Documentation & Assistance To Support BPA's Environmental Compliance Group |
A: 165. Environmental Compliance For Data Collection Activities 2012 - 2013 |
|
07/30/2012 |
03/01/2012 |
Analyze & Interpret Fall Hydroacoustic Data (Surveys To Be Completed In Jan/Feb 2012) |
B: 162. Analyze & Interpret Fall Hydroacoustic Data (Survey To Be Completed In Jan/Feb 2012) |
|
11/30/2012 |
07/31/2012 |
Conduct Summer Hydroacoustic Survey In Lake Billy Chinook |
C: 157. Conduct Summer Hydroacoustic Survey In Lake Billy Chinook |
|
11/30/2012 |
08/31/2012 |
Analyze & Interpret Summer Hydroacoustic Data |
D: 162. Analyze & Interpret Summer Hydroacoustic Data |
|
02/28/2013 |
02/28/2013 |
Conduct Fall Hydroacoustic Survey In Lake Billy Chinook |
E: 157. Conduct Fall Hydroacoustic Survey In Lake Billy Chinook |
|
12/31/2012 |
12/27/2012 |
Analyze & Interpret Fall Hydroacoustic Data |
F: 162. Analyze & Interpret Fall Hydroacoustic Data |
|
02/28/2013 |
02/28/2013 |
Install Smolt Trap At Suttle Lake Outlet In Lake Creek |
G: 70. Install Smolt Trap At Suttle Lake Outlet In Lake Creek |
|
09/30/2012 |
04/23/2012 |
Monitor/Assess Timing & Abundance Of O. nerka Outmigrants From Suttle Lake |
H: 157. Monitor/Assess Timing & Abundance Of O. nerka Outmigrants From Suttle Lake |
|
11/30/2012 |
07/18/2012 |
PIT Tag O. nerka Outmigrants From Suttle Lake |
I: 158. PIT Tag O. nerka Outmigrants From Suttle Lake |
|
10/31/2012 |
06/15/2012 |
Install Full Duplex PIT Tag Antennae in Lake Creek |
J: 70. Install Full-Duplex PIT Tag Antennae In Lake Creek |
|
09/30/2012 |
04/13/2012 |
Develop, Operate & Maintain Full-Duplex PIT Tag Antenna Arrays In Lake Creek |
K: 157. Collect PIT Tag Data From Antenna Arrays In Lake Creek |
|
11/30/2012 |
07/18/2012 |
Analyze & Interpret PIT Tagged O. nerka Data |
L: 162. Analyze & Interpret PIT Tagged O. nerka Data |
|
02/28/2013 |
02/15/2013 |
Estimate Abundance of Adfluvial O. nerka From Lake Billy Chinook Entering Metolius River To Spawn |
M: 157. Estimate Abundance Of Adfluvial O. nerka From Lake Billy Chinook Entering Metolius River To Spawn |
|
11/30/2012 |
10/26/2012 |
Mark/Tag O. nerka In Lake Billy Chinook |
N: 158. Mark/Tag O. nerka In Lake Billy Chinook |
|
09/30/2012 |
09/06/2012 |
Analyze Mark-Resight Data To Produce Estimate Of O. nerka Spawners In Metolius River |
O: 162. Analyze Mark-Resight Data to Produce Estimate Of O. nerka Spawners In Metolius River |
|
02/28/2013 |
02/01/2013 |
Collect Sort Returning Adult O. nerka At Pelton Trap |
P: 157. Collect Adult O. nerka At Pelton Trap To Compare SAR Rates Between Suttle Lake & Lake Billy Chinook |
|
11/30/2012 |
11/30/2012 |
Analyze Suttle Lake & Lake Billy Chinook O. nerka SAR |
Q: 162. Analyze Suttle Lake & Lake Billy Chinook O. nerka SAR |
|
02/28/2013 |
02/28/2013 |
Coordinate Sockeye Reintroduction Plan |
R: 191. Coordinate On Sockeye Reintroduction Plan |
|
02/28/2013 |
02/28/2013 |
Complete Sockeye Reintroduction Plan |
S: 174. Complete Sockeye Reintroduction Plan |
|
02/28/2013 |
02/28/2013 |
Upload PIT Tag Data To PTAGIS |
T: 159. Upload PIT Tag Data To PTAGIS |
|
02/28/2013 |
07/16/2012 |
Attach Progress Report In Pisces |
V: 132. Submit Progress Report For The Period March 2011 - February 2012 |
|
12/31/2012 |
11/16/2012 |
Funding Package - Submit Package To COTR |
W: 119. Manage Project |
|
11/30/2012 |
11/30/2012 |