Contract 65446: 2002-059-00 EXP YANKEE FORK RESTORATION - PREACHERS COVE
Project Number:
Title:
Yankee Fork Salmon River Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
65446
Contract Title:
2002-059-00 EXP YANKEE FORK RESTORATION - PREACHERS COVE
Contract Continuation:
Previous: Next:
n/a
  • 69333: 2002-059-00 EXP WEST FORK YANKEE FORK PHASE I
Contract Status:
History
Contract Description:
This project includes habitat improvement on the Yankee Fork at Preachers Cove to increase the habitat quantity and quality of that area.  This will be accomplished by building habitat structures consisting of wood, rock, and spawning gravel at 11 locations, removing a flood-plain berm, and planting vegetation in areas disturbed by construction.  Habitat structures will provide resting cover for adults, will create channel roughness that will help retain and sort spawning gravels and activate the flood-plain, and will provide habitat for juvenile Chinook and steelhead during both summer and winter.  Removal of the flood-plain berm (old road embankment) will ensure that high flows are able to continue on the flood-plain rather than being artificially routed back to the mainstem Yankee Fork.  Planting riparian vegetation will help the disturbed area recover quickly and will provide debris input to aid in stream primary production. Implementation of this project is scheduled for fall 2014.
Account Type(s):
Expense
Contract Start Date:
06/15/2014
Contract End Date:
08/31/2015
Current Contract Value:
$181,592
Expenditures:
$181,592

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Chad Colter Shoshone-Bannock Tribes No Interested Party ccolter@sbtribes.com (208) 239-4553
Mark Davidson Trout Unlimited (TU) No Supervisor mdavidson@tu.org (208) 720-2475
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Paul Drury US Bureau of Reclamation (BOR) No Interested Party pdrury@usbr.gov (208) 378-5076
Israel Duran Bonneville Power Administration No Env. Compliance Lead induran@bpa.gov (503) 230-3967
Evelyn Galloway Shoshone-Bannock Tribes No Technical Contact egalloway@sbtribes.com (208) 239-4570
Matt Green Trout Unlimited (TU) Yes Contract Manager mgreen@tu.org (208) 251-0197
Jim Gregory Trout Unlimited (TU) Yes Technical Contact gregory_jim@yahoo.com (208) 390-5306
Jerry Myers Trout Unlimited (TU) Yes Technical Contact jmyers@tu.org (208) 394-2111
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Complete all required EC and obtain site specific permits prior to implementation of project a A: 165. Environmental Compliance 04/30/2015 09/02/2014
All administrative tasks fulfilled with timely quality products B: 119. Manage and Administer Project 08/15/2014 08/15/2014
Construction Management Complete C: 100. Construction management for Preachers Cove restoration project 01/31/2015 12/31/2014
As built record drawings submitted to BPA. D: 29. Increase complexity in Yankee Fork at Preachers Cove 12/31/2014 02/06/2015
As built record drawings submitted to BPA. E: 180. Enhance floodplain, remove road embankment 12/31/2014 02/06/2015
As built record drawings submitted. F: 55. Construction Site Best Management Practices 12/31/2014 02/06/2015
Plant vegetation at Preachers Cove habitat restoration project G: 47. Plant vegetation at Preachers Cove 09/30/2014 09/18/2014
Attach Progress Report in Pisces H: 132. Submit Progress Report for the period July 2014 thru July 2015 01/15/2015
Obtain and stage supplies (rock and trees) for West Fork Yankee Fork Confluence Project J: 29. Obtain and stage rocks and trees for West Fork Yankee Fork Confluence Project 08/28/2015 08/21/2015
Collect willow and tree cuttings, plant and grow cuttings at a nursery K: 47. Collect willow and tree cuttings, plant and grow cuttings at a nursery 07/01/2015 07/01/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 05/01/2014
B 119 Manage and Administer Project 05/01/2014
C 100 Construction management for Preachers Cove restoration project 05/01/2014
D 29 Increase complexity in Yankee Fork at Preachers Cove 07/07/2014
E 180 Enhance floodplain, remove road embankment 07/15/2014
F 55 Construction Site Best Management Practices 07/08/2014
G 47 Plant vegetation at Preachers Cove 07/07/2014
H 132 Submit Progress Report for the period July 2014 thru July 2015 05/01/2014
I 185 Periodic Status Reports for BPA 05/01/2014
J 29 Obtain and stage rocks and trees for West Fork Yankee Fork Confluence Project 06/15/2014
K 47 Collect willow and tree cuttings, plant and grow cuttings at a nursery 06/15/2014