Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 70046: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Project Number:
Title:
Hood River Fish Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
70046
Contract Title:
1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Continuation:
Previous: Next:
66119: 1998-021-00 EXP HOOD RIVER FISH HABITAT
  • 73854: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Status:
Closed
Contract Description:
ADMINISTRATIVE SUMMARY
The Confederated Tribes of the Warm Springs Reservation of Oregon
Hood River Production Program
6030 Dee Highway
Parkdale, Oregon 97041
Fisheries Program Manager:  Brad Houslet (541) 553-2039
Fiscal Officer: Arthur Mitchell (541) 553-3219
Hood River Production Program Coordinator:  Chris Brun (541) 352-3548
Technical Contact:  Joe McCanna (541) 352-9326

FISCAL YEAR 2016

OBJECTIVE 1.  Provide coordination of all activities, administrative oversight, project planning and implementation activities

OBJECTIVE 2.  Coordinate and implement Hood River Watershed Action Plan.

OBJECTIVE 3. Continue  long term pesticide sampling in the Hood River subbasin.

OBJECTIVE 4. Partner with Columbia Gorge Fruit Growers to evaluate pesticide spray drift vegetative buffers.

OBJECTIVE 5. Procure logs for out year LWD projects in the event the USFS is unable to provide them.

OBJECTIVE 6.  Work with East Fork Irrigation District to design and install head gate telemetry system.

OBJECTIVE 7. Inspect previously implemented LWD project to determine if project goals have been met.

OBJECTIVE 8. Secure water  instream.

OBJECTIVE 9. Maintain existing riparian exclosure fences.

OBJECTIVE 10. Restore a portion of Odell Creek after removal of a small dam.

OBJECTIVE 11. Identify and develop stream restoration projects in the East Fork and Neal Creek watersheds.

Funds from this project will be contracted to the USFS to hire equipment and operators and haul logs / boulders to implement the Red Hill large wood placement project.

CCR 36055: Add Objective 11; Replace Evan's Creek culvert.
Modify Objective 5. Procure logs for out year LWD from the USFS.
Account Type(s):
Expense
Contract Start Date:
10/01/2015
Contract End Date:
09/30/2016
Current Contract Value:
$223,706
Expenditures:
$223,706

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All work complies with environmental regulations B: 165. Work with BPA on Environmental Compliance requirements. 09/30/2016 09/30/2016
Project administration requirements completed C: 119. Manage Project 09/30/2016 09/30/2016
Pesticide trend assessment in Hood River subbasin. D: 115. Pesticide assessment in Hood River Subbasin. 09/30/2016 09/30/2016
Hood River Watershed Group support E: 114. Provide implementation support 09/30/2016 09/30/2016
Riparian fences maintained. F: 186. Maintain riparian fences 09/01/2016 09/01/2016
Riparian spray buffers inspected. G: 47. Inspect riparian spray buffer planting projects. 09/02/2016 09/02/2016
EFID by-pass reach instream flow maintained. H: 154. Secure water instream. 09/30/2016 09/30/2016
Progress towards a hydro water lease with an irrigation district. I: 154. Irrigation District Water Transactions Assistance 09/30/2016 09/30/2016
Powerdale water right transferred instream. J: 154. Powerdale instream water right transfer 09/30/2016 09/30/2016
: Eight LWD placement projects inspected. K: 186. Inspect large wood placement projects. 09/30/2016 09/30/2016
0.6 mile of fish habitat improved in West Fork Hood River L: 29. West Fork Red Hill Large Wood Placement – Phase 1. 09/16/2016 08/30/2016
Up to 256 mbf of fish logs procured and stockpiled. M: 29. Obtain logs for out year fish habitat restoration projects. 09/30/2016
Maintain vegetation under Big Eddy Power to 4 ft. high where it crosses West Fork Hood River N: 198. BPA Powerline Vegetation Maintenance 08/01/2016 06/30/2016
FY 2015 Annual Progress Report complete O: 132. Prepare and submit annual report for FY 15 work 02/12/2016 02/12/2016
Fish habitat improvement project in East Fork watershed planned P: 114. Identify and develop instream fish habitat improvement projects in East Fork watershed. 09/30/2016 09/30/2016
Fish habitat improvement project in Neal Creek planned. Q: 114. Identify and develop instream fish habitat improvement projects in Neal Creek. 09/30/2016 09/30/2016
Stream channel restored. R: 180. Odell Creek small hydro dam removal stream channel restoration. 09/30/2016 09/23/2016
Telemetry equipment installed at four sites in EFID. S: 148. East Fork Irrigation District Telemetry System Design and Construction 09/30/2016
72 ft. long open arch culvert installed underneath Hudson Rd. along Evans Creek. T: 184. Replace culvert in Evans Creek. 09/30/2016 09/30/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 148 Install Flow Measuring Device
  • 3 instances of WE 154 Develop and Negotiate Water Right Transaction
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 184 Install Fish Passage Structure
  • 3 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 154 Develop and Negotiate Water Right Transaction
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 3 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 148 Install Flow Measuring Device
  • 3 instances of WE 154 Develop and Negotiate Water Right Transaction
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 148 Install Flow Measuring Device
  • 3 instances of WE 154 Develop and Negotiate Water Right Transaction
Lamprey, River (L. ayresi)
  • 1 instance of WE 115 Produce Inventory or Assessment
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2015
B 165 Work with BPA on Environmental Compliance requirements. 10/01/2015
C 119 Manage Project 10/01/2015
D 115 Pesticide assessment in Hood River Subbasin. 10/01/2015
E 114 Provide implementation support 10/01/2015
F 186 Maintain riparian fences 10/01/2015
G 47 Inspect riparian spray buffer planting projects. 10/01/2015
H 154 Secure water instream. 10/01/2015
I 154 Irrigation District Water Transactions Assistance 10/01/2015
J 154 Powerdale instream water right transfer 10/01/2015
K 186 Inspect large wood placement projects. 10/01/2015
L 29 West Fork Red Hill Large Wood Placement – Phase 1. 10/01/2015
M 29 Obtain logs for out year fish habitat restoration projects. 10/01/2015
N 198 BPA Powerline Vegetation Maintenance 10/01/2015
O 132 Prepare and submit annual report for FY 15 work 10/01/2015
P 114 Identify and develop instream fish habitat improvement projects in East Fork watershed. 10/01/2015
Q 114 Identify and develop instream fish habitat improvement projects in Neal Creek. 10/01/2015
R 180 Odell Creek small hydro dam removal stream channel restoration.
S 148 East Fork Irrigation District Telemetry System Design and Construction 10/01/2015
T 184 Replace culvert in Evans Creek.