| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Walla Walla | 100.00% |
| Previous: | Next: |
|---|---|
| 43565: 200902600 CAP CONSTRUCT-OLD LOWDEN-BERGEVIN WILLIAMS CONSOLIDATN |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Audrey Ahmann | Walla Walla County Conservation District (SWCD) | Yes | Contract Manager | audrey.ahmann@wwccd.net | (509) 522-6340x107 |
| Dawn Boorse | Bonneville Power Administration | No | Env. Compliance Lead | drboorse@bpa.gov | (503) 230-5678 |
| Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
| Rick Jones | Walla Walla County Conservation District (SWCD) | Yes | Supervisor | rick.jones@wwccd.net | (509) 522-6340x110 |
| Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
| Tracey Yerxa | Bonneville Power Administration | Yes | COR | tyerxa@bpa.gov | (503) 230-4738 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Documentation and assistance to support BPA's Environmental Compliance Group | A: 165. Complete environmental compliance for BWOL diversion | 09/30/2013 | 09/30/2013 | |
| Project management & administrative work on BWOL diversion complete | B: 119. Manage and Administer BWOL Project | 09/30/2013 | 09/30/2013 | |
| WWCCD Completion Report | C: 132. BWOL and Blalock Progress Report for the period 06/20/2012 to 09/30/2013 | 09/30/2013 | ||
| A completed structure with pumps and pipeline ready for fish screen and cleaning system | D: 84. Construct BWOL diversion structure at existing L2 & GC diversion | 09/30/2013 | ||
| A NOAA compliant fish screen and cleaning system installed in the new B-W / OL structure | E: 69. Fabricate fish screen and install in new BWOL diversion structure | 03/01/2013 | 03/01/2013 | |
| Construction Management Complete | F: 100. Provide BWOL construct oversight, inspections & contract compliance checks | 09/30/2013 | 09/30/2013 | |
| Complete and operational Blalock Irrigation District diversion and fish screen | H: 69. Install Blalock ID Diversion and Fish Screen | 04/30/2013 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Complete environmental compliance for BWOL diversion | 12/01/2011 | ||||||
| B | 119 | Manage and Administer BWOL Project | 12/01/2011 | ||||||
| C | 132 | BWOL and Blalock Progress Report for the period 06/20/2012 to 09/30/2013 | 12/01/2011 | ||||||
| D | 84 | Construct BWOL diversion structure at existing L2 & GC diversion | 05/11/2012 | ||||||
| E | 69 | Fabricate fish screen and install in new BWOL diversion structure | 05/11/2012 | ||||||
| F | 100 | Provide BWOL construct oversight, inspections & contract compliance checks | 05/01/2012 | ||||||
| G | 185 | Periodic Status Reports for BPA | 12/01/2011 | ||||||
| H | 69 | Install Blalock ID Diversion and Fish Screen | 06/26/2012 |