Contract 52092: 2001-027-00 EXP WESTERN POND TURTLE RECOVERY IN COL. R. GORGE
Project Number:
Title:
Western Pond Turtle Recovery
Stage:
Closed
Area:
Province Subbasin %
Columbia Gorge Columbia Gorge 100.00%
Contract Number:
52092
Contract Title:
2001-027-00 EXP WESTERN POND TURTLE RECOVERY IN COL. R. GORGE
Contract Continuation:
Previous: Next:
46394: 2001-027-00 EXP WESTERN POND TURTLE RECOVERY
Contract Status:
History
Contract Description:
The goal of WDFW's western pond turtle recovery program is to establish four self-sustaining populations of western pond turtles in the Columbia River Gorge recovery zone.

Project Manager - District Wildlife Biologist:  David P. Anderson (509) 395-2232
Project Manager – Endangered Species Section Manager: Harriet Allen (360) 902-2694
Regional Program Manager – Sandra Jonker: (360) 906-6722
WDFW Contracts – Janice Jackson: (360) 902-2444
Account Type(s):
Expense
Contract Start Date:
03/01/2011
Contract End Date:
03/15/2012
Current Contract Value:
$90,504
Expenditures:
$90,504

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Project management activities complete B: 119. Manage Project 03/15/2012 03/15/2012
Environmental compliance requirements complete. C: 165. Work with BPA on environmental compliance needs 02/29/2012 02/29/2012
Head start field activities and data analysis complete D: 157. Headstart field efforts and data collection 02/15/2012 02/15/2012
Head start turtle activities complete E: 98. Headstart program at Zoos 02/29/2012 02/29/2012
Development of western pond turtle database F: 160. Continue mark recapture analysis and program development 02/29/2012 02/29/2012
Improve western pond turtle nesting habitat G: 53. Enhance upland habitat for western pond turtle nesting 10/31/2011 12/30/2011
Reduce non-native bullfrog populations H: 190. Predator control - Bullfrog removal at select ponds 08/15/2011 08/15/2011
Attach Final Progress Report in Pisces I: 132. Submit Progress Report for calendar year 2010 02/15/2012 02/15/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 98 Other
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2011
B 119 Manage Project 03/01/2011
C 165 Work with BPA on environmental compliance needs 03/01/2011
D 157 Headstart field efforts and data collection 01/04/2011
E 98 Headstart program at Zoos 01/04/2011
F 160 Continue mark recapture analysis and program development 03/01/2011
G 53 Enhance upland habitat for western pond turtle nesting 01/04/2011
H 190 Predator control - Bullfrog removal at select ponds 01/04/2011
I 132 Submit Progress Report for calendar year 2010 03/01/2011