport 10/01/2010
L 61 Maintain Umatilla Hatchery 10/01/2010
M 174 Produce 2012 Annual Operating Plan 10/01/2010
N 141 Status Reporting 10/01/2010
O 132 Annual Report 10/01/2010
P 119 Manage and Administer Projects 10/01/2010