Close Message
CBFish website will be offline for approximately one hour starting at 5 PM today for maintenance. Thank you for your patience.
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 71619: 2007-397-00 EXP JOHN DAY TRIB/PASS & FLOW
Project Number:
Title:
John Day Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
71619
Contract Title:
2007-397-00 EXP JOHN DAY TRIB/PASS & FLOW
Contract Continuation:
Previous: Next:
64905: 2007-397-00 CAP JOHN DAY TRIB/PASS & FLOW
  • 78267: 2007-397-00 EXP JOHN DAY TRIB/PASS & FLOW
Contract Status:
Closed
Contract Description:
The goal of this project is to address limiting factors by implementing restoration actions that protect and restore passage, flow, and habitat for anadromous fish and listed species in the John Day River Basin.  This includes use of the John Day Basin Watershed Restoration Strategy to assist the Confederated Tribes of Warm Springs Reservation of Oregon (CTWSRO),  John Day Basin Office, John Day Watershed Restoration Program with the ability to focus on implementing suites of restoration actions that will more effectively identify and address priority limiting factors.

In addition to addressing limiting factors outlined in the 2008 FCRPS BiOp, the primary goal of the CTWSRO, Fisheries Habitat Restoration Program is to protect, manage, and restore aquatic habitats in Reservation watersheds.  CTWSRO defines protect, manage and restore as:

1. Protect existing high-quality habitats that have functioning ecological processes;
2. Manage future land use through an integrated planning process to promote ecological integrity and sustainability; and
3. Restore watersheds and habitats using a prioritized approach based on limiting factors analysis.

In 1855, the Confederated Tribes of the Warm Springs Reservation of Oregon (CTWSRO) ceded a majority of the John Day basin to the Federal government.  In 1997, the Tribes established an office in the basin to coordinate restoration projects, monitoring, planning and other watershed activities on private and public lands.  Once established, the John Day Basin Office (JDBO) formed partnerships with local agencies and stakeholders to implement restoration activities from the John Day Basin Office and Watershed Restoration Program.

The John Day River basin is within the CTWSRO ceded lands and supporting restoration efforts such as this project is an important part of maintaining cultural foods and fish populations.  The mission of the CTWSRO Branch of Natural Resources Fisheries Department is to provide fisheries populations at harvestable levels for tribal members using information gained from research, management, production, and habitat programs while exercising our co-management authority across ceded lands and usual and accustomed stations.

The John Day is the nation’s second longest free-flowing river in the contiguous United States and the longest containing entirely un-supplemented runs of anadromous fish.  Located in eastern Oregon, the basin drains over 8,000 square miles, Oregon's fourth largest drainage basin, and incorporates portions of eleven counties.  Originating in the Strawberry Mountains near Prairie City, the John Day River flows 284 miles in a northwesterly direction, entering the Columbia River approximately four miles upstream of the John Day dam.  With wild runs of spring Chinook salmon and summer steelhead, westslope cutthroat, and redband and bull trout, the John Day system is truly a basin with national significance.

The John Day Watershed Restoration Program (JDWR) is an on-going, multi-agency program that has historically focused on inefficient, detrimental land-use practices and implemented irrigation system upgrades, diversion passage improvements, upland restoration, and riparian fencing and planting.  The Program’s objectives include removing fish passage impediments, increasing water flows, increasing water quality, and enhancing riparian and stream channel recovery.  Though benefits most readily apply to fish species, the cumulative effects apply to basin-wide watershed recovery.

Projects implemented by the JDWR under this contract are intended to increase in-season river flows through a combination of irrigation efficiency measures; reduce bank instability, sedimentation, bed load movement, and summer passage impediments; improve riparian condition; and implement an annual monitoring program evaluating each of the projects.  These projects respond directly to, and are consistent with, tribal, state, and federal goals and objectives within the region's plans and programs.  Previous projects of these types have demonstrated success in addressing limiting factors identified for salmonid production in the basin.  They follow comprehensive assessments of the watershed, the John Day Subbasin plan and Mid-Columbia Steelhead Recovery Plan.  The benefits are to entirely wild stocks and associated habitats.  Each project utilizes standard design criteria, and was selected using an evaluation and prioritization process.  The effects of individual projects have been evaluated as to short and long term beneficial and/or adverse effects on aquatic and terrestrial species.

For project implementation the JDWR has worked with local SWCDs, Watershed Councils, and other agencies to complete landowner contacts, preliminary planning, engineering designs, permitting, construction contracting, and construction implementation phases.  The JDWR has worked to complete the planning, grant solicitation/defense, environmental compliance, administrative contracting, monitoring, juniper removal contracting, water development implementation, riparian planting, and reporting for the program.  Most phases of project planning, implementation, and monitoring are coordinated with the private landowners and basin agencies, such as the Oregon Department of Fish and Wildlife (ODFW) and Oregon Water Resources Department.  The projects implemented through the JDWR are strictly voluntary and the majority on private land, these multi-agency partnerships are essential to local support and private landowner involvement.  Project efforts rely and build adaptively upon previous and ongoing activities. The overall restoration program appears to have resulted in some significant successes, in particular with spawning and rearing of spring Chinook on private lands.

Through the Accord period (2008-2017) active restoration projects have and will be implemented throughout the John Day Basin, through the CTWSRO JDWR under this contract.  Actions going forward from 2014 will be prioritized through a scientific and stakeholder technical advisory team and based on an implementation strategy.
Account Type(s):
Expense
Contract Start Date:
02/01/2016
Contract End Date:
01/31/2018
Current Contract Value:
$4,684,131
Expenditures:
$4,684,131

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Amy Charette Confederated Tribes of Warm Springs Yes Contract Manager amy.charette@ctwsbnr.org (541) 575-1866
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Allison Field Confederated Tribes of Warm Springs No Technical Contact allison.field@ctwsbnr.org (541) 777-2841
Allen Gillette Confederated Tribes of Warm Springs Yes Technical Contact allen.gillette@ctwsbnr.org (541) 575-1866
Brad Houslet Confederated Tribes of Warm Springs No Interested Party brad.houslet@ctwsbnr.org (541) 553-2039
Dennis Johnson Confederated Tribes of Warm Springs No Interested Party dennis.johnson@wstribes.org (541) 553-3479
Joseph Lemanski Confederated Tribes of Warm Springs Yes Technical Contact joe.lemanski@ctwsbnr.org (248) 408-4074
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Arthur Mitchell Confederated Tribes of Warm Springs No Administrative Contact arthur.mitchell@wstribes.org (541) 553-3219
Wendy Neal Confederated Tribes of Warm Springs Yes Technical Contact wendy.neal@ctwsbnr.org (541) 575-1866
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Nicholas Smith Confederated Tribes of Warm Springs Yes Technical Contact nicholas.smith@ctwsbnr.org (541) 620-1496
Scott Turo Confederated Tribes of Warm Springs Yes Supervisor scott.turo@ctwsbnr.org (541) 553-2025
Sean Welch Bonneville Power Administration No Interested Party spwelch@bpa.gov (503) 230-7691
Jesse Wilson Bonneville Power Administration Yes COR jcwilson@bpa.gov (503) 230-4506
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Coordination with John Day Partners, Project Selection, and Prioritization A: 114. Project Selection and Prioritization 01/31/2018 01/31/2018
BPA Project Administration Requirements B: 119. Manage Administer Projects 01/31/2018 01/31/2018
Completed Environmental Compliance Documentation C: 165. 2016 Documents 01/31/2017 01/31/2017
Completed Environmental Compliance Documentation D: 165. 2017 Documents 01/31/2018 01/31/2018
Completed Annual Report F: 132. Submit Annual Report for the Period (02/01/2014) to (01/31/2016) 12/31/2016 12/31/2016
Education and Community Relations G: 99. Fair Booths/Community Education and Participation/ School Presentations 01/31/2018 01/31/2018
Data for Compliance, Status and Trend, and Effectiveness Monitoring H: 157. Implementation/Effectiveness Monitoring 01/31/2018 01/31/2018
Data for Compliance, Status and Trend, and Effectiveness Monitoring I: 157. John Day Temperature Status and Trends 01/31/2018 01/31/2018
Flow Data Available on USGS Website J: 157. Middle Fork Gaging Station Operation and Maintenance 01/31/2018 01/31/2018
Rock Creek PIT Tagging K: 158. Rock Creek PIT Tag Array 09/30/2017 09/30/2017
Middle Fork John Day PIT Tagging L: 158. Steelhead Fry and Habitat Research 09/30/2017 09/30/2017
IDIQ Contract M: 122. IDIQ Engineering Support 01/31/2018 01/31/2018
John Day Partnership N: 191. John Day Partnership 01/31/2018 01/31/2018
Easement Management Plan P: 193. Canyon Ranch Easement Management Plan 09/30/2017 01/31/2018
Construct RPB Easement Fence Q: 40. RPB Easement Fence 01/31/2018 10/15/2016
Project Design for Pope Moon Creek Restoration R: 175. Design - Pope Moon Creek 12/31/2016 06/30/2016
Project Design for Dovenberg Habitat Improvement V: 175. Design - Dovenberg Habitat Improvement 04/30/2017 08/30/2016
Dovenberg Habitat Improvement W: 29. Dovenberg Habitat Improvement 12/31/2017 08/31/2016
Project Design for Starr Habitat and Diversion X: 175. Design - Starr Habitat and Diversion 12/31/2016 07/25/2016
Design and Implement a Log and Boulder Revetment and Instream Habitat Complexity Y: 29. Starr Habitat and Diversion: Instream Habitat 12/31/2016 07/25/2016
Starr Habitat and Diversion: Side Channel Creation Z: 30. Starr Habitat and Diversion: Side Channel Creation 12/31/2016 10/01/2016
Starr Habitat and Diversion: Pump Station AA: 84. Starr Habitat and Diversion; Pump Station 12/31/2016 10/01/2016
Breech Railroad Grade in Floodplain AB: 180. Dunstan Preserve Flood Plain Enhancement: Phase Two 12/31/2017
TNC Riparian Planting and Maintenance AC: 47. TNC Riparian Planting and Maintenance 01/31/2018 12/31/2017
Mullin Phase 2 Juniper Removal AD: 199. Mullin Phase 2 Juniper Removal 01/31/2018 12/31/2017
Mascall Phase 2 Juniper Removal AE: 199. Mascall Phase 2 Juniper Removal 01/31/2018 12/31/2017
Lemons Phase 2 Juniper Removal AF: 199. Lemons Phase 2 Juniper Removal 01/31/2018 12/31/2017
Planting and Maintenance AG: 198. Beech Creek Riparian Planting and Maintenance 01/31/2018 12/31/2017
Planting and Maintenance AH: 198. Izee Riparian Planting and Maintenance 01/31/2018 12/31/2017
Planting and Maintenance AI: 47. Bridge/Bear Creek Riparian Planting 12/31/2017 12/31/2017
Project Selection AJ: 114. Program Support 01/31/2018 01/31/2018
Project Design for Olex Diversion and Restoration AK: 175. Design Olex Diversion and Stream Restoration 12/31/2017 07/31/2017
Design and Implement Instream Habitat Complexity on Rock Creek AL: 29. Olex Diversion Stream Restoration: Instream Habitat Complexity 12/31/2017
Design and Implement Removal of Passage Barrier on Rock Creek AM: 84. Olex Diversion Stream Restoration: Passage Barrier Removal 12/31/2017
Project Design for Hewes Diversion and Stream Restoration AN: 175. Design Hewes Diversion and Stream Restoration 12/31/2017 06/01/2017
Project Design for Harper Diversion and Stream Restoration AQ: 175. Design Harper Diversion and Stream Restoration 12/31/2017 07/31/2017
Design and Implement Instream Habitat Complexity at Diversion Removal Site AR: 29. Harper Diversion Stream Restoration: Instream Habitat Complexity 12/31/2017 12/31/2017
Design and Implement Removal of Passage Barrier on Rock Creek AS: 84. Harper Diversion Stream Restoration: Diversion Removal 12/31/2017 12/31/2017
Thirtymile PIT Tag Array AT: 70. Thirtymile Creek Steelhead PIT Tag Monitoring 09/30/2017 02/01/2016
Weed Control AU: 199. Noxious Weed Control at Project Sites 01/31/2018 01/31/2018
Project Design for Larson: One Canyon and Three Berry Creek Push-up Dam Replacements AV: 175. Design - Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements 12/31/2017 07/31/2017
Design and Replace Four Push-Up Dams on Canyon and Berry Creeks AW: 84. Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements 12/31/2017 09/30/2017
Henslee Fox Creek Habitat (Design) AY: 175. Design - Henslee Fox Creek Habitat 01/31/2018
McGirr Fox Creek Habitat & Passage AZ: 175. Design - McGirr Fox Creek Habitat & Passage 01/31/2018
Cavender Riparian Habitat and Wetland Habitat Protection BB: 180. Cavender Riparian Habitat and Wetland Habitat Protection 12/31/2017 11/15/2016
Design and Implement Instream Habitat Work on Bridge Creek BD: 29. Bridge Creek Holistic Restoration 12/31/2017 12/31/2017
Rock Creek Habitat Assessment BE: 115. Rock Creek Reach Assessment 11/30/2017 11/30/2017
Upper Rock Creek Watershed Enhancement BF: 199. Upper Rock Creek Watershed Enhancement 01/31/2018 01/31/2018
Design Review BG: 175. Design Review of Projects not covered by HIP III 01/31/2018 01/31/2018
East Fork Beech Creek Instream and Floodplain Wood Project BH: 29. East Fork Beech Creek Wood #1 12/31/2017 09/30/2017
Squaw Creek Meadow Restoration: Phase 2: Meadow Restoration BI: 30. Squaw Creek Meadow Restoration: Phase 2: Meadow Restoration 12/31/2016 09/30/2016
Squaw Creek Restoration: Phase 2: Instream Habitat BJ: 29. Squaw Creek Meadow Restoration: Phase 2: Instream Habitat 12/31/2016 09/30/2016
Camp Creek Headwater Restoration: Instream Habitat BK: 29. Camp Creek Headwater Restoration: Instream Habitat 12/31/2016 09/30/2016
Camp Creek Headwaters Restoration: Riparian Plantings BL: 47. Camp Creek Headwaters Restoration: Riparian Plantings 12/31/2016 09/30/2016
MFJDR Galena Tailings Design BM: 175. Design - MFJDR Galena Tailings 01/31/2018 01/31/2018
John Day River and Reynolds Creek Project Design BN: 175. Design - John Day River and Reynolds Creek Habitat 01/31/2018 01/31/2018
Completed Annual Report CC: 132. Submit Annual Report for the Period (2/1/2010) to (1/31/2014) 12/31/2016 12/31/2016
South Fork John Day Riparian Planting CE: 47. Tier 2: South Fork John Day Riparian Planting 01/31/2018 12/31/2017
Complete Technical Memorandum CF: 162. Dunstan Groundwater Well Analysis 06/30/2017 06/30/2017
Design of Cottonwood Creek Basin WASCOBs CG: 175. Design Cottonwood Sediment Control 12/31/2017 12/31/2017
Produce Design CH: 175. Design Fox Creek Habitat 10/31/2017 09/30/2017
Produce Design CI: 175. Design Rock Creek Diversion 12/31/2017
Install Pipeline CJ: 203. Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements - Pipeline 04/30/2017 12/01/2016
Install bridge, fencing, water development, and riparian planting CK: 184. CCR-38546 Upper John Day River Crossing 12/15/2017 12/15/2017
Produce accessible, error-checked datasets CL: 157. CCR-38546 Collection of Fish Data (Biological, Physical, Demographic) 01/31/2018
Complete Mark-Recapture Activities, will be determined when abundance is known. CM: 158. CCR-38546 Mark-Recapture Studies 01/31/2018
Data Analysis CN: 162. CCR-38546 Analysis and Interpretation of Field Data Collected from Fisheries Surveys 01/31/2018
Fox Creek Design Reach 18 CO: 175. CCR-38546 Fox Creek Design Reach 18 Instream Restoration 01/31/2018 01/31/2018
Harvest Whole Trees for Instream Restoration Work CP: 199. CCR-38546 Fox Creek Harvest Whole Trees for Instream Restoration 01/31/2018 12/31/2017
Remove Juniper CQ: 199. CCR-38546 Fox Creek Juniper Removal 01/31/2018 12/31/2017
Planting Plan CR: 174. CCR-38546 Fox Creek Vegetation and Planting Plan 01/31/2018 12/31/2017
Fox Creek Mid Reach 10 Habitat Project Phase 1 CS: 30. CCR-38546 Fox Creek Mid Reach 10 Habitat Restoration, Phase 1 01/31/2018
Pre-acquisition Activities CT: 172. CCR-38546 Pre-Acquisition Activities for GSG Easement 01/30/2018
Project Development and Data Management CU: 98. CCR-38546 JDBO Project Development and Data Management 01/31/2018 01/31/2018
Conduct Lonerock Ridge Juniper Project CV: 199. CCR-38546 Lonerock Ridge Juniper Project 01/31/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 8 instances of WE 199 Remove Vegetation
  • 2 instances of WE 198 Maintain Vegetation
  • 3 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 193 Produce Land Management Plan
  • 14 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 40 Install Fence
  • 5 instances of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 3 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 8 instances of WE 84 Remove/Install Diversion
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 184 Install Fish Passage Structure
  • 2 instances of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 98 Other
  • 2 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan
  • 19 instances of WE 175 Produce Design
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 158 Mark/Tag Animals
  • 2 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 9 instances of WE 199 Remove Vegetation
  • 2 instances of WE 198 Maintain Vegetation
  • 3 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 193 Produce Land Management Plan
  • 14 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 4 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 40 Install Fence
  • 5 instances of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 3 instances of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 8 instances of WE 84 Remove/Install Diversion
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 184 Install Fish Passage Structure
  • 2 instances of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 98 Other
  • 2 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan
  • 19 instances of WE 175 Produce Design
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 158 Mark/Tag Animals
  • 2 instances of WE 162 Analyze/Interpret Data
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 199 Remove Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 114 Project Selection and Prioritization 02/01/2016
B 119 Manage Administer Projects 02/01/2016
C 165 2016 Documents 02/01/2016
D 165 2017 Documents 02/01/2016
E 185 Periodic Status Reports for BPA 02/01/2016
F 132 Submit Annual Report for the Period (02/01/2014) to (01/31/2016) 02/01/2016
G 99 Fair Booths/Community Education and Participation/ School Presentations 02/01/2016
H 157 Implementation/Effectiveness Monitoring 02/01/2016
I 157 John Day Temperature Status and Trends 02/01/2016
J 157 Middle Fork Gaging Station Operation and Maintenance 02/01/2016
K 158 Rock Creek PIT Tag Array 02/01/2016
L 158 Steelhead Fry and Habitat Research 02/01/2016
M 122 IDIQ Engineering Support 02/01/2016
N 191 John Day Partnership 02/01/2016
O 172 Canyon Ranch Easement Pre-Acquisition Activities 02/01/2016
P 193 Canyon Ranch Easement Management Plan
Q 40 RPB Easement Fence 04/15/2016
R 175 Design - Pope Moon Creek
S 29 Pope Moon Creek Restoration: Instream Habitat - Canceled
T 85 Pope Moon Creek Restoration : Bridge - Canceled
U 203 Pope Moon Creek Restoration: Pipeline - Canceled
V 175 Design - Dovenberg Habitat Improvement 08/15/2016
W 29 Dovenberg Habitat Improvement 08/15/2016
X 175 Design - Starr Habitat and Diversion 08/15/2016
Y 29 Starr Habitat and Diversion: Instream Habitat 07/25/2016
Z 30 Starr Habitat and Diversion: Side Channel Creation 07/25/2016
AA 84 Starr Habitat and Diversion; Pump Station 07/25/2016
AB 180 Dunstan Preserve Flood Plain Enhancement: Phase Two
AC 47 TNC Riparian Planting and Maintenance 06/13/2016
AD 199 Mullin Phase 2 Juniper Removal 04/15/2016
AE 199 Mascall Phase 2 Juniper Removal 04/14/2016
AF 199 Lemons Phase 2 Juniper Removal 04/14/2016
AG 198 Beech Creek Riparian Planting and Maintenance 04/22/2016
AH 198 Izee Riparian Planting and Maintenance 04/22/2016
AI 47 Bridge/Bear Creek Riparian Planting 04/22/2016
AJ 114 Program Support 02/01/2016
AK 175 Design Olex Diversion and Stream Restoration 08/08/2017
AL 29 Olex Diversion Stream Restoration: Instream Habitat Complexity 07/19/2017
AM 84 Olex Diversion Stream Restoration: Passage Barrier Removal 07/18/2017
AN 175 Design Hewes Diversion and Stream Restoration
AO 29 Hewes Diversion Stream Restoration: Instream Habitat Complexity
AP 84 Hewes Diversion Stream Restoration: Diversion Removal
AQ 175 Design Harper Diversion and Stream Restoration 07/19/2017
AR 29 Harper Diversion Stream Restoration: Instream Habitat Complexity 07/19/2017
AS 84 Harper Diversion Stream Restoration: Diversion Removal 07/19/2017
AT 70 Thirtymile Creek Steelhead PIT Tag Monitoring 04/14/2016
AU 199 Noxious Weed Control at Project Sites 04/22/2016
AV 175 Design - Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements 05/15/2017
AW 84 Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements 06/28/2017
AX 175 Design - Lemons Infiltration Gallery
AY 175 Design - Henslee Fox Creek Habitat
AZ 175 Design - McGirr Fox Creek Habitat & Passage
BA 175 Design - Blue Mountain Diversion Adaptive Management
BB 180 Cavender Riparian Habitat and Wetland Habitat Protection 06/30/2016
BC 55 Cottonwood Sediment Control
BD 29 Bridge Creek Holistic Restoration 08/14/2017
BE 115 Rock Creek Reach Assessment 04/14/2016
BF 199 Upper Rock Creek Watershed Enhancement 08/08/2017
BG 175 Design Review of Projects not covered by HIP III 06/14/2016
BH 29 East Fork Beech Creek Wood #1 07/17/2018
BI 30 Squaw Creek Meadow Restoration: Phase 2: Meadow Restoration 06/09/2016
BJ 29 Squaw Creek Meadow Restoration: Phase 2: Instream Habitat 06/14/2016
BK 29 Camp Creek Headwater Restoration: Instream Habitat 06/09/2016
BL 47 Camp Creek Headwaters Restoration: Riparian Plantings 06/09/2016
BM 175 Design - MFJDR Galena Tailings 01/31/2019
BN 175 Design - John Day River and Reynolds Creek Habitat 02/01/2016
BO 29 Tier 2. Holliday Bank Stabilization/Instream Habitat
BP 47 Tier 2: John Day Native Hardwood Planting #2
BQ 29 Tier 2: Big Creek Mining Levee Removal: Instream Habitat
BR 30 Tier 2: Big Creek Mining Levee Removal: Create Side Channels
BS 180 Tier 2: Big Creek Mining Levee Removal: Levee Removal
BT 33 Tier 2: Mallory Creek Road Re-Route
BU 84 Tier 2: Badger Creek Diversion #4: Passage Barrier Removal
BV 84 Tier 2: Badger Creek Diversion #5: Passage Barrier Removal
BW 84 Tier 2: Badger Creek Diversion #6: Passage Barrier Removal
BX 29 Tier 2: Derr Meadow Habitat
BY 203 Tier 2: Upper Badger Creek Pipeline
BZ 175 Design - Tier 2: Badger Creek Habitat #1 TA
CA 199 Tier 2: Middle Bear Creek Watershed Improvement
CB 29 Tier 2: Pine Hollow Restoration Project
CC 132 Submit Annual Report for the Period (2/1/2010) to (1/31/2014) 02/01/2016
CD 85 Tier 2: Boundary Creek Culverts: Fish Passage
CE 47 Tier 2: South Fork John Day Riparian Planting 09/01/2017
CF 162 Dunstan Groundwater Well Analysis 02/01/2016
CG 175 Design Cottonwood Sediment Control 07/31/2017
CH 175 Design Fox Creek Habitat 09/30/2017
CI 175 Design Rock Creek Diversion
CJ 203 Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements - Pipeline 07/14/2017
CK 184 CCR-38546 Upper John Day River Crossing 08/28/2017
CL 157 CCR-38546 Collection of Fish Data (Biological, Physical, Demographic)
CM 158 CCR-38546 Mark-Recapture Studies
CN 162 CCR-38546 Analysis and Interpretation of Field Data Collected from Fisheries Surveys 02/01/2016
CO 175 CCR-38546 Fox Creek Design Reach 18 Instream Restoration
CP 199 CCR-38546 Fox Creek Harvest Whole Trees for Instream Restoration 02/01/2018
CQ 199 CCR-38546 Fox Creek Juniper Removal 02/01/2018
CR 174 CCR-38546 Fox Creek Vegetation and Planting Plan 05/12/2017
CS 30 CCR-38546 Fox Creek Mid Reach 10 Habitat Restoration, Phase 1 01/23/2018
CT 172 CCR-38546 Pre-Acquisition Activities for GSG Easement 02/01/2016
CU 98 CCR-38546 JDBO Project Development and Data Management 05/12/2017
CV 199 CCR-38546 Lonerock Ridge Juniper Project