Province | Subbasin | % |
---|---|---|
Columbia Gorge | Hood | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Sep-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Relevant documents/permits submitted to BPA for environmental compliance review. | B: 165. Ensure environmental compliance is adequate | 10/30/2012 | 10/30/2012 | |
26,000 PIT tagged steelhead and spring Chinook salmon. | C: 158. PIT tag hatchery steelhead and spring Chinook salmon | 09/30/2013 | 09/30/2013 | |
Monitor water temperatures in the Hood River subbasin | D: 157. Collect water temperature data in the Hood River subbasin | 09/30/2013 | 09/30/2013 | |
Record water flows in Rogers and Odell Creeks. | E: 157. Record stream flows in the Hood River basin. | 09/30/2013 | 09/30/2013 | |
East Fork irrigation canal salvage activities complete | F: 28. Salvage and transport fish entrained in irrigation canals to nearest free-flowing waterbody | 11/16/2012 | 11/01/2012 | |
Juvenile spring Chinook salmon distribution | G: 157. Conduct basin-wide juvenile spring Chinook distribution surveys. | 09/30/2013 | 09/30/2013 | |
Submit HRPP hatchery production PIT tag codes to PTAGIS database. | H: 159. Input Hood River PIT tag data to appropriate databases | 09/30/2013 | 09/30/2013 | |
2012-2013 Hood River spring Chinook salmon spawning distribution and condition. | I: 157. Chinook spawning surveys | 09/30/2013 | 09/30/2013 | |
Estimate of adult spring Chinook salmon returns to the mouth of the Hood River. | J: 157. Spring Chinook salmon preseason adult run size forecast. | 09/30/2013 | 09/30/2013 | |
Estimate tribal harvest of spring Chinook salmon in the Hood River. | K: 157. Spring Chinook salmon tribal harvest monitoring | 09/30/2013 | 09/30/2013 | |
Fully functional PIT interrogation systems in Hood River. | L: 70. Install and operate PIT antenae | 09/30/2013 | 09/30/2013 | |
Assist with determining Dee Mill trap efficiency. | M: 158. Determine East Fork Dee Mill trap efficiency. | 09/30/2013 | 09/30/2013 | |
2012 Final Report uploaded to Pisces (10/1/11 - 9/30/12) | N: 132. Produce Annual Report for 10/1/11 - 9/30/12 | 09/30/2013 | 09/30/2013 | |
Project administration & coordination complete | O: 119. Manage Project | 09/30/2013 | 09/30/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 10/01/2012 | ||||||
B | 165 | Ensure environmental compliance is adequate | 10/01/2012 | ||||||
C | 158 | PIT tag hatchery steelhead and spring Chinook salmon | 10/01/2012 | ||||||
D | 157 | Collect water temperature data in the Hood River subbasin | 10/01/2012 | ||||||
E | 157 | Record stream flows in the Hood River basin. | 10/01/2012 | ||||||
F | 28 | Salvage and transport fish entrained in irrigation canals to nearest free-flowing waterbody | 10/01/2012 | ||||||
G | 157 | Conduct basin-wide juvenile spring Chinook distribution surveys. | 10/01/2012 | ||||||
H | 159 | Input Hood River PIT tag data to appropriate databases | 10/01/2012 | ||||||
I | 157 | Chinook spawning surveys | 10/01/2012 | ||||||
J | 157 | Spring Chinook salmon preseason adult run size forecast. | 10/01/2012 | ||||||
K | 157 | Spring Chinook salmon tribal harvest monitoring | 10/01/2012 | ||||||
L | 70 | Install and operate PIT antenae | 10/01/2012 | ||||||
M | 158 | Determine East Fork Dee Mill trap efficiency. | 10/01/2012 | ||||||
N | 132 | Produce Annual Report for 10/1/11 - 9/30/12 | 10/01/2012 | ||||||
O | 119 | Manage Project | 10/01/2012 |