Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 174: 2008-458-00 EXP STEELHEAD KELT RECONDITIONING
Project Number:
Title:
Steelhead Kelt Reconditioning
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Cascade Columbia Upper Middle 100.00%
Contract Number:
56662 REL 174
Contract Title:
2008-458-00 EXP STEELHEAD KELT RECONDITIONING
Contract Continuation:
Previous: Next:
56662 REL 150: 2008-458-00 EXP STEELHEAD KELT RECONDITIONING
  • 56662 REL 202: 1996-040-00 EXP UC STEELHEAD KELT RECONDITIONING
Contract Status:
Closed
Contract Description:
The general objective of this project is to test whether the abundance of naturally produced Upper Columbia River steelhead on natural spawning grounds can be increased through the use of long-term kelt reconditioning methods.  Project objectives include: (1) Recondition UCR steelhead kelts using long-terms methods at existing facilities, (2) Evaluate kelt survival and effectiveness of reconditioning methods, and (3) Collaborating with ongoing M&E studies to document the reproductive success of kelts released from the reconditioning program.  The scope of this contract covers steps taken in the seventh year of implementation of a kelt reconditioning project in the Upper Columbia River.  Activities expected to be completed within the contract period include the collection, reconditioning, transportation, and release of natural origin (NOR) steelhead kelts.  Coordination with affected stakeholders (USFWS, WDFW, USGS, USFS, Chelan PUD and Douglas PUD) regarding live spawning of NOR broodstock, trapping and collection of kelts, and evaluations of kelt survival, maturation, and reproductive success will take place.  An effort will be made under this contract to work with stakeholders to find areas where collaboration on projects could be mutually beneficial.  Steelhead kelt collection will continue under this contract.  A temporary weir trap designed to downstream migrating steelhead kelts will be operated in Little Bridge Creek, South Fork Gold Cr., and Beaver Cr.  NOR kelts collected at these traps will be transported to the Methow Steelhead Kelt Facility (MSKF) for reconditioning.  In addition to trapping kelts at tributary weirs the YN will also participate in hook and line broodstock collection of steelhead for Winthrop National Fish Hatchery.  All NOR females used as broodstock by Winthrop National Fish Hatchery will be live spawned in a combined effort by the YN and USFWS staff.  All NOR females from the Twisp River conservation hatchery program operated by Douglas County PUD at the Methow Hatchery will be live spawned in a combined effort by the YN and DPUD staff.   Live spawning will allow the fishes' inclusion in the kelt reconditioning project.  YN will collaborate with Chelan County PUD to collect kelts moving downstream through the juvenile bypass at Rock Island dam. The reconditioning process will begin once kelts have been transported to the MSKF.  Reconditioning will include the reintroduction of feed and pathogen treatment.  Kelts will be reconditioned for approximately six months before they are released near the mouth of the Methow River.  The project will have discussions with cooperating agencies to determine the feasibility of these actions.
Account Type(s):
Expense
Contract Start Date:
02/01/2019
Contract End Date:
01/31/2020
Current Contract Value:
$342,370
Expenditures:
$342,370

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Matthew Abrahamse Yakama Confederated Tribes Yes Contract Manager abrm@yakamafish-nsn.gov (509) 996-3122
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Heidi Haak Bonneville Power Administration No Interested Party hlhaak@bpa.gov (541) 922-6856
Tana Hoptowit Yakama Confederated Tribes No CO Assistant hopt@yakamafish-nsn.gov (509) 865-5121x6318
Cory Kamphaus Yakama Confederated Tribes Yes Interested Party kamc@yakamafish-nsn.gov (509) 548-9413x102
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Eric McOmie Bonneville Power Administration Yes COR ermcomie@bpa.gov (503) 230-4964
Keely Murdoch Yakama Confederated Tribes Yes Supervisor murk@yakamafish-nsn.gov (509) 548-2206
Jackie Olney Yakama Confederated Tribes No Administrative Contact olnj@yakamafish-nsn.gov (509) 865-5121x6313
Tabatha Rood Bonneville Power Administration Yes Interested Party tmrood@bpa.gov (503) 230-5736
Thomas Scribner Yakama Confederated Tribes Yes Interested Party scrt@yakamafish-nsn.gov (503) 331-9850
Tybee Sheidler Bonneville Power Administration No Interested Party tasheidler@bpa.gov (503) 230-3820
Andraya Trujillo Yakama Confederated Tribes No Interested Party trua@yakamafish-nsn.gov (509) 865-5121
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Elham Zolmajd-Haghighi Bonneville Power Administration No Interested Party ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Manage and administer 2019 upper Columbia kelt reconditioning project 01/31/2020 01/31/2020
Environmental Compliance Documentation C: 165. ESA compliance for project implementation 02/01/2019 02/01/2019
2017 Progress Report D: 132. Submit progress report for the period (1/2017) to (12/2017) 03/31/2019 03/31/2019
2018 Progress Report E: 132. Submit progress report for the period (1/2018) to (12/2018) 01/31/2020 01/31/2020
Kelts for the reconditioning project F: 66. Temporary tributary weirs - Beaver Cr. 06/15/2019 06/15/2019
Kelts for the reconditioning project G: 66. Temporary tributary weir - Little Bridge Cr. 06/15/2019 06/15/2019
Kelts for reconditioning project H: 66. Steelhead broodstock collection and live spawning 06/30/2019 06/30/2019
Functional Kelt Facility I: 61. Methow Steelhead Kelt Facility (MSKF) operation 01/31/2020 01/31/2020
Reconditioned Kelts J: 176. Steelhead kelt reconditioning 01/31/2020 01/31/2020
Kelts for reconditioning project K: 66. Kelt Collection at Rock Island Dam 06/30/2019 06/30/2019
Tagged kelts L: 158. PIT and radio tag kelts 10/31/2019 10/31/2019
Submit BiOp RPA Report in Taurus M: 202. BiOp RPA Report for CY 2018 03/15/2019 03/15/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 4 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 158 Mark/Tag Animals

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/01/2019
B 119 Manage and administer 2019 upper Columbia kelt reconditioning project 02/01/2019
C 165 ESA compliance for project implementation 02/01/2019
D 132 Submit progress report for the period (1/2017) to (12/2017) 02/01/2019
E 132 Submit progress report for the period (1/2018) to (12/2018) 02/01/2019
F 66 Temporary tributary weirs - Beaver Cr. 03/08/2019
G 66 Temporary tributary weir - Little Bridge Cr. 03/08/2019
H 66 Steelhead broodstock collection and live spawning 03/08/2019
I 61 Methow Steelhead Kelt Facility (MSKF) operation 03/08/2019
J 176 Steelhead kelt reconditioning 03/08/2019
K 66 Kelt Collection at Rock Island Dam 03/08/2019
L 158 PIT and radio tag kelts 03/08/2019
M 202 BiOp RPA Report for CY 2018