Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 70742: 1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - SHOPAI
Project Number:
Title:
Southern Idaho Wildlife Mitigation--Shoshone-Paiute Tribes
Stage:
Implementation
Area:
Province Subbasin %
Middle Snake Owyhee 100.00%
Contract Number:
70742
Contract Title:
1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - SHOPAI
Contract Continuation:
Previous: Next:
66560: 1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - SHOPAI
  • 74845: 1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MIT.
Contract Status:
Closed
Contract Description:
Project Goal:
**This SOW is accepted with understanding that work elements referencing the NRCS management plan will not occur until The Tribe has provided the plan to BPA and BPA has provided concurrence***.

The objective of this project is to implement wildlife mitigation activities under the Southern Idaho Wildlife Mitigation Program in order to protect, enhance and/or restore and maintain  deciduous scrub-shrub wetland, shrubsteppe, deciduous shrubland, agriculture/pasture, and riverine habitats at suitable sites in the Middle Snake Province as mitigation for wildlife losses associated with the construction of  Anderson Ranch hydro-electric project.  Target fish and wildlife species include mule deer, elk, mallard, mink,  yellow warbler, bobolink, sandhill crane, Columbia spotted frog, greater sage-grouse and redband trout, . This contract has been developed to cover personnel, administrative, and operating costs related to the Wilson/101 Ranch.  

Property Background:

The Wilson Ranch is a 938 acre ranch located on the East Fork Owyhee River in Mountain City, Nevada. The ranch was purchased in November 2009 and  consists of six parcels. Habitats present on the ranch include sagebrush steppe, deciduous scrub-shrub wetland, riverine, and agriculture/pasture. The property was purchased as partial mitigation for wildlife habitat lost due to the construction and inundation of Anderson Ranch Dam and Reservoir in the Middle Snake Province.

During the FY2016 contract period the Tribes will focus on: (1) continuing to implement the Weed Management Strategy for the property,  (2) implement a  bank stabilization project on the East Fork Owyhee River,  (3) begin development of a native plant propagation program,  and (4) begin implementation of Vegetation Management Plan for the ranch.
Account Type(s):
Expense
Contract Start Date:
10/01/2015
Contract End Date:
09/30/2016
Current Contract Value:
$155,602
Expenditures:
$155,602

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Cecilia Brown Bonneville Power Administration Yes COR ckbrown@bpa.gov (503) 230-3462
Lisa Dexter Bonneville Power Administration No Interested Party lldexter@bpa.gov (503) 230-3893
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Carol Perugini Shoshone-Paiute Tribes Yes Contract Manager perugini.carol@shopai.org (775) 763-6015
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Kristin Scheidt Bonneville Power Administration No Technical Contact kmscheidt@bpa.gov (503) 230-3918
Jinwon Seo Shoshone-Paiute Tribes No Supervisor seo.jinwon@shopai.org (208) 759-3246
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Receipt of EC documentation/clearance from BPA A: 165. Satisfy environmental compliance requirements 05/31/2016 05/05/2016
Complete project administration B: 119. Project administration 09/30/2016 09/30/2016
Completed Annual Report C: 132. Submit Progress Report for the period (10/1/2014 to 9/30/2015) 04/01/2016 05/03/2016
Investigate and Address Trespass D: 26. Prevent trespass on property and USFS allotment 09/30/2016 09/30/2016
Construction of permanent fence to protect California Creek E: 40. Construct permanent fence to protect California Creek on Ratliff parcel 09/30/2016 06/15/2016
Property and facilities maintained F: 186. Maintain structures, facilities and property 09/30/2016 09/30/2016
Willow poles/willow weavings planted along a stretch of the East Fork Owyhee River at Home Parcel G: 47. Implement bank stabilization project on section of East Fork Owyhee River on Home Parcel 09/30/2016
Upload income-production report for calendar year 2015 to Pisces H: 194. Documentation of income-producing activities on Wilson/101 Ranch 04/30/2016 04/14/2016
Fences/Diversions Water Developments O&M Completed I: 186. Maintain Fences/Water Developments/Diversions 09/30/2016 09/02/2016
Native seed collected from at least 4 forbs, 3 grasses and 3 shrubs J: 47. Implement pilot native seed collection activities 09/30/2016 09/14/2016
Implement Weed Treatment Strategies on wildlife area K: 115. Document locations of noxious weeds, update weed management strategy 09/30/2016 09/30/2016
Weed Treatment Records L: 198. Implement weed treatment strategy on Angell Parcel 09/30/2016 09/30/2016
Weed Treatment Records M: 198. Implement weed treatment strategy on Baker Parcel 09/30/2016 09/30/2016
Weed Treatment Records N: 198. Implement weed treatment strategy on Bend Parcel 09/30/2016 09/30/2016
Weed Treatment Records O: 198. Implement weed treatment strategy on Home Parcel 09/30/2016 09/30/2016
Weed Treatment Records P: 198. Implement weed treatment strategy on Ratliff Parcel 09/30/2016 09/30/2016
Weed Treatment Records Q: 198. Implement weed treatment strategy on McGinnes Parcel 09/30/2016 09/30/2016
Columbia Spotted Frog survey results R: 115. Conduct Columbia spotted frog surveys 09/30/2016 09/30/2016
Vegetation activities completed S: 198. Implement NRCS Vegetation Management Plan on Angell Parcel 09/30/2016 09/30/2016
Vegetation activities completed T: 198. Implement NRCS Vegetation Management Plan on Baker Parcel 09/30/2016 07/29/2016
Vegetation activities completed U: 198. Implement NRCS Vegetation Management Plan on Bend Parcel 09/30/2016 09/19/2016
Vegetation activities completed V: 198. Implement NRCS Vegetation Management Plan on Home Parcel 09/30/2016 09/30/2016
Vegetation activities completed W: 198. Implement NRCS Vegetation Management Plan on McGinnes Parcel 09/30/2016 07/29/2016
Vegetation activities completed X: 198. Implement NRCS Vegetation Management Plan on Ratliff Parcel 09/30/2016
Debris Removed Y: 27. Remove debris from Ratliff parcel SW of California Creek 09/30/2016 07/19/2016
Complete Public Outreach Z: 99. Public Outreach 09/30/2016 09/30/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 47 Plant Vegetation
Wildlife
  • 12 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 27 Remove Debris
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 2 instances of WE 115 Produce Inventory or Assessment

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Satisfy environmental compliance requirements 10/01/2015
B 119 Project administration 10/01/2015
C 132 Submit Progress Report for the period (10/1/2014 to 9/30/2015) 10/01/2015
D 26 Prevent trespass on property and USFS allotment 10/01/2015
E 40 Construct permanent fence to protect California Creek on Ratliff parcel 05/11/2016
F 186 Maintain structures, facilities and property 10/01/2015
G 47 Implement bank stabilization project on section of East Fork Owyhee River on Home Parcel 10/01/2015
H 194 Documentation of income-producing activities on Wilson/101 Ranch 10/01/2015
I 186 Maintain Fences/Water Developments/Diversions 05/11/2016
J 47 Implement pilot native seed collection activities 10/01/2015
K 115 Document locations of noxious weeds, update weed management strategy 10/01/2015
L 198 Implement weed treatment strategy on Angell Parcel 10/01/2015
M 198 Implement weed treatment strategy on Baker Parcel 10/01/2015
N 198 Implement weed treatment strategy on Bend Parcel 10/01/2015
O 198 Implement weed treatment strategy on Home Parcel 10/01/2015
P 198 Implement weed treatment strategy on Ratliff Parcel 10/01/2015
Q 198 Implement weed treatment strategy on McGinnes Parcel 10/01/2015
R 115 Conduct Columbia spotted frog surveys 10/01/2015
S 198 Implement NRCS Vegetation Management Plan on Angell Parcel 05/11/2016
T 198 Implement NRCS Vegetation Management Plan on Baker Parcel 05/11/2016
U 198 Implement NRCS Vegetation Management Plan on Bend Parcel 05/11/2016
V 198 Implement NRCS Vegetation Management Plan on Home Parcel 05/11/2016
W 198 Implement NRCS Vegetation Management Plan on McGinnes Parcel 05/11/2016
X 198 Implement NRCS Vegetation Management Plan on Ratliff Parcel 05/11/2016
Y 27 Remove debris from Ratliff parcel SW of California Creek 05/11/2016
Z 99 Public Outreach 10/01/2015
AA 185 Periodic Status Reports for BPA 10/01/2015