Contract 51522: 2009-026-00 CAP MILL CREEK PASSAGE IMPROVEMENTS
Project Number:
Title:
Umatilla Tribe Ceded Area Juvenile & Adult Fish Passage Improvement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
51522
Contract Title:
2009-026-00 CAP MILL CREEK PASSAGE IMPROVEMENTS
Contract Continuation:
Previous: Next:
n/a
  • 58747: 2009-026-00 CAP MILL CREEK REACH 6 IMPROVEMENTS
Contract Status:
Closed
Contract Description:
This contract begins on-the-ground work to improve fish passage within a six mile reach of the Mill Creek Flood Control Channel. Within the project reach, there is a 2.5 mile section of concrete lined channel (flume section). The remaining sections (above and below the flume section) are open bottomed channel with channel-spanning stabilizers (sills) for energy dissipation.

To date, a passage assessment identified the location and type of fish passage barriers, and passage designs have been developed to the 30% level for the entire project reach. A 1:8 scale physical model was constructed to test the performance of passage designs in the flume section. The model study will be completed by the end of 2010.

This contract provides match funds to two SRFB grants for two construction projects that will occur at three sites. The Sills Passage project will install passage structures on four of the channel spanning stabilizers at Tausick Way. The Flume Transitions project will reconstruct fishways at each end of the concrete flume section (at Roosevelt St and 9th Ave).
Account Type(s):
Capital
Contract Start Date:
02/15/2011
Contract End Date:
03/31/2012
Current Contract Value:
$138,037
Expenditures:
$138,037

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

Description: The four sills shown are the four that will receive passage corrections. Flow shown is 4.5 cfs.

Contract(s):

51522

Dimensions: 1600 x 1200

Description: This is the uppermost of the four sills that will receive passage corrections. The drop over the sill is 1.7 feet. This was referred to as Sill #1 in construction.

Contract(s):

51522

Dimensions: 1600 x 1200

Description: Uppermost transition between the concrete channel and the open bottom channel.

Contract(s):

51522

Dimensions: 1600 x 1200

Description: The lower transition between the concrete channel and open bottom channel. View is looking downstream.

Contract(s):

51522

Dimensions: 1600 x 1200

Description: Upper most of four sill notches at Tausick Way

Contract(s):

51522

Dimensions: 2576 x 1932

Description: Second of four sills at Tausick Way

Contract(s):

51522

Dimensions: 2576 x 1932

Description: Upstream view of project reach

Contract(s):

51522

Dimensions: 2576 x 1932

Description: Low flow channel looking upstream. The notched weir is in the background.

Contract(s):

51522

Dimensions: 2576 x 1932

Description: New roughened concrete and resting pool, prior to re-watering.

Contract(s):

51522

Dimensions: 2576 x 1932


Full Name Organization Write Permission Contact Role Email Work Phone
Dawn Boorse Bonneville Power Administration Yes Env. Compliance Lead drboorse@bpa.gov (503) 230-5678
Brian Burns Tri-State Steelheaders Yes Contract Manager brian.burns@tristatesteelheaders.com (509) 529-3543
Gary James Umatilla Confederated Tribes (CTUIR) No Supervisor garyjames@ctuir.org (541) 429-7285
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Michelle O'Malley Bonneville Power Administration Yes COR mmomalley@bpa.gov (503) 230-5138
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Jed Volkman Umatilla Confederated Tribes (CTUIR) Yes Interested Party jedvolkman@ctuir.org (541) 429-7539


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental compliance clearance received B: 165. Environmental compliance for fish passage structures 08/01/2011 09/30/2011
Public meetings C: 99. Public meetings 08/30/2011 07/07/2011
Final designs and specs D: 175. Final plans and specs 07/01/2011 07/14/2011
Post Construction Report attached in Pisces E: 132. Submit Progress Report for the period Oct 2010 to Apr 2011 01/31/2012 03/31/2012
Install fishways F: 184. New fishway at Roosevelt St 11/15/2011 10/31/2011
Fishway at 9th Ave G: 184. New fishway at 9th Ave 11/15/2011 10/31/2011
Construct low flow notches in four sills H: 85. Add low flow notches to sills 11/15/2011 10/31/2011
Add resting pools I: 29. Add resting pools 11/15/2011 10/31/2011
Final billing resolved J: 119. Manage project 03/31/2012 12/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 01/01/2011
B 165 Environmental compliance for fish passage structures 01/01/2011
C 99 Public meetings 01/01/2011
D 175 Final plans and specs 01/01/2011
E 132 Submit Progress Report for the period Oct 2010 to Apr 2011 01/01/2011
F 184 New fishway at Roosevelt St 08/05/2011
G 184 New fishway at 9th Ave 08/05/2011
H 85 Add low flow notches to sills 08/05/2011
I 29 Add resting pools 08/05/2011
J 119 Manage project 01/01/2011