Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 68742: 2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
Project Number:
Title:
Upper Salmon Basin Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
68742
Contract Title:
2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
Contract Continuation:
Previous: Next:
65294: 2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
  • 72593: 2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
Contract Status:
Closed
Contract Description:
The Lemhi River Restoration Planning contract provides the Idaho Office of Species Conservation (OSC) with funding to cover subcontracted expenses associated with on the ground implementation of salmon and steelhead recovery projects in the Lemhi watershed.  Habitat projects will be implemented for 2010-072-00 Lemhi River Restoration or other OSC-sponsored projects.  

In 2008, Idaho's Governor directed that all funding and contracting for Idaho's Accord projects was to go through the OSC.  OSC manages individual projects as needed to ensure adequate oversight and provide that all state agencies and their partners work in a coordinated fashion.  OSC will provide contract oversight.  Implementation work will be completed by a subcontractor, Lemhi Soil and Water Conservation District (District).  

Deliverables under the contract include project implementation support.  The subcontractor will also assist BPA's Environmental Compliance Lead to ensure that environmental compliance requirements are met during habitat project implementation.
Account Type(s):
Expense
Contract Start Date:
06/01/2015
Contract End Date:
05/31/2016
Current Contract Value:
$25,147
Expenditures:
$25,147

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Bertram Idaho Governor's Office of Species Conservation Yes Technical Contact daniel.bertram@osc.idaho.gov (208) 756-6322
Allen Bradbury Idaho Governor's Office of Species Conservation Yes Technical Contact allen.bradbury@osc.idaho.gov (208) 756-6322
Sharon Clark Idaho Department of Fish and Game (IDFG) No Interested Party sharon.clark@idfg.idaho.gov (208) 287-2784
Jeffrey DiLuccia Idaho Department of Fish and Game (IDFG) Yes Technical Contact jeff.diluccia@idfg.idaho.gov (208) 756-2271
Hannah Dondy-Kaplan Bonneville Power Administration Yes COR hadondy-kaplan@bpa.gov (503) 230-4071
Mike Edmondson Idaho Governor's Office of Species Conservation No Supervisor mike.edmondson@osc.idaho.gov (208) 334-2189
Abbie Gongloff Idaho Governor's Office of Species Conservation Yes Technical Contact abbie.gongloff@osc.idaho.gov (208) 756-6322
Amy Hines Idaho Governor's Office of Species Conservation Yes Contract Manager amy.hines@osc.idaho.gov (208) 332-1557
Eric (IDFG) Leitzinger Idaho Department of Fish and Game (IDFG) Yes Technical Contact eric.leitzinger@idfg.idaho.gov (208) 287-2798
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Stacey Meyer Idaho Department of Fish and Game (IDFG) Yes Technical Contact stacey.meyer@idfg.idaho.gov (208) 756-6022
Bob Minton Lemhi Soil and Water Conservation District (SWCD) No bobminton@hotmail.com (208) 756-4262
Gregory Smith Bonneville Power Administration Yes Env. Compliance Lead gmsmith@bpa.gov (503) 230-5049
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products B: 119. Manage and Administer Lemhi River Restoration Planning contract 05/31/2016 05/31/2016
All administrative tasks fulfilled with timely quality products C: 119. Manage and Administer Habitat Projects: Provide Project Implementation Support 05/31/2016 05/31/2016
Assist BPA's Environmental Compliance Lead to meet necessary environmental compliance requirem D: 165. Environmental Compliance: Lemhi River Restoration 05/31/2016 05/31/2016
Participate in local planning meetings as needed E: 191. Participate in local planning meetings as needed 05/31/2016 05/31/2016
Progress Report has been published F: 132. Submit Progress Report for the period (Jun 2015) to (May 2016) 05/31/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 06/01/2015
B 119 Manage and Administer Lemhi River Restoration Planning contract 06/01/2015
C 119 Manage and Administer Habitat Projects: Provide Project Implementation Support 06/01/2015
D 165 Environmental Compliance: Lemhi River Restoration 06/01/2015
E 191 Participate in local planning meetings as needed 06/01/2015
F 132 Submit Progress Report for the period (Jun 2015) to (May 2016) 06/01/2015