| Province | Subbasin | % |
|---|---|---|
| Columbia Gorge | Fifteenmile | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Israel Duran | Bonneville Power Administration | Yes | Env. Compliance Lead | induran@bpa.gov | (503) 230-3967 |
| Derrek Faber | Oregon Department of Fish and Wildlife | Yes | Contract Manager | derrek.m.faber@state.or.us | (541) 296-3023x221 |
| Richard Golden Jr | Bonneville Power Administration | Yes | COR | rlgolden@bpa.gov | (503) 230-5119 |
| Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
| Jerilyn Irvine | Oregon Department of Fish and Wildlife | No | Administrative Contact | jerilyn.irvine@state.or.us | (503) 947-6137 |
| David Roberts | Bonneville Power Administration | Yes | F&W Approver | daroberts@bpa.gov | (503) 230-4511 |
| James Ruzycki | Oregon Department of Fish and Wildlife | Yes | Supervisor | james.r.ruzycki@odfw.oregon.gov | (541) 962-3731 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| All permits in place | A: 165. Complete the Permitting Process Required to Operate Adult and Juvenile Steelhead Migrant Traps | 12/31/2012 | 12/31/2012 | |
| PIT antenna array installation | C: 70. Install PIT tag arrays | 01/31/2013 | 12/31/2012 | |
| PIT antenna array installation (CANCELLED) | D: 70. Install PIT tag arrays (CANCELLED) | 01/31/2013 | 12/31/2012 | |
| Install adult monitoring weir and trap. | E: 70. Install weir and adult monitoring components | 01/25/2012 | 01/09/2012 | |
| Relocate PIT monitoring equipment upstream. | F: 70. Relocate PIT antennas to confluence of Fifteenmile/Eightmile Cks. | 01/25/2012 | 01/25/2012 | |
| Equipment Mobilized/De-Mobilized | G: 70. Install and remove screw trap | 12/31/2012 | 12/31/2012 | |
| PIT tagged juvenile steelhead | H: 158. PIT tag juvenile steelhead | 01/31/2013 | 12/31/2012 | |
| Smolt abundance and smolt-to-adult-return (SAR) | I: 157. SAR and Migrant Abundance | 08/15/2012 | 08/15/2012 | |
| Collect adult steelhead data, monitor environmental conditions | J: 157. Adult Escapement and Distribution | 06/30/2012 | 06/30/2012 | |
| Adult abundance and survival | K: 162. Calculate Adult/Juvenile metrics | 08/15/2012 | 08/15/2012 | |
| Professional Presentation of Results | L: 161. Presentation of results at regional and professional meetings | 01/31/2013 | 01/31/2013 | |
| Complete annual reports | M: 132. Produce Annual Reports for 2010/11 and 2011/12 trapping seasons | 01/31/2013 | 01/31/2013 | |
| Funding Package - Submit draft to COTR | N: 119. Contract renewal | 10/31/2012 | 10/31/2012 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Complete the Permitting Process Required to Operate Adult and Juvenile Steelhead Migrant Traps | 08/16/2011 | ||||||
| B | 185 | Periodic Status Reports for BPA | 08/16/2011 | ||||||
| C | 70 | Install PIT tag arrays | 08/16/2011 | ||||||
| D | 70 | Install PIT tag arrays (CANCELLED) | 08/16/2011 | ||||||
| E | 70 | Install weir and adult monitoring components | 10/30/2012 | ||||||
| F | 70 | Relocate PIT antennas to confluence of Fifteenmile/Eightmile Cks. | 08/16/2011 | ||||||
| G | 70 | Install and remove screw trap | 08/16/2011 | ||||||
| H | 158 | PIT tag juvenile steelhead | 10/30/2012 | ||||||
| I | 157 | SAR and Migrant Abundance | 10/30/2012 | ||||||
| J | 157 | Adult Escapement and Distribution | 10/30/2012 | ||||||
| K | 162 | Calculate Adult/Juvenile metrics | 08/16/2011 | ||||||
| L | 161 | Presentation of results at regional and professional meetings | 08/16/2011 | ||||||
| M | 132 | Produce Annual Reports for 2010/11 and 2011/12 trapping seasons | 08/16/2011 | ||||||
| N | 119 | Contract renewal | 08/16/2011 |