Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 75300: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Project Number:
Title:
John Day Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
75300
Contract Title:
1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
71856: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
  • 74313 REL 26: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
This project was initiated on July 1, 1984 and allows for initial landowner contacts, agreement development, project design, budgeting, and implementation for anadromous fish habitat improvement on privately owned lands within the John Day Basin.  

The purpose of the John Day Fish Habitat Enhancement Program is to enhance production of indigenous wild stocks of spring chinook and summer steelhead within the subbasin through habitat protection, enhancement and fish passage improvements.

Under this contract we coordinate with 8 landowners (USFS Umatilla, Ecotrust, USFS Malheur, Mund, Antone, Brown/Stafford, Lavelle Holmes, Neal, and Pryor properties) and construct approximately 27.3 miles of riparian protection fence to protect 1865 acres and 16.00 miles of stream.   Construction will include approximately 45 gates and 15 watergaps at the sites identified below:
• 5.5 miles of riparian fence on Hinton Creek, a tributary to the North Fork John Day River (USFS Umatilla)
• 4.0 miles of riparian fence on Desolation Creek, , a tributary of the North Fork John Day River (Ecotrust property)
• 2.0 miles riparian fence on Lemon Creek,, a tributary of the South Fork John Day River(USFS Malheur)
• 5.5 miles riparian fence on the MFJDR (Mund property).
• 1.3 miles riparian fence on Pine Hollow Creek  a tributary of Rock/Mountain Creek's a tributary to Lower John Day River (Antone property)
• 1.0 miles on Badger Creek a tributary to Lower John Day River (Stafford/Brown property).
•              1.0 miles on Middle Fork John Day River/Lavelle Holmes property.
•              1.0 miles on Long Creek/Neal property (Over site and Maintenance of this project.
•               6.0 miles on Ten Mile Creek/ Pryor property,  Will use all OWEB funds for Labor costs,  BPA funds purchased the materials in the 2016 budget.

  

An OWEB application has been for 50% of funds for Labor and Materials on all projects except MFJDR/Mund,  Explanations are after each project listed above.
Account Type(s):
Expense
Contract Start Date:
03/01/2017
Contract End Date:
02/28/2018
Current Contract Value:
$581,188
Expenditures:
$581,188

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Program Management and Project Prioritization A: 119. Program Management 02/28/2018 02/28/2018
EC for the Fish Habitat Program B: 165. Environmental Compliance 07/30/2017 07/30/2017
Select Project Sites C: 114. Select Project Sites 02/28/2018 12/29/2017
Riparian Fence Installation D: 40. USFS Property - Hinton Creek 08/31/2017 08/31/2017
Riparian Fence Installation E: 40. Ecotrust Property - Desolation Creek 02/28/2018 12/29/2017
Riparian Fence Installation F: 40. USFS Property - Lemon Creek 09/29/2017 09/29/2017
Riparian Fence Installation G: 40. Mund Property - Middle Fork John Day River 02/28/2018 02/28/2018
Riparian Fence Installation H: 40. Antone Property - Pine Hollow Creek 02/28/2018
Riparian Fence Installation I: 40. Brown Property - Badger Creek 02/28/2018 12/29/2017
Riparian Fence Installation J: 40. Holmes Property - Middle Fork John Day River 12/01/2017 12/29/2017
Riparian Fence Installation K: 40. Pryor Property - Ten Mile Creek 09/18/2017 09/18/2017
15 Year Cooperative Agreement on Neal Property - Long Creek L: 92. Neal Property - Long Creek 03/27/2017 03/27/2017
Maintenance of Riparian Projects M: 186. Maintain Terrestrial Structures 02/28/2018 12/29/2017
Rebuild of wildfire damaged riparian fence N: 186. Maintain Terrestrial Structures - Campbell Property - Hay Creek 02/28/2018 12/29/2017
Herbicide Application O: 198. Herbicide Application 09/30/2017 09/30/2017
Completed Annual Report Q: 132. Submit Progress Report for the Period (March 1, 2016) to (February 28, 2017) 05/31/2017 05/31/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 8 instances of WE 40 Install Fence
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 8 instances of WE 40 Install Fence
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Program Management 03/01/2017
B 165 Environmental Compliance 03/01/2017
C 114 Select Project Sites 03/01/2017
D 40 USFS Property - Hinton Creek 11/30/2017
E 40 Ecotrust Property - Desolation Creek 11/30/2017
F 40 USFS Property - Lemon Creek 11/30/2017
G 40 Mund Property - Middle Fork John Day River 11/30/2017
H 40 Antone Property - Pine Hollow Creek 11/29/2018
I 40 Brown Property - Badger Creek 11/30/2017
J 40 Holmes Property - Middle Fork John Day River 11/30/2017
K 40 Pryor Property - Ten Mile Creek 03/01/2018
L 92 Neal Property - Long Creek 02/03/2017
M 186 Maintain Terrestrial Structures 02/03/2017
N 186 Maintain Terrestrial Structures - Campbell Property - Hay Creek 02/03/2017
O 198 Herbicide Application 11/29/2017
P 185 Periodic Status Reports for BPA 03/01/2017
Q 132 Submit Progress Report for the Period (March 1, 2016) to (February 28, 2017) 03/01/2017