| Province | Subbasin | % |
|---|---|---|
| Blue Mountain | Grande Ronde | 100.00% |
| Previous: | Next: |
|---|---|
| n/a |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Produce environmental compliance documentation | A: 165. Produce Environmental Compliance Documents | 12/01/2013 | 12/01/2013 | |
| Add wood and boulders to approximately 4 miles of Meadow Creek. | B: 29. Structure Construction | 12/02/2013 | 12/02/2013 | |
| Plant Seedlings and Cuttings | C: 47. Plant Seedlings and Cuttings | 07/01/2013 | 07/01/2013 | |
| Exclosure Fence Reconstruction | D: 40. Reconstruct .2 miles of exclosure fence | 12/02/2013 | 07/18/2012 | |
| Seed and mulch disturbed areas | E: 47. Seed and Mulch disturbed areas | 11/30/2012 | 11/30/2012 | |
| Remove culvert # 1 | F: 84. Remove Culvert #1 | 11/30/2012 | 08/01/2012 | |
| Remove Culvert #2 | G: 84. Remove Culvert #2 | 11/30/2012 | 08/01/2012 | |
| Project Administration | H: 119. Project Administration | 02/28/2014 | 02/28/2014 | |
| Monitoring | I: 157. Monitoring | 01/30/2014 | 01/30/2014 | |
| Attach Completion Report in Pisces | J: 132. Project Completion Report May 2012 - February 2014 | 02/14/2014 | 02/28/2014 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Produce Environmental Compliance Documents | 06/01/2020 | ||||||
| B | 29 | Structure Construction | 05/01/2012 | ||||||
| C | 47 | Plant Seedlings and Cuttings | 02/01/2012 | ||||||
| D | 40 | Reconstruct .2 miles of exclosure fence | 05/01/2012 | ||||||
| E | 47 | Seed and Mulch disturbed areas | 05/01/2012 | ||||||
| F | 84 | Remove Culvert #1 | 05/01/2012 | ||||||
| G | 84 | Remove Culvert #2 | 05/01/2012 | ||||||
| H | 119 | Project Administration | 06/01/2020 | ||||||
| I | 157 | Monitoring | 05/01/2012 | ||||||
| J | 132 | Project Completion Report May 2012 - February 2014 | 06/01/2020 | ||||||
| K | 185 | Quarterly Status Reports | 06/01/2020 |