SOW Report
Contract 72548: 1999-017-00 EXP NPT LAPWAI CREEK WATERSHED RESTORATION
Project Number:
Title:
Protect and Restore Lapwai Creek Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
72548
Contract Title:
1999-017-00 EXP NPT LAPWAI CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
68672: 1999-017-00 EXP NPT - LAPWAI CREEK WATERSHED RESTORATION
  • 75888: 1999-017-00 EXP LAPWAI CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
PROJECT/CONTRACT HISTORY:

Our mission is to work proactively within the region’s diverse landscapes to restore and protect the ecological processes of the Lapwai Creek watershed to the greatest extent possible.  We will work to rehabilitate habitat that will support healthy, self-sustaining fish populations and provide clean water for the benefit of all.  We will work within present challenges and opportunities toward achieving a balance whereby all communities can thrive for generations to come.

Hé-yey, Nez Perce for steelhead or rainbow trout (Oncorhynchus mykiss), are a culturally and ecologically significant resource of the Lapwai Creek watershed and compose a portion of the federally listed Snake River Basin Steelhead distinct population segment (DPS).  The majority of the Lapwai Creek drainage is federally identified as critical habitat for this DPS while also providing habitat for the federally listed Snake River Nacó’x, or fall chinook (Oncorhynchus tshawytscha), evolutionarily significant unit (ESU).  The Nez Perce Soil and Water Conservation District (District) and the Nez Perce Tribe Department of Fisheries Resources Management- Watershed (Tribe), in an effort to support the continued existence of these and other aquatic species, have developed the "Strategy for the Ecological Restoration of Lapwai Creek Watershed" document to direct efforts and resources toward the highest priority restoration projects and areas of the Lapwai Creek watershed.  The prioritization framework considered four aspects to determine the relative importance of performing restoration in a certain area: density of critical fish species, physical condition of the AU, water quantity, and water quality.  It was established, through vigorous data analysis within these four areas, that the top three areas to pursue restoration within the Lapwai Creek watershed are Lapwai Creek from stream km 17-34, Sweetwater Creek from the mouth to km 13 and from the mouth of Lapwai Creek to km 17.

SUMMARY OF CY 16 CONTRACT:

The "Strategy for the Ecological Restoration of Lapwai Creek Watershed," which was completed under the FY 07 contract, was the main reference for prioritizing implementation and developing the CY 16 SOW.  

Implementation projects planned for the 2016 SOW include the following:

A total of 7 sites, treating 27.35 acres.

o  Tribal Trust Unit 3123 Spring Creek Raceway- implementation of noxious weed control and maintenance of riparian planting on 1.0 acres.
o  Tribal Trust Unit 3123 Spring Creek Wetlands- implementation of noxious weed control on1.0 acres.
o  Tribal Trust Unit 3125 Fisheries Building -  implementation of noxious weed control and maintenance of riparian planting on 0.4 acres.
o  Tribal Trust Unit 30 - implementation of noxious weed control and maintenance of riparian planting on 9.0 acres.
o  Tribal Allotment 365 - implementation of noxious weed control and maintenance of riparian plantings on 6.45 acres.
o  Tribal Allotment 419A - implementation of noxious weed control and seeding of native grasses on 9.0 acres.
o  Lutes Wetland adjacent to Tribal Allotment 350 - implementation of noxious weed control and maintenance of plantings on 0.5 acres.


Bridge Replacement--  A bridge will be replaced on Tribal Allotment 365 over Sweetwater Creek

Design-- An environmental consulting firm will be contracted to develop a final restoration design for a .4 mile section of Sweetwater Creek located in Sweetwater Creek Assessment Unit #1 (the 2nd highest priority Assessment Unit).

Outreach and Education-- Education and outreach will continue to the general public, fellow professionals, high school and college students, and especially elementary school students, e.g. the  "Steelhead in the Classroom" program for 6th graders. Partners include the Lapwai School District, Lewiston School District, and Idaho Department of Fish and Game.
Account Type(s):
Expense
Contract Start Date:
05/01/2016
Contract End Date:
04/30/2017
Current Contract Value:
$358,205
Expenditures:
$358,205

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration No Interested Party dxaffonso@bpa.gov (503) 230-3893
Elisabeth Bowers Bonneville Power Administration Yes Env. Compliance Lead ekbowers@bpa.gov (503) 230-5184
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Paul Charpentier Nez Perce Tribe Yes Interested Party paulc@nezperce.org (208) 621-4739
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Bobby Hills Nez Perce Tribe Yes Technical Contact bobbyh@nezperce.org (208) 621-3537
Travis House Nez Perce Tribe Yes Contract Manager thouse@nezperce.org (208) 621-4739
Mary Hoxer Bonneville Power Administration Yes Interested Party mjhoxer@bpa.gov (503) 230-4475
Shawn Kaschmitter Nez Perce Tribe Yes Technical Contact shawnk@nezperce.org (208) 621-4728
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Ashlee Rudolph Bonneville Power Administration No Interested Party abrudolph@bpa.gov (503) 230-4475
Emmit Taylor, Jr. Nez Perce Tribe Yes Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
ESA/NEPA/NHPA Compliance complete B: 165. ESA/NEPA/NHPA Compliance for Implementation Projects 04/30/2017 04/30/2017
1.0 Acres Maintenance of Native Vegetation on TU 3123 Spring Creek Raceway C: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Raceway 04/30/2017 04/30/2017
1.0 Acres of Invasive Plant Species Controlled on TU 3123 Spring Creek Wetland D: 198. Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Wetland 04/30/2017 04/30/2017
9.0 Acres Maintenance of Native Vegetation on TU 30 E: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TU 30 04/30/2017 04/30/2017
0.40 Acres Maintenance of Native Vegetation on TU 3125 Fisheries Building F: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species TU 3125 Fisheries Building 04/30/2017 04/30/2017
5.45 Acres of Plant maintenance and weed control at TA 365 G: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TA 365 04/30/2017 04/30/2017
.5 acres of plant maintenance and weed control at Lutes wetland, adjacent to TA 350 H: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species at Lutes Wetland 04/30/2017 04/30/2017
9.0 Acres of Invasive Plant Management on TA 419A I: 198. Treat Exotic Invasive Plant Species and seed native grasses on TA 419A 04/30/2017 04/30/2017
Sweetwater Creek Bridge XS-15 replaced J: 184. Replace Sweetwater Creek Bridge XS-15 03/15/2017 03/30/2017
Engineering design for .4 miles of Sweetwater Creek K: 175. Engineering Design for Sweetwater Creek SW-03 project 04/28/2017 04/28/2017
Environmental and Cultural Compliance of Upper Lapwai Creek -- Reach 14 L: 175. Environmental Compliance and Cutural Assessment for Restoration of Reach 14 Upper Lapwai Creek 03/30/2017 03/30/2017
Lapwai Creek Education and Outreach M: 99. Lapwai Creek Project Area Education and Outreach 04/30/2017 04/30/2017
FY 17 SOW Package N: 119. Management, Coordination and Communication 04/30/2017 04/30/2017
Completed Annual Report O: 132. Submit Progress Report for the period May 2016 to April 2017 04/30/2017 04/30/2017
Completed Annual Report P: 132. Confirm previous year's (May 2015- April 2016) progress report is uploaded 05/30/2016 05/30/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 7 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 05/01/2016
B 165 ESA/NEPA/NHPA Compliance for Implementation Projects 05/01/2016
C 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Raceway 05/01/2016
D 198 Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Wetland 05/01/2016
E 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TU 30 05/01/2016
F 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species TU 3125 Fisheries Building 05/01/2016
G 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TA 365 05/01/2016
H 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species at Lutes Wetland 05/01/2016
I 198 Treat Exotic Invasive Plant Species and seed native grasses on TA 419A 05/01/2016
J 184 Replace Sweetwater Creek Bridge XS-15 05/01/2016
K 175 Engineering Design for Sweetwater Creek SW-03 project 05/01/2016
L 175 Environmental Compliance and Cutural Assessment for Restoration of Reach 14 Upper Lapwai Creek 05/01/2016
M 99 Lapwai Creek Project Area Education and Outreach 05/01/2016
N 119 Management, Coordination and Communication 05/01/2016
O 132 Submit Progress Report for the period May 2016 to April 2017 05/01/2016
P 132 Confirm previous year's (May 2015- April 2016) progress report is uploaded 05/01/2016