Contract 54450: 1994-050-00 EXP SALMON RIVER HABITAT ENHANCEMENT
Project Number:
Title:
Salmon River Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
54450
Contract Title:
1994-050-00 EXP SALMON RIVER HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
49384: 1994-050-00 EXP SALMON RIVER HABITAT ENHANCEMENT
  • 58504: 1994-050-00 EXP SALMON RIVER HABITAT ENHANCE
Contract Status:
Closed
Contract Description:
The Salmon River Habitat Enhancement Project will continue to implement habitat restoration projects within the Salmon Subbasin where human and environmental impacts have impaired mainstem passage, harvest rates, predation, impacts from hatchery fish, blocked habitat, spawning and rearing systems.  Some monitoring will include thermal regimes, and distribution of anadromous fish (redd counts).  The project will continue to work with cooperating agencies utilizing database, sharing information, monitoring activities on public and private lands, and coordinating future habitat projects implemented by both SBT- ESA Habitat and S.R.H.E.  The project will provide public information to the Shoshone Bannock Tribes of activities conducted by the SBT- Fish & Wildlife projects and work with neighboring schools such as the SBT- High School and Universities to help educate the youth and provide awareness of hunting and fishing rights.
Account Type(s):
Expense
Contract Start Date:
09/01/2011
Contract End Date:
08/31/2012
Current Contract Value:
$225,657
Expenditures:
$225,657

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Kermit Bacon Shoshone-Bannock Tribes Yes Technical Contact kbacon@sbtribes.com (208) 239-4556
Chad Colter Shoshone-Bannock Tribes No Supervisor ccolter@sbtribes.com (208) 239-4553
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Israel Duran Bonneville Power Administration No Env. Compliance Lead induran@bpa.gov (503) 230-3967
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Sammy Matsaw Shoshone-Bannock Tribes Yes Technical Contact smatsaw@sbtribes.com (208) 239-4550
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Shannell Ward Shoshone-Bannock Tribes No Technical Contact shannell.ward@sbtribes.com (208) 478-3821
Dawn Williams Shoshone-Bannock Tribes No Interested Party dwilliams@sbtribes.com (208) 478-3927


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All EC documents and permits B: 165. Provide all EC documentation to BPA 08/31/2012 08/31/2012
Programmatic and Contractual Requirements C: 119. Manage Habitat Program 06/30/2012 06/29/2012
Select and Solicit Habitat Projects in the Upper Salmon Subbasin D: 114. Identify, Asses, Prioritize and Select Habitat Projects 08/31/2012 08/31/2012
Review technical details and reports E: 122. Review Technical details 08/31/2012 08/31/2012
Attach Progress Report in Pisces F: 132. Submit Progress Report for the period (Sept 2010) to (Aug 2011) 08/31/2012
Panther Creek Exclosure Fence: Rooker Basin G: 40. Panther Creek Exclosure Fence: Rooker Basin 08/31/2012
Lower Big Flats Exclosure Fence H: 40. Lower Big Flats Exclosure Fence 08/31/2012 11/18/2011
Kenney Creek Exclosure I: 40. Kenney Creek Exclosure Fence 08/31/2012 09/30/2011
Hayden Creek Exclosure J: 40. Hayden Creek Exclosure Fence 08/31/2012 05/20/2012
Pole Creek Exclosure K: 40. Pole Creek Exclosure Fence 08/31/2012
Install exclosure fence L: 40. Tower Creek Exclosure Fence 06/29/2012 06/15/2012
R1/R4 Inventory for the Panther Creek instream restoration M: 115. Panther Creek Instream Restoration: R1/R4 Inventory 08/31/2012 08/31/2012
Install exclosure fence N: 40. Carmen Creek Exclosure Fence: Jackson's 08/31/2012 06/22/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 40 Install Fence
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 6 instances of WE 40 Install Fence
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 122 Provide Technical Review and Recommendation
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 7 instances of WE 40 Install Fence
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 122 Provide Technical Review and Recommendation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 09/01/2011
B 165 Provide all EC documentation to BPA 09/01/2011
C 119 Manage Habitat Program 09/01/2011
D 114 Identify, Asses, Prioritize and Select Habitat Projects 09/01/2011
E 122 Review Technical details 09/01/2011
F 132 Submit Progress Report for the period (Sept 2010) to (Aug 2011) 09/01/2011
G 40 Panther Creek Exclosure Fence: Rooker Basin 09/01/2011
H 40 Lower Big Flats Exclosure Fence 09/01/2011
I 40 Kenney Creek Exclosure Fence 09/01/2011
J 40 Hayden Creek Exclosure Fence 09/01/2011
K 40 Pole Creek Exclosure Fence 09/01/2011
L 40 Tower Creek Exclosure Fence 09/01/2011
M 115 Panther Creek Instream Restoration: R1/R4 Inventory 09/01/2011
N 40 Carmen Creek Exclosure Fence: Jackson's 09/01/2011