Complete BPA EC permitting process |
A: 165. Produce all environmental compliance documentation |
|
11/30/2013 |
11/29/2013 |
Contract Administration |
B: 119. Project management/ coordination/ provide BPA programmatic information |
|
11/30/2013 |
11/30/2013 |
Watershed-wide coordination with other restoration entities |
C: 191. Coordination with MRC, YN, and Watershed Council of implementation on watershed scale |
|
11/30/2013 |
11/29/2013 |
Remove levee - 1,100 lineal feet |
D: 180. WDFW project area - levee removal, floodplain enhancement |
|
11/30/2013 |
10/15/2013 |
Installation of 28 LWD and ELJ components as described |
E: 29. WDFW - Mainstem and side channel ELJs/LWD, and removal of grade control materials |
|
11/30/2013 |
10/15/2013 |
Installation of1 ELJ structure as described |
F: 29. WDFW - Mainstem ELJ near MVID East Diversion |
|
11/30/2013 |
11/30/2013 |
Install culvert |
G: 184. WDFW - install south culvert to connect the wetland pond and the main river channel |
|
11/30/2013 |
10/10/2013 |
Install culvert |
H: 181. WDFW - install north culvert to connect the floodplain with the wetland pond |
|
11/30/2013 |
10/10/2013 |
Complete described work components |
I: 181. WDFW project area - enhance wetlands on public and private property |
|
11/30/2013 |
10/10/2013 |
Establish riparian plantings and protection as described in project area |
J: 47. WDFW - Plant native riparian vegetation and establish irrigation |
|
11/30/2013 |
|
Weed control, maintain plantings from WE H |
K: 197. WDFW - Protection / exclusion for existing vegetation, remove noxious and exotic plants |
|
11/30/2013 |
11/15/2013 |
Installation of 49 total LWD and ELJ components and 1 live crib structure, as described |
L: 29. WFI - Mainstem and side channel ELJs/LWD, engineered live crib wall |
|
11/30/2012 |
12/07/2012 |
Maintain, Repair, Install and/or Remove |
M: 186. Construction Services 2012 - 2013 |
|
11/30/2013 |
11/30/2013 |
Technical review |
N: 122. WDFW review and acceptance of proposed work elements and construction follow-through |
|
11/30/2013 |
|
Establish riparian vegetation in project area as described |
O: 47. WFI - Plant native riparian vegetation |
|
11/30/2012 |
11/30/2012 |
Complete treatment of1.23 acres |
P: 197. WFI - Establish plant protection and exclusion, remove noxious and exotic plants |
|
11/30/2012 |
11/30/2012 |
Attach Annual Progress Report in Pisces |
R: 132. Submit Annual Progress Report for the period May 2012 to October 2013) |
|
11/30/2013 |
|