| All work complies with environmental regulations |
B: 165. Work with BPA on Environmental Compliance requirements. |
|
09/30/2016 |
09/30/2016 |
| Project administration requirements completed |
C: 119. Manage Project |
|
09/30/2016 |
09/30/2016 |
| Pesticide trend assessment in Hood River subbasin. |
D: 115. Pesticide assessment in Hood River Subbasin. |
|
09/30/2016 |
09/30/2016 |
| Hood River Watershed Group support |
E: 114. Provide implementation support |
|
09/30/2016 |
09/30/2016 |
| Riparian fences maintained. |
F: 186. Maintain riparian fences |
|
09/01/2016 |
09/01/2016 |
| Riparian spray buffers inspected. |
G: 47. Inspect riparian spray buffer planting projects. |
|
09/02/2016 |
09/02/2016 |
| EFID by-pass reach instream flow maintained. |
H: 154. Secure water instream. |
|
09/30/2016 |
09/30/2016 |
| Progress towards a hydro water lease with an irrigation district. |
I: 154. Irrigation District Water Transactions Assistance |
|
09/30/2016 |
09/30/2016 |
| Powerdale water right transferred instream. |
J: 154. Powerdale instream water right transfer |
|
09/30/2016 |
09/30/2016 |
| : Eight LWD placement projects inspected. |
K: 186. Inspect large wood placement projects. |
|
09/30/2016 |
09/30/2016 |
| 0.6 mile of fish habitat improved in West Fork Hood River |
L: 29. West Fork Red Hill Large Wood Placement – Phase 1. |
|
09/16/2016 |
08/30/2016 |
| Up to 256 mbf of fish logs procured and stockpiled. |
M: 29. Obtain logs for out year fish habitat restoration projects. |
|
09/30/2016 |
|
| Maintain vegetation under Big Eddy Power to 4 ft. high where it crosses West Fork Hood River |
N: 198. BPA Powerline Vegetation Maintenance |
|
08/01/2016 |
06/30/2016 |
| FY 2015 Annual Progress Report complete |
O: 132. Prepare and submit annual report for FY 15 work |
|
02/12/2016 |
02/12/2016 |
| Fish habitat improvement project in East Fork watershed planned |
P: 114. Identify and develop instream fish habitat improvement projects in East Fork watershed. |
|
09/30/2016 |
09/30/2016 |
| Fish habitat improvement project in Neal Creek planned. |
Q: 114. Identify and develop instream fish habitat improvement projects in Neal Creek. |
|
09/30/2016 |
09/30/2016 |
| Stream channel restored. |
R: 180. Odell Creek small hydro dam removal stream channel restoration. |
|
09/30/2016 |
09/23/2016 |
| Telemetry equipment installed at four sites in EFID. |
S: 148. East Fork Irrigation District Telemetry System Design and Construction |
|
09/30/2016 |
|
| 72 ft. long open arch culvert installed underneath Hudson Rd. along Evans Creek. |
T: 184. Replace culvert in Evans Creek. |
|
09/30/2016 |
09/30/2016 |