Ensure environmental compliance requirements are complete |
A: 165. Complete Environmental Compliance Requirements |
|
09/30/2012 |
06/12/2012 |
DR: Collect water temperature data |
B: 157. Deschutes River (DR): 2001 - 2012 Record tributary water temperatures for lamprey life-history use. |
|
09/30/2012 |
09/28/2012 |
Estimate adult lamprey escapement for 2012 |
C: 162. DR: 2012 Generate Pacific lamprey escapement upstream of Sherars Falls |
|
06/30/2012 |
03/30/2012 |
Collect data associated with estimating escapement for Pacific lamprey in 2012 |
D: 157. DR: 2012 Field activities to generate Pacific lamprey escapement estimate upstream of Sherars Falls |
|
09/30/2012 |
09/28/2012 |
Tag adult lamprey at Sherars Falls |
E: 158. DR: 2012 Tag lamprey to estimate abundance at Sherars Falls |
|
09/30/2012 |
09/28/2012 |
Develop HDX arrays |
F: 70. DR: Establish Half Duplex PIT (HDX) arrays in the Warm Springs River |
|
09/30/2012 |
08/06/2012 |
Operate HDX arrays in Warm Springs River and Shitike Creek |
G: 157. DR: Collect data from half-duplex (HDX) sites on CTWSRO reservation |
|
09/30/2012 |
09/28/2012 |
Conduct end of distribution surveys |
H: 157. DR: End of distribution surveys in Badger, Beaver, Shitike creeks & Warm Springs River |
|
09/30/2012 |
09/28/2012 |
Conduct larval lamprey density surveys |
I: 157. DR: Ammocoete density surveys in Badger, Beaver, Shitike creeks & Warm Springs River |
|
09/30/2012 |
09/28/2012 |
Synthesize data gathered to date for ISRP review |
K: 161. DR: Synthesize data to date in Deschutes River Subbasin for ISRP |
|
09/30/2012 |
09/28/2012 |
Collect water temperature data in all potential lamprey habitat in Fifteenmile Creek Subbasin |
L: 157. Fifteenmile (FM): Record tributary water temperatures for lamprey life-history use |
|
09/30/2012 |
09/28/2012 |
Install LPS |
M: 184. FM: Install lamprey passage system (LPS) |
|
09/30/2012 |
09/28/2012 |
Install monitoring equipment into LPS |
N: 70. FM: Install fish monitoring equipment into LPS for escapement monitoring |
|
09/30/2012 |
09/28/2012 |
Escapement estimate feasibility |
O: 157. FM: Determine the feasibility of estimating lamprey escapement at Seufert Falls |
|
09/30/2012 |
09/28/2012 |
Tag lamprey |
P: 158. FM: Tag lamprey for escapement estimates |
|
09/30/2012 |
09/28/2012 |
Fifteenmile Creek adult Pacific lamprey escapement estimate for summer 2011 |
Q: 162. FM: Generate 2011 lamprey escapement estimate at Seufert Falls |
|
09/30/2012 |
04/15/2012 |
FM: Develop and installs HDX monitoring sites |
R: 70. FM: Install Half Duplex PIT Tag Interrogation Sites in Fifteenmile Creek |
|
09/30/2012 |
09/28/2012 |
Operation of HDX PIT Tag Arrays In Fifteenmile Creek Subbasin |
S: 157. FM: Collect Movement Data From Fifteenmile PIT Arrays |
|
09/30/2012 |
09/28/2012 |
Conduct end of distribution surveys |
T: 157. FM: End of distribution surveys in Fifteenmile Creek Subbasin |
|
09/30/2012 |
09/28/2012 |
Conduct end of distribution surveys |
U: 157. FM: Ammocoete density surveys in Fifteenmile Creek Subbasin |
|
09/30/2012 |
09/28/2012 |
Compile information on potential limiting factors to lamprey production |
V: 191. FM: Collect information on potential limiting factors to lamprey production |
|
09/30/2012 |
09/28/2012 |
Development and maintenance of a permanent flow gaging station in Fifteenmile Creek |
W: 148. FM: Install flow gage with satelite link in Fifteenmile Creek (phase 2 continued) |
|
09/30/2012 |
09/28/2012 |
Establish HDX array in Hood River |
X: 70. Hood River (HR): Install Half Duplex PIT tag Interrogation Site in Hood River |
|
09/30/2012 |
09/28/2012 |
Operation of HDX PIT Tag Arrays In Hood River |
Y: 157. NEW: HR: Collect data from half-duplex site in Hood River |
|
09/30/2012 |
09/28/2012 |
Conduct end of distribution surveys |
Z: 157. HR: End of distribution surveys in Hood River Subbasin |
|
09/30/2012 |
09/28/2012 |
Conduct larval lamprey density surveys |
AA: 157. HR: Ammocoete density surveys in Hood River Subbasin |
|
09/30/2012 |
09/28/2012 |
Develop methods to assess recolonization of Pacific lamprey in the Hood River |
AB: 156. HR: Assess natural recolonization of lamprey |
|
09/30/2012 |
09/28/2012 |
Enter HDX Tag information into PTAGIS. |
AC: 159. DR, FM, & HR: Enter HDX PIT tag information into PTAGIS |
|
09/30/2012 |
09/28/2012 |
Participate in regional lamprey research and recovery forums |
AD: 189. DR, FM, & HR: Participate in regional planning and recovery actions for Pacific lamprey |
|
09/30/2012 |
09/28/2012 |
Lamprey Education and Outreach (E&O) |
AE: 99. DR, FM, & HR Education & Outreach (E&O) |
|
09/30/2012 |
09/28/2012 |
HDX Pit tag Plan for CTWSRO |
AF: 174. DR, FM, & DR PIT tag plan |
|
09/30/2012 |
09/28/2012 |
Submit Funding Package To COTR |
AG: 119. Manage Project |
|
07/01/2012 |
06/28/2012 |
Attach Progress Report in Pisces |
AH: 132. DR, FM, & HR: Progress Reports for combined projects 2007-007-00 & 2002-016-00 |
|
08/15/2012 |
08/01/2012 |