| Coordination with John Day Partners, Project Selection, and Prioritization |
A: 114. Project Selection and Prioritization |
|
01/31/2015 |
01/31/2015 |
| BPA Project Administration Requirements |
B: 119. Manage Administer Projects |
|
01/31/2016 |
01/29/2016 |
| Produce All Required NEPA Documents |
C: 165. Produce Environmental Compliance Documentation - 2014 - 2015 |
|
01/31/2016 |
01/29/2016 |
| Jacobs Lower Island Ditch Diversion |
D: 84. Jacobs Lower Island Ditch Diversion |
|
11/30/2015 |
09/30/2015 |
| Voigt Lower Clear Creek Diversion |
F: 84. Voigt Lower Clear Creek Diversion |
|
11/30/2015 |
09/30/2015 |
| Baucum Passage Improvements |
G: 184. Baucum Passage Improvements |
|
10/31/2015 |
12/31/2014 |
| Enterprise Passage Improvements |
H: 184. Enterprise Passage Improvements |
|
10/31/2014 |
10/31/2014 |
| Submit Drawings and/or Specifications to BPA |
J: 175. Ricco: Eight John Day River Push-up Dam Replacements Designs |
|
01/31/2016 |
09/30/2015 |
| Jacobs Roberts Creek Diversion Head Wall and Check Sill |
L: 184. Jacobs Roberts Creek Diversion |
|
12/31/2015 |
09/30/2015 |
| Submit Drawings and/or Specifications to BPA |
M: 175. Design of Nine Diversion Projects |
|
12/31/2015 |
09/30/2015 |
| Weed Control |
N: 199. Noxious Weed Control at Project Sites |
|
11/30/2015 |
|
| Mountain Creek Water Quality |
O: 29. Mountain Creek Water Quality |
|
10/31/2014 |
10/31/2014 |
| Mountain/Indian Creek Culvert Replacements |
P: 85. Mountain/Indian Creek Culvert Replacements |
|
12/31/2014 |
12/31/2014 |
| Indian Creek Diversion and Pipeline |
Q: 84. Indian Creek Diversion and Pipeline |
|
10/31/2015 |
09/30/2015 |
| Replace Diversion |
R: 84. Badger Creek #3 Diversion |
|
10/31/2015 |
09/30/2015 |
| Mountain Creek Restoration Phase 4 |
S: 29. Mountain Creek Restoration Phase 4 |
|
10/31/2014 |
10/31/2014 |
| Bridge-Bear Habitat Phase #3 |
T: 29. Bridge-Bear Habitat Phase #3 |
|
12/31/2014 |
12/31/2014 |
| Badger Creek Habitat #2 |
U: 29. Badger Creek Habitat #2 |
|
11/30/2014 |
11/30/2014 |
| Butte Creek Culvert Replacements |
V: 85. Butte Creek-Hoover Culverts |
|
10/31/2015 |
09/30/2015 |
| Hashknife Juniper |
W: 199. Hashknife Juniper |
|
01/31/2016 |
01/29/2016 |
| Bear Creek Juniper Removal |
X: 199. Bear Creek Juniper |
|
01/31/2016 |
01/29/2016 |
| Remove Fish Passage Structure |
Y: 84. Bettencourt/Olson Diversion |
|
11/30/2014 |
11/30/2014 |
| Replace Diversion |
Z: 84. Lonerock/Campbell Diversion |
|
10/31/2015 |
10/31/2015 |
| Replace Culvert |
AA: 184. Lonerock Culvert #2 Brown |
|
10/31/2014 |
10/31/2014 |
| Replace Culvert |
AB: 184. Lonerock Culvert #1 Buckhorn |
|
10/31/2014 |
10/31/2014 |
| Eliminate fish passage issues caused by the Deer Creek culvert |
AD: 85. Deer Creek Culvert Replacement |
|
09/30/2015 |
09/30/2015 |
| Install Pipeline |
AE: 149. Osburn Pipeline Phase 2 |
|
12/31/2015 |
12/31/2015 |
| Lower Cottonwood Diversion Passage Improvements |
AF: 85. Lower Cottonwood Diversion Passage Improvements |
|
11/30/2015 |
11/30/2015 |
| IDIQ Contract |
AI: 122. IDIQ Engineering Support |
|
01/31/2015 |
01/31/2015 |
| Oxbow Phase 3A |
AJ: 30. Oxbow Phase 3A |
|
11/30/2014 |
11/30/2014 |
| John Day Basin CTWS Strategy |
AK: 174. John Day Basin Strategy and Project Prioritization Development |
|
02/28/2015 |
02/28/2015 |
| Dunstan Preserve Low Flow Enhancement |
AL: 30. Dunstan Preserve Low Flow Enhancement |
|
10/30/2015 |
09/30/2015 |
| Planting and Maintenance |
AM: 198. Edigar Riparian Planting and Maintenance |
|
12/31/2015 |
09/30/2014 |
| Planting and Maintenance |
AN: 198. Izee Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AO: 198. Kinzau Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AP: 198. St. Clair/Rosebud Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AQ: 198. Circle W Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AR: 198. Barker Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AS: 198. Blanchett Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AT: 198. Rittner Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AU: 198. Painted Hills Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting and Maintenance |
AV: 198. Meredith Riparian Planting and Maintenance |
|
12/31/2015 |
12/31/2015 |
| Planting |
AW: 47. Bridge/Bear Creek Riparian Planting |
|
11/30/2015 |
11/30/2015 |
| Windlass Creek Culvert Replacement |
AX: 85. Windlass Creek Culvert Replacement |
|
12/31/2015 |
12/31/2015 |
| Construct RPB Easement Fence |
AY: 40. RPB Easement Fence |
|
01/31/2016 |
12/31/2015 |
| Develop Design Plan |
BA: 115. Starr Habitat |
|
12/31/2015 |
12/31/2015 |
| Develop Plan to Install Fish Screen and Piping |
BB: 115. Pope - Moon Creek Irrigation Ditch Piping and Fish Screen |
|
12/31/2015 |
12/31/2015 |
| John Day Native Hardwood Planting |
BD: 47. John Day Native Hardwood Planting |
|
11/30/2015 |
09/30/2015 |
| Willow Springs Channel and Meadow Restoration |
BF: 29. Willow Springs Channel and Meadow Restoration |
|
10/31/2014 |
10/31/2014 |
| Attach Progress Report in Pisces |
BH: 132. Submit Annual Report for the Period (02/01/2010) to (01/31/2012) |
|
12/31/2015 |
|
| Attach Progress Report in Pisces |
BI: 132. Submit Annual Report for the Period (02/01/2012) to (01/31/2014) |
|
12/31/2015 |
|
| John Day Partnership |
BJ: 191. John Day Partnership |
|
01/31/2016 |
12/31/2015 |
| Aspen Fence |
BK: 40. Sheep Creek Restoration |
|
01/31/2016 |
12/31/2015 |
| Produce accessible, error-checked datasets |
BL: 157. Telemetry Tracking |
|
01/31/2016 |
12/31/2015 |
| Fish Passage on Meredith #3 |
BM: 184. Meredith #3 |
|
12/31/2015 |
09/30/2015 |
| Fish Passage on Meredith #4 |
BN: 184. Meredith #4 |
|
12/31/2015 |
09/30/2015 |
| Cottonwood Diversion Improvement #2 Cox/Bansen |
BQ: 84. Cottonwood Creek #2 Cox/Bansen Diversion |
|
10/31/2015 |
09/30/2015 |
| EC Compliance for 2016-2017 Projects |
BR: 165. Produce Environmental Compliance Documentation - 2016 - 2017 |
|
01/31/2016 |
01/29/2016 |
| Design of Mallory Creek Road Re-Route |
BS: 175. Design of Mallory Creek Road Re-Route |
|
01/31/2016 |
09/30/2015 |
| Design of Pope Moon Creek Project |
BT: 175. Design of Pope Moon Creek Project |
|
01/31/2016 |
01/29/2016 |