Contract 51571: 2002-059-00 EXP YANKEE FORK SALMON RIVER RESTORATION
Project Number:
Title:
Yankee Fork Salmon River Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
51571
Contract Title:
2002-059-00 EXP YANKEE FORK SALMON RIVER RESTORATION
Contract Continuation:
Previous: Next:
45892: 2002-059-00 EXP YANKEE FORK SALMON RIVER RESTORATION
  • 56041: 2002-059-00 EXP YANKEE FORK SALMON RIVER RESTORATION
Contract Status:
Closed
Contract Description:
The Yankee Fork Restoration Project contract for 2011 will continue to capture baseline water quality data within the Yankee Fork Salmon River drainage. This includes using long term deployment of multi-parameter water quality monitors (Sondes) at five sites: Flat Rock, Bonanza Bridge, Jordan Creek Bridge, Custer Bridge and West Fork Yankee Fork to collect continuous water quality measures including: ph, conductivity, temperature, turbidity, and dissolved oxygen. Data collection begins March and continues through November, and is dependent upon the stream conditions and storm events.  Temperature data will continue to be collected on the Yankee Fork and references reaches within the Upper Salmon River Basin.  The project installs air and water thermal data loggers beginning in March and retrieves them in November as conditions permit.  Within the mainstem Yankee Fork, the project will be collecting data throughout the year, commencing in February 2011 and continuing through January 2012. Additionally, the project will continue to collect discharges measurements and stage readings (manually and digitally, with the use of pressure transducers).  The pressure transducers will gather continuous water levels throughout the field season. For the 2011 season, there will be additional installation sites for these devices on, upper, mid and lower Yankee Fork locations, including the West Fork Yankee Fork and Jordan Creek tributaries. The project will continue to complete Rosgen surveying at each of our sites on the YFSR and references reaches.  This methodology of data collection will assist us to understand how the undisturbed system is functioning and quantified results can be applied to YFSR impacted reaches.  To assist with monitoring the flows throughout the hydrologic cycle on the Yankee Fork Salmon River, the project will contract with USGS to install a permanent gauging station in the lower portion of the drainage.  This process will begin with a sub-contract, site location, necessary permits required for installation, and implementation and future maintenance of gauging station.
Additionally, the project will begin a narrative to complete other restoration actions within the Yankee Fork Salmon River, outside the dredge sections.  The project is currently working with the private landowners to acquire an agreement, but this may take some time to accomplish. Consequently the project is looking to complete other implementation actions throughout the YFSR. This narrative will be submitted to and approved by the ISRP prior to any implementation efforts.
Account Type(s):
Expense
Contract Start Date:
02/01/2011
Contract End Date:
01/31/2012
Current Contract Value:
$317,134
Expenditures:
$317,134

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Mickey Carter Bonneville Power Administration No Interested Party macarter@bpa.gov (503) 230-5885
Chad Colter Shoshone-Bannock Tribes No Supervisor ccolter@sbtribes.com (208) 239-4553
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Evelyn Galloway Shoshone-Bannock Tribes Yes Technical Contact egalloway@sbtribes.com (208) 239-4570
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Shannell Ward Shoshone-Bannock Tribes No Contract Manager shannell.ward@sbtribes.com (208) 478-3821
Dawn Williams Shoshone-Bannock Tribes No Interested Party dwilliams@sbtribes.com (208) 478-3927


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
approval from BPA B: 165. Environmental compliance to install pressure transducers/monitoring equipment 08/31/2011 02/01/2011
Summary of meeting notes and an access/easement agreement with Simplot C: 191. Meetings and Input from YFSR tech team and stakeholders & Access Agreement from Simplot 01/31/2012 01/06/2011
Confirm installation D: 148. Install pressure transducers 04/30/2011 04/11/2011
profile for each site E: 157. Rosgen Habitat Survey 01/31/2012
YFSR Water Quality report F: 157. Collect Water Quality Data 01/31/2012 01/18/2012
annual report G: 162. Analyze Water Quality 01/31/2012
report tables and hydro-graphs (summery) within the annual report H: 162. Analyze Pressure transducers data 01/31/2012
YFSR Habitat inventory report I: 162. Analyze Interpret and report habitat inventory 01/31/2012
tabled water quality data J: 161. Disseminate water quality 01/31/2012 01/30/2012
Develop hydro-graphs K: 161. Disseminate all pressure transducer data 12/30/2011 01/31/2012
habitat site profiles L: 161. Disseminate habitat inventory to interested agencies 01/31/2012
Attach Progress Report in Pisces M: 132. Submit Progress Report for the period (Feb 2011 to Jan 2012) 01/31/2012
Provide accrual information to BPA N: 119. Routine administration of contract 07/01/2011 09/05/2011
confirmation of Installed gauging station O: 148. Gauging station on YFSR 11/01/2011 10/11/2011
Yankee Fork outreach video P: 99. Yankee Fork outreach video 09/01/2011 09/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 3 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 148 Install Flow Measuring Device
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 3 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 148 Install Flow Measuring Device

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/01/2011
B 165 Environmental compliance to install pressure transducers/monitoring equipment 02/01/2011
C 191 Meetings and Input from YFSR tech team and stakeholders & Access Agreement from Simplot 02/01/2011
D 148 Install pressure transducers 02/01/2011
E 157 Rosgen Habitat Survey 02/01/2011
F 157 Collect Water Quality Data 02/01/2011
G 162 Analyze Water Quality 02/01/2011
H 162 Analyze Pressure transducers data 02/01/2011
I 162 Analyze Interpret and report habitat inventory 02/01/2011
J 161 Disseminate water quality 02/01/2011
K 161 Disseminate all pressure transducer data 02/01/2011
L 161 Disseminate habitat inventory to interested agencies 02/01/2011
M 132 Submit Progress Report for the period (Feb 2011 to Jan 2012) 02/01/2011
N 119 Routine administration of contract 02/01/2011
O 148 Gauging station on YFSR 07/07/2011
P 99 Yankee Fork outreach video 02/01/2011