Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
71856
Contract Title:
1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
68536: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
  • 75300: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
This project was initiated on July 1, 1984 under the BPA contract and allows for initial landowner contacts, agreement development, project design, budgeting, and implementation for anadromous fish habitat improvement on privately owned lands within the John Day Basin.  

The purpose of the John Day Fish Habitat Enhancement Program is to enhance production of indigenous wild stocks of spring chinook and summer steelhead within the sub basin through habitat protection, enhancement and fish passage improvements.

In work period 3-1-2016 thru 2-29-2017 the fish habitat program will construct approximately 25.4 miles of riparian protection fence, 325 acres and 13.50 miles of creeks protected, coordination with 4 landowners (Martin, Ecotrust, USFS/permittee, and Pryor).  The actual number of stream miles protected is probably higher, due to sinuosity and ground truthing this summer will correct any missed judgments.  Construction will include approximately 1.0 miles of riparian fence on Fields Creek/Martin property tributary to the John Day River, 5.0 miles of riparian fence on Ecotrust property on Desolation Creek tributary of the North Fork John Day River, 11.40 miles riparian fence on Tex and Murderer's Creek on USFS property tributary of the Upper John Day River, and 8.0 miles riparian fence on the Tenmile Creek on Pryor property tributary of the Lower John Day River.  There will be approximately 42 gates and 15 watergaps constructed on riparian fence project sites.

An OWEB application has been applied for on all projects asking for 50% of funds.  The USFS has also provided $28,000 towards Tex and Murderer's Creek projects.
Account Type(s):
Expense
Contract Start Date:
03/01/2016
Contract End Date:
02/28/2017
Current Contract Value:
$582,143
Expenditures:
$582,143

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC for the Fish Habitat Program A: 165. Environmental Compliance 09/30/2016 09/30/2016
Select Project Sites B: 114. Select Project Sites 02/28/2017 02/28/2017
Riparian Fence Installation C: 40. Martin Property - Fields Creek 08/31/2016 08/31/2016
Riparian Fence Installation D: 40. Ecotrust Property - Desolation Creek 09/01/2016 09/01/2016
Riparian Fence Installation E: 40. USFS Property - Tex Creek 12/30/2016 12/30/2016
Riparian Fence Installation F: 40. USFS Property - Murderer's Creek 10/15/2016 10/15/2016
Riparian Fence Installation G: 40. Pryor Property - Tenmile Creek 10/15/2016
15 Year Cooperative Agreement on Martin Property - Fields Creek I: 92. Martin Property - Fields Creek 04/01/2016 04/01/2016
15 Year Cooperative Agreement on Ecotrust Property - Desolation Creek J: 92. Ecotrust Property - Desolation Creek 08/01/2016 08/01/2016
15 Year Cooperative Agreement on USFS Property - Tex Creek K: 92. USFS Property - Tex Creek 03/31/2016 03/31/2016
15 Year Cooperative Agreement on USFS Property - Murderer's Creek L: 92. USFS Property - Murderer's Creek 04/03/2016 04/03/2016
15 Year Cooperative Agreement on Pryor Property - Tenmile Creek M: 92. Pryor Property - Tenmile Creek 04/03/2016 04/03/2016
15 Year Cooperative Agreement- John Day River Basin N: 92. New Place Holder - John Day River Basin 03/31/2016 03/31/2016
Maintenance of Riparian Projects O: 186. Maintain Terrestrial Structures 02/28/2017 02/28/2017
Herbicide Application P: 198. Herbicide Application 09/30/2016 09/30/2016
Completed Annual Report R: 132. Submit Progress Report for the Period (March 1, 2015) to (February 29, 2016) 05/16/2016 05/16/2016
Program Management and Project Prioritization S: 119. Program Management 02/28/2017 02/28/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 6 instances of WE 40 Install Fence
  • 6 instances of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 6 instances of WE 40 Install Fence
  • 6 instances of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 03/01/2016
B 114 Select Project Sites 03/01/2016
C 40 Martin Property - Fields Creek 07/13/2016
D 40 Ecotrust Property - Desolation Creek 07/13/2016
E 40 USFS Property - Tex Creek 07/13/2016
F 40 USFS Property - Murderer's Creek 07/13/2016
G 40 Pryor Property - Tenmile Creek 07/13/2016
H 40 New Fence Placeholder Approximately 2 Miles (Location Unknown Placeholder)
I 92 Martin Property - Fields Creek 03/01/2016
J 92 Ecotrust Property - Desolation Creek 03/01/2016
K 92 USFS Property - Tex Creek 03/01/2016
L 92 USFS Property - Murderer's Creek 03/01/2016
M 92 Pryor Property - Tenmile Creek 03/01/2016
N 92 New Place Holder - John Day River Basin 03/01/2016
O 186 Maintain Terrestrial Structures 03/01/2016
P 198 Herbicide Application 07/13/2016
Q 185 Periodic Status Reports for BPA 03/01/2016
R 132 Submit Progress Report for the Period (March 1, 2015) to (February 29, 2016) 03/01/2016
S 119 Program Management 03/01/2016