Contract 50087: 199802100 EXP HOOD RIVER FISH HABITAT
Project Number:
Title:
Hood River Fish Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
50087
Contract Title:
199802100 EXP HOOD RIVER FISH HABITAT
Contract Continuation:
Previous: Next:
44523: 199802100 EXP HOOD RIVER FISH HABITAT
  • 54380: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Status:
Closed
Contract Description:
ADMINISTRATIVE SUMMARY
The Confederated Tribes of the Warm Springs Reservation of Oregon
Hood River Production Program
6030 Dee Highway
Parkdale, Oregon 97041
Fisheries Program Manager:  Brad Houslet (541) 553-2039
Fiscal Officer: Arthur Mitchell (541) 553-3219
Hood River Production Program Coordinator:  Chris Brun (541) 806-0293
Technical Contact:  Joe McCanna (541) 352-9326

FISCAL YEAR 2011

OBJECTIVE 1.  Provide coordination of all activities, administrative oversight, project planning and implementation activities.

OBJECTIVE 2.  Coordinate and implement Hood River Watershed  Action Plan.

OBJECTIVE 3.  Conduct project effectiveness monitoring to determine extent of  water quality improvement in Neal Creek resulting from completion of the East Fork Irrigation Central Canal project.

OBJECTIVE 4.  Utilize POCIS / SPMD sampling methods to conduct baseline pesticide monitoring in the Hood River subbasin.

OBJECTIVE 5. Conduct Level II stream surveys in Hood River basin.

OBJECTIVE 6.  Acquire logs for instream large wood addition projects.

OBJECTIVE 7.  Add large wood to McGee Creek.

OBJECTIVE 8. Consolidate Hood River watershed restoration information.

OBJECTIVE 9. Construct livestock exclusion fence along Teiman Creek and maintain existing fences where needed.

OBJECTIVE 10. Partner with Columbia Gorge Growers to plant spray buffer vegetation along selected stream reaches.

OBJECTIVE: 11 Provide cost share to Middle Fork Irrigation District to implement Middle Fork IFIM flow study.
Account Type(s):
Expense
Contract Start Date:
10/01/2010
Contract End Date:
09/30/2011
Current Contract Value:
$334,610
Expenditures:
$334,610

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
FY 2010 Annual Progress Report complete B: 132. Prepare and submit annual report for FY10 work 03/31/2011 03/31/2011
Project administration requirements completed C: 119. Manage Project 09/30/2011 09/30/2011
Data on Neal Creek water quality D: 157. Monitor water quality in Neal Creek. 09/30/2011 09/30/2011
Consolidated habitat restoration data. E: 157. Consolidate basinwide habitat inventories and data. 09/30/2011 09/30/2011
Baseline and Trend Pesticide Monitoring in The Hood River Subbasin. F: 157. Pesticide monitoring in the Hood River basin 09/30/2011 09/30/2011
Hood River Watershed Group support G: 114. Provide implementation support 09/30/2011 09/30/2011
Place large wood in McGee Creek. H: 29. Place large wood along a 1.3 miles of McGee Creek. 09/09/2011 09/02/2011
Acquire logs for out year fish habitat projects. I: 29. Acquire fish habitat logs. 09/30/2011 09/30/2011
200' livestock exclusion fence and a water crossing constructed along Teiman Cr. J: 40. Install riparian fence along Teiman Cr. 09/02/2011 09/02/2011
Riparian fences maintained. K: 186. Maintain riparian fences 09/09/2011 09/09/2011
2,000 riparian shrubs planted along Evans and Neal Creeks. L: 47. Plant riparian vegetation to reduce orchard spray drift from entering Neal and Evans Creeks. 09/30/2011 09/30/2011
Middle Fork Hood River IFIM Study M: 115. Conduct instream flow assesement for Middle Fork 09/30/2011 09/30/2011
Level II stream surveys completed. N: 115. Conduct stream habitat surveys in West Fork watershed. 09/30/2011 09/30/2011
All work complies with environmental regulations O: 165. Work with BPA on environmental compliance requirements 09/30/2011 09/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Deschutes River Summer/Fall ESU
  • 1 instance of WE 47 Plant Vegetation
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2010
B 132 Prepare and submit annual report for FY10 work 10/01/2010
C 119 Manage Project 10/01/2010
D 157 Monitor water quality in Neal Creek. 10/01/2010
E 157 Consolidate basinwide habitat inventories and data. 10/01/2010
F 157 Pesticide monitoring in the Hood River basin 10/01/2010
G 114 Provide implementation support 10/01/2010
H 29 Place large wood along a 1.3 miles of McGee Creek. 11/10/2010
I 29 Acquire fish habitat logs. 11/10/2010
J 40 Install riparian fence along Teiman Cr. 10/01/2010
K 186 Maintain riparian fences 10/01/2010
L 47 Plant riparian vegetation to reduce orchard spray drift from entering Neal and Evans Creeks. 10/01/2010
M 115 Conduct instream flow assesement for Middle Fork 10/01/2010
N 115 Conduct stream habitat surveys in West Fork watershed. 10/01/2010
O 165 Work with BPA on environmental compliance requirements 10/01/2010