Contract Continuation:
Previous: Next:
51456: 2010-003-00 EXP LOWER SO FORK CLEARWATER R WATERSHED RESTORATION
  • 64048: 2010-003-00 EXP LOWER SOUTH FORK CLEARWATER RESTORATION
Contract Status:
Closed
Contract Description:
Contract History:

This project is implemented as part of the Nez Perce National Forest (NPNF)/Nez Perce Tribe (NPT) restoration partnership.  This project represents a merger of two ongoing Bonneville Power Administration (BPA) and NPT restoration projects, #1996-077-05, Meadow Creek Watershed Restoration and #2000-036-00, Mill Creek Watershed Restoration, and an expansion of the project area to include all of the NPNF lands in the lower South Fork Clearwater Basin rather than just selected watersheds.  The restoration partnership has been ongoing in the basin since 1996 and this project unification greatly increases the geographic area covered, and enhances the administrative and financial efficiency in order to maximize the direct benefit to fish and wildlife.

The goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural, and economic practices of the Nez Perce Tribe.  The South Fork Clearwater River watershed contains proposed critical habitat for listed species steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for spring Chinook salmon.  Restoration follows a ridge top to ridge top approach with implementation focused on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, aquatic habitat connectivity, and exotic, invasive plants.  The cost share for this project has been contributed by the Nez Perce National Forest who provides at least a 20% match including cash and in-kind contributions. Project planning and implementation responsibilities are also shared with the Nez Perce National Forest.

FY 13 Implementation Summary:

FY 13 implementation includes the survey and contract preparation for the future removal of up to 15 miles of roads (to reduce sediment input to streams), one road improvement project (to improve hydrologic capacity, reduce potential sediment delivery, and provide connectivity), one culvert replacement (to improve hydrologic capacity, reduce potential sediment delivery, and provide connectivity), riparian planting (to decrease water temperatures and reduce potential sediment delivery), fence maintenance (to protect riparian plants), project implementation, effectiveness, and status and trend monitoring and evaluation, and continued planning and coordination for next year's projects and out-year habitat improvements.  NPT Watershed personnel will also continue an inventory of roads and stream crossings throughout the Lower South Fork Clearwater River watershed in order to identify fish passage barriers and road associated risks to aquatic species.
Account Type(s):
Expense
Contract Start Date:
03/01/2013
Contract End Date:
02/28/2014
Current Contract Value:
$725,842
Expenditures:
$725,842

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Miranda Gordon Nez Perce Tribe No mirandag@nezperce.org (208) 621-3547
Jenifer Harris Nez Perce Tribe No Interested Party jeniferh@nezperce.org (208) 983-1290
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Mark Johnson Nez Perce Tribe Yes Contract Manager markj@nezperce.org (208) 621-3561
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Heidi McRoberts Nez Perce Tribe Yes Supervisor heidim@nezperce.org (208) 621-3548
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Provide environmental compliance information to BPA for projects on Forest Service Lands 01/31/2014 01/31/2014
Culvert replaced B: 184. Replace Hunt Creek Culvert 10/25/2013 10/17/2013
Sediment reduced from Forest Road 469 C: 38. Forest Road 469 Road Improvement 11/01/2013 10/15/2013
Designs and cost estimates D: 175. Designs for Meadow Face IV Road Decommissioning 02/28/2014 02/07/2014
Riparian vegetation planted E: 47. Plant Riparian Vegetation - Mill Creek 02/28/2014 02/14/2014
Riparian vegetation planted F: 47. Plant Riparian Vegetation - McComas Meadows 02/28/2014 02/14/2014
Cages inspected and relocated as needed G: 197. Protect Hawthorn Trees Within McComas Meadows 10/31/2013 09/30/2013
Fence maintained H: 186. Maintain Fence - Mill Creek 07/01/2013 06/19/2013
Fence maintained I: 186. Maintain Fence - McComas Meadows 07/01/2013 06/19/2013
Culvert and bridge inventory J: 115. Collect Data on Existing Culverts and Bridges 10/31/2013 10/31/2013
Road inventory K: 115. Collect Data on Roads to Identify Aquatic Impacts 10/31/2013 10/31/2013
Culvert data collected L: 115. Collect Data on Culverts/Bridges that have been Replaced 10/31/2013 10/01/2013
Road data collected M: 115. Collect Data on Roads that were Removed 11/01/2013 10/25/2013
Habitat data collected N: 157. Stream Habitat Data Collection 02/28/2014 09/20/2013
Data analyzed and 2013 reports completed O: 162. Lower South Fork Clearwater Data Analysis 02/28/2014 02/27/2014
FY 2014 SOW package and FY 2013 accrual estimate P: 119. Management, Coordination, and Communication 12/13/2013 06/23/2013
Final FY 2013 annual report uploaded to Pisces and Taurus Q: 132. Produce Annual Report for Period 1/1/2013 - 12/31/2013 02/28/2014 02/14/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 4 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 4 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide environmental compliance information to BPA for projects on Forest Service Lands 03/01/2013
B 184 Replace Hunt Creek Culvert 03/01/2013
C 38 Forest Road 469 Road Improvement 08/20/2010
D 175 Designs for Meadow Face IV Road Decommissioning 04/08/2013
E 47 Plant Riparian Vegetation - Mill Creek 02/10/2011
F 47 Plant Riparian Vegetation - McComas Meadows 03/01/2013
G 197 Protect Hawthorn Trees Within McComas Meadows 03/01/2013
H 186 Maintain Fence - Mill Creek 03/01/2013
I 186 Maintain Fence - McComas Meadows 03/01/2013
J 115 Collect Data on Existing Culverts and Bridges 04/08/2013
K 115 Collect Data on Roads to Identify Aquatic Impacts 04/08/2013
L 115 Collect Data on Culverts/Bridges that have been Replaced 04/08/2013
M 115 Collect Data on Roads that were Removed 04/08/2013
N 157 Stream Habitat Data Collection 04/08/2013
O 162 Lower South Fork Clearwater Data Analysis 03/01/2013
P 119 Management, Coordination, and Communication 03/01/2013
Q 132 Produce Annual Report for Period 1/1/2013 - 12/31/2013 03/01/2013
R 185 Periodic Status Reports for BPA 03/01/2013