| All work complies with environmental regulations |
B: 165. Work with BPA on Environmental Compliance requirements. |
|
09/30/2017 |
09/29/2017 |
| Project administration requirements completed |
C: 119. Manage Project |
|
09/30/2017 |
09/29/2017 |
| Hood River Watershed Group support |
D: 114. Provide implementation support |
|
09/29/2017 |
09/29/2017 |
| Riparian fences maintained. |
E: 186. Maintain riparian fences |
|
08/18/2017 |
07/14/2017 |
| Riparian spray buffers inspected. |
F: 47. Inspect riparian spray buffer planting projects. |
|
09/30/2017 |
09/29/2017 |
| EFID by-pass reach instream flow maintained. |
G: 154. Record East Fork stream flows in the EFID by-pass reach |
|
09/30/2017 |
09/29/2017 |
| Progress towards a hydro water lease with an irrigation district. |
H: 154. Facilitate completion of forbearance agreement with FID to protect water instream. |
|
09/30/2017 |
|
| Powerdale water right transferred instream. |
I: 154. Powerdale instream water right transfer |
|
09/30/2017 |
09/29/2017 |
| Evaluation of Dog River pipeline for water loss. |
J: 154. Evaluate City of The Dalles Dog River diversion and pipeline for water savings. |
|
09/30/2017 |
|
| Eight LWD placement projects inspected. |
K: 186. Inspect large wood placement projects. |
|
09/30/2017 |
09/29/2017 |
| 0.6 mile of fish habitat improved in West Fork Hood River |
L: 29. West Fork Red Hill Large Wood Placement – Phase II |
|
09/29/2017 |
09/22/2017 |
| 300 logs procured and stockpiled. |
M: 29. Obtain logs for out year fish habitat restoration projects. |
|
09/29/2017 |
09/29/2017 |
| 0.25 miles of fish habitat restored in Neal Creek |
N: 29. Neal Creek Large Wood Placement |
|
09/29/2017 |
|
| Maintain vegetation under Big Eddy Power to 4 ft. high where it crosses West Fork Hood River |
O: 198. BPA Powerline Vegetation Maintenance |
|
08/11/2017 |
06/30/2017 |
| Fish habitat project(s) developed for implementation in 2019. |
P: 114. Identify and develop instream fish habitat improvement projects in the Hood River watershed. |
|
09/30/2017 |
09/29/2017 |
| 2.5 miles of open irrigation ditch piped. |
Q: 203. East Fork Irrigation District - Highline Lateral Canal Piping Project |
|
09/29/2017 |
09/29/2017 |
| 72 ft. long open arch culvert installed underneath Hudson Rd. along Evans Creek. |
R: 184. Replace culvert in Evans Creek. |
|
09/29/2017 |
|
| FY 2016 Annual Progress Report complete |
S: 132. Prepare and submit annual report for FY 16 work |
|
02/12/2017 |
02/09/2017 |