| Province | Subbasin | % |
|---|---|---|
| Mountain Snake | Clearwater | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Brenda Aguirre | Bonneville Power Administration | Yes | Env. Compliance Lead | baguirre@bpa.gov | (503) 230-5928 |
| Miranda Gordon | Nez Perce Tribe | Yes | Technical Contact | mirandag@nezperce.org | (208) 621-3547 |
| Jenifer Harris | Nez Perce Tribe | No | Interested Party | jeniferh@nezperce.org | (208) 983-1290 |
| Tracy Hauser | Bonneville Power Administration | Yes | COR | tlhauser@bpa.gov | (503) 230-4296 |
| Arleen Henry | Nez Perce Tribe | No | Administrative Contact | arleenh@nezperce.org | (208) 621-3833 |
| Mark Johnson | Nez Perce Tribe | Yes | Contract Manager | markj@nezperce.org | (208) 621-3561 |
| Heidi McRoberts | Nez Perce Tribe | Yes | Supervisor | heidim@nezperce.org | (208) 621-3548 |
| John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
| Emmit Taylor, Jr. | Nez Perce Tribe | No | Supervisor | emmitt@nezperce.org | (208) 621-3544 |
| Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental compliance documentation submitted to BPA | A: 165. Provide environmental compliance information to BPA for projects on Forest Service Lands | 02/28/2015 | 02/27/2015 | |
| Designs and Cost Estimates | B: 175. Final Design and Cost Estimate for Adams Creek Culvert | 02/28/2015 | 01/15/2015 | |
| Road Decommissioning Completed | C: 33. Meadow Face Phase IV Road Decommissioning | 12/15/2014 | 10/24/2014 | |
| Sediment Reduced from Forest Road 469 | D: 38. Forest Road 469 Improvement | 11/01/2014 | 09/19/2014 | |
| Sediment Reduced from Mill Creek Trail #313 | E: 38. Mill Creek Trail #313 Improvement | 08/31/2014 | 08/08/2014 | |
| Riparian Vegetation Planted | F: 47. Plant Riparian Vegetation - Previous Restoration Projects | 02/28/2015 | 02/27/2015 | |
| Riparian Vegetation Planted | G: 47. Plant Riparian Vegetation - McComas Meadows | 02/28/2015 | 02/01/2015 | |
| Exclosure Fence Maintained | H: 186. Maintain Exclosure Fences - Mill Creek | 08/01/2014 | 04/18/2014 | |
| Exclosure fence maintained | I: 186. Maintain Exclosure Fences - McComas Meadows | 07/01/2014 | 06/13/2014 | |
| Culvert and Bridge Inventory | J: 115. Assess Condition of Existing Culverts and Bridges | 02/28/2015 | 02/25/2015 | |
| Road Inventory | K: 115. Assess Condition of Roads to Identify Aquatic Impacts | 11/30/2014 | 12/19/2014 | |
| FY 2015 SOW package and FY 2014 accrual estimate | L: 119. Management, Coordination, and Communication | 12/05/2014 | 12/26/2014 | |
| Final FY 2014 Annual Report | M: 132. Produce Annual Report for Period 3/1/2014 - 2/28/2015 | 02/28/2015 | 02/27/2015 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Provide environmental compliance information to BPA for projects on Forest Service Lands | 03/01/2014 | ||||||
| B | 175 | Final Design and Cost Estimate for Adams Creek Culvert | 03/27/2014 | ||||||
| C | 33 | Meadow Face Phase IV Road Decommissioning | 03/01/2014 | ||||||
| D | 38 | Forest Road 469 Improvement | 03/01/2014 | ||||||
| E | 38 | Mill Creek Trail #313 Improvement | 03/01/2014 | ||||||
| F | 47 | Plant Riparian Vegetation - Previous Restoration Projects | 03/01/2014 | ||||||
| G | 47 | Plant Riparian Vegetation - McComas Meadows | 03/01/2014 | ||||||
| H | 186 | Maintain Exclosure Fences - Mill Creek | 03/27/2014 | ||||||
| I | 186 | Maintain Exclosure Fences - McComas Meadows | 03/27/2014 | ||||||
| J | 115 | Assess Condition of Existing Culverts and Bridges | 03/27/2014 | ||||||
| K | 115 | Assess Condition of Roads to Identify Aquatic Impacts | 03/27/2014 | ||||||
| L | 119 | Management, Coordination, and Communication | 03/01/2014 | ||||||
| M | 132 | Produce Annual Report for Period 3/1/2014 - 2/28/2015 | 03/01/2014 | ||||||
| N | 185 | Periodic Status Reports for BPA | 03/01/2014 |