Contract 55666: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-OSC
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
55666
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT-OSC
Contract Continuation:
Previous: Next:
49705: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-OSC
  • 59523: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - OSC
Contract Status:
Closed
Contract Description:
The purpose of this contract is to fund renovation of two Idaho Power Company owned diversion structures in the Pahsimeroi River.  The initial planning work by the Idaho Department of Fish and Game (IDFG) was completed under contract 44180 and 49705.   Construction of the chosen design will now be completed.  These diversions divert water for an anadromous fish hatchery operated by IDFG.  Upon assessing passage for all age classes of anadromous fish, a bid package will be developed for engineering services associated with redesigning the structures to facilitate fish passage.  The bid packages will then be advertised according to state law and an engineering firm chosen to complete all necessary survey and engineering design work for options to provide fish passage on both hatchery diversion structures.  The engineered drawings will then be used to attain construction bids.  If necessary, an environmental consultant will assist with compilation of data and compliance with all environmental regulations, as well as drafting necessary environmental documents and coordinating with all agencies (BPA, ID Power, IDFG, ACOE, IWDR, etc).  An Idaho Department of Fish and Game regional fishery biologist will coordinate and plan all necessary meetings and field activities, and administer the contract on a local basis.  This will include site visits and planning meetings with all necessary parties (engineers, environmental compliance consultants, Idaho Power representatives, IDFG officials, etc.).  

This contract will also allow for the identification and development of new projects not associated with hatchery diversion structures in the Pahsimeroi River Valley.  All projects identified and developed as part of this contract will be reviewed and ranked through the Upper Salmon Basin Technical Team.  This process will allow for a level of scrutiny and comment that will insure that the best projects are allowed to proceed to implementation.
Account Type(s):
Expense
Contract Start Date:
01/01/2012
Contract End Date:
12/31/2012
Current Contract Value:
$44,887
Expenditures:
$44,887

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Confirmation of EC/permits to BPA B: 165. Environmental Compliance 12/31/2012 12/31/2012
Funding Package - Submit draft to COTR C: 119. Routine/daily administration of contract work elements 11/15/2012 11/15/2012
Duck Creek floodplain revegetation D: 47. Duck Creek riparian revegetation 09/28/2012 09/28/2012
Attach Progress Report in Pisces E: 132. Submit Progress Report for the period (Sept 2010Y) to (Dec 2011) 02/15/2012 01/10/2012
Modified Pahsimeroi Hatchery Diversions F: 184. Pahsimeroi hatchery diversion modification 12/31/2012
Control of invasive plant species on Duck Creek G: 197. Weed control on Duck Creek site 11/30/2012 11/30/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 09/15/2011
B 165 Environmental Compliance 09/15/2011
C 119 Routine/daily administration of contract work elements 09/15/2011
D 47 Duck Creek riparian revegetation 11/23/2011
E 132 Submit Progress Report for the period (Sept 2010Y) to (Dec 2011) 09/15/2011
F 184 Pahsimeroi hatchery diversion modification
G 197 Weed control on Duck Creek site 01/01/2012