Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 54705: 1992-061-06 EXP ALBENI FALLS WL COUER D'ALENE
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Coeur D'Alene Tribe
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
54705
Contract Title:
1992-061-06 EXP ALBENI FALLS WL COUER D'ALENE
Contract Continuation:
Previous: Next:
49932: 1992-061-06 EXP ALBENI FALLS WL COUER D'ALENE
  • 59160: 1992-061-06 EXP ALBENI FALLS WL COEUR D'ALENE
Contract Status:
Closed
Contract Description:
Tribes and Agencies that implement the mitigation for Albeni Falls dam due to the construction and inundation are: Idaho Department of Fish and Game, the Kalispel Tribe, the Coeur D'Alene Tribe, the Kootenai Tribe of Idaho and the U. S. Army Corps of Engineers. Once the loss assessments were completed, these agencies and tribes worked collectively to protect, enhance and mitigate wildlife impacts in the Coeur d' Alene and Pend Oreille Subbasins. This contract provides for the enhancement, operations and maintenance, construction and implementation on mitigation properties managed by the Coeur d' Alene Tribe.  In addition, this contract provides the funding for the Tribe to conduct planning and design activities for the potential acquisition of mitigation properties.  Currently the Tribe owns and manages approximately 3,400 acres under the Albeni Falls Wildlife Mitigation Project.

To date, Operation and Maintenance and limited enhancement work (wetland creation) have been conducted on the mitigation properties (Goose Haven Lake - wetland creation/enhancement) under this project number. Full scale stream restoration and flood plain enhancement is being conducted on the Benewah Creek mitigation acquisition as part of the Fisheries Program's enhancement project.

The properties acquired to date by the Coeur d'Alene Tribe fall into two general categories. Those that are conservation type with limited enhancements necessary and those that have high potential habitat value but require active enhancement activities to realize potential.
Account Type(s):
Expense
Contract Start Date:
10/01/2011
Contract End Date:
09/30/2012
Current Contract Value:
$410,327
Expenditures:
$410,327

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Katey Grange Bonneville Power Administration Yes Env. Compliance Lead kcgrange@bpa.gov (503) 230-4047
Cameron Heusser Coeur D'Alene Tribe No Supervisor cheusser@cdatribe-nsn.gov (208) 686-5521
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Rosemary Mazaika Bonneville Power Administration No Interested Party rxmazaika@bpa.gov (503) 230-5869
Anders Mikkelsen Coeur D'Alene Tribe Yes Contract Manager amikkelsen@cdatribe-nsn.gov (208) 686-8902
Jenna Peterson Bonneville Power Administration No Interested Party jepeterson@bpa.gov (503) 230-3018
Nicole Rutherford Bonneville Power Administration No Interested Party narutherford@bpa.gov (503) 230-4320
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance B: 165. NEPA checklist/Compliance 09/28/2012 09/26/2012
Regional Wildlife Program Document Review C: 122. Regional Workgroup Management Plan and Acquisition Review 09/28/2012 09/26/2012
Management Plan Development and Revision D: 174. Produce management plans 09/28/2012 09/26/2012
Debris Removal on Habitat Properties E: 27. Elkhorn Ranch Property Debris Removal 09/28/2012 09/26/2012
Debris Removal on Habitat Properties F: 27. St. Joe River Property Debris Removal 09/28/2012 09/26/2012
Maintain perimeter fence and gates on all properties G: 186. Maintain Fence line and Structures 09/28/2012 09/26/2012
Investigate to trespass on all mitigation sites H: 26. Investigate trespass on mitigation properties 09/28/2012 09/26/2012
Vegetation Planting on The Goose Haven Lake Property I: 47. Plant vegetation to restore native habitats within the Goose Haven Lake Property 09/28/2012 09/26/2012
Completed HEP Reports J: 87. Prepare HEP report for the Albeni Falls Mitigation Projects 09/28/2012 09/26/2012
Albeni Falls Project Management K: 119. Albeni Falls Wildlife Mitigation Program 09/28/2012 09/26/2012
Install and maintain no trespassing signs L: 188. Install and maintain no trespassing signs on all mitigation properties 09/28/2012 09/26/2012
PISCES Quarterly reports M: 132. Submit Progress Report for the period (October 2011 ) to (September 2012) 09/28/2012 09/26/2012
Fee-title acquisition. N: 172. Conduct Pre-Acquisition Activities for Albeni Falls Mitigation Projects 09/28/2012 09/26/2012
Herbicide application and re-establish native plant species O: 197. Treat moxious weeds and maintain vegetation on Goose Haven Lake 09/30/2012 09/26/2012
Debris Removal on Habitat Properties P: 27. Hepton Lake Property Debris Removal. 09/30/2012 09/26/2012
Herbicide application on mitigation acquisitions Q: 197. Treat noxious weeds on Hepton Lake 09/30/2012 09/26/2012
Herbicide application on mitigation acquisitions R: 197. Treat noxious weeds on Ellkhorn Flats 09/30/2012 09/26/2012
Herbicide application on mitigation acquisitions S: 197. Treat noxious weeds on Windy Bay 09/30/2012 09/26/2012
Herbicide application on mitigation acquisitions T: 197. Treat noxious weeds on St. Joe River 09/30/2012 09/26/2012
Herbicide application on mitigation acquisitions U: 197. Treat noxious weeds on Cougar Creek 09/30/2012 09/26/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 6 instances of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 3 instances of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 87 Prepare HEP Report
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2011
B 165 NEPA checklist/Compliance 10/01/2011
C 122 Regional Workgroup Management Plan and Acquisition Review 10/01/2011
D 174 Produce management plans 10/01/2011
E 27 Elkhorn Ranch Property Debris Removal 10/01/2011
F 27 St. Joe River Property Debris Removal 10/01/2011
G 186 Maintain Fence line and Structures 10/01/2011
H 26 Investigate trespass on mitigation properties 10/01/2011
I 47 Plant vegetation to restore native habitats within the Goose Haven Lake Property 10/01/2011
J 87 Prepare HEP report for the Albeni Falls Mitigation Projects 10/01/2011
K 119 Albeni Falls Wildlife Mitigation Program 10/01/2011
L 188 Install and maintain no trespassing signs on all mitigation properties 10/01/2011
M 132 Submit Progress Report for the period (October 2011 ) to (September 2012) 10/01/2011
N 172 Conduct Pre-Acquisition Activities for Albeni Falls Mitigation Projects 10/01/2011
O 197 Treat moxious weeds and maintain vegetation on Goose Haven Lake 10/31/2011
P 27 Hepton Lake Property Debris Removal.
Q 197 Treat noxious weeds on Hepton Lake 10/01/2011
R 197 Treat noxious weeds on Ellkhorn Flats 10/01/2011
S 197 Treat noxious weeds on Windy Bay 10/01/2011
T 197 Treat noxious weeds on St. Joe River 10/01/2011
U 197 Treat noxious weeds on Cougar Creek 10/01/2011