| Receipt of environmental compliance clearance from BPA. |
A: 165. Complete and/or initiate Environmental Permitting for Project Activities |
|
04/30/2018 |
04/30/2018 |
| Receipt of environmental compliance clearance from BPA. |
B: 165. Rock Creek Fish Habitat Enhancement Project EC requirements |
|
04/30/2018 |
04/30/2018 |
| All administrative tasks fulfilled with timely quality products |
C: 119. Phase 3 Rock Creek Project Administration |
|
04/30/2018 |
|
| Install large wood complexes and habitat boulders to increase habitat complexity and diversity |
D: 29. Install Large Wood Complexes and habitat boulders along Rock Creek |
|
04/30/2018 |
|
| Construct meandering stream channel |
E: 30. Construct Rock Creek Restoration Channel |
|
04/30/2018 |
|
| Remove draw bottom road |
F: 33. Obliterate draw bottom road along Rock Creek |
|
04/30/2018 |
|
| All administrative tasks fulfilled with timely quality products |
G: 119. Southern Cross Conservation Property Fish Habitat Enhancement Project Administration |
|
04/30/2017 |
09/30/2016 |
| Construct Riparian Conservation Easement Fences |
H: 40. Install Riparian Fences on Cunha Easement along Dark Canyon and Meadow Creeks |
|
06/23/2017 |
06/23/2017 |
| Construct Riparian and Property Fences |
I: 40. Install Fences on Catherine Creek Conservation Projects |
|
06/30/2017 |
06/30/2017 |
| Plant native trees, shrubs, and grass on the CC44 Southern Cross Project |
J: 47. Plant native trees, shrubs, and grasses CC44 Southern Cross Conservation Property |
|
04/30/2017 |
11/11/2016 |
| Conduct Fish Salvage Operations |
K: 28. Conduct Fish Salvage operations on the CC44 Project |
|
08/15/2016 |
08/15/2016 |
| Replace undersized culvert on Sheep Creek |
L: 184. Conduct site survey, prepare design and install culvert on Sheep Creek |
|
04/30/2017 |
09/30/2016 |
| Survey & Design for Limber Creek culverts |
M: 175. Conduct site survey & prepare culvert designs Limber Jim Creek/North Fork Limber Ck |
|
04/30/2017 |
10/28/2016 |
| Conduct maintenance on McCoy, Dark Canyon, Meadow, Willow, Rock, and Catherine Projects |
N: 186. Maintain instream structures, fences, and off-channel water developments |
|
04/30/2018 |
04/30/2018 |
| Maintain vegetation and control weeds on conservation projectst |
O: 198. Maintain Vegetation and Control Weeds on conservation projects |
|
04/30/2018 |
04/30/2018 |
| Complete outreach & education activities |
P: 99. Public Outreach and Education |
|
04/30/2018 |
04/30/2018 |
| Conduct ongoing project development and coordination activities |
Q: 114. CTUIR Grande Ronde Subbasin Restoration Coordination |
|
04/30/2018 |
04/30/2018 |
| BiOp Fish Habitat Project Opportunity Development and Review |
R: 114. Solicit, review and select BiOp expense & capital projects |
|
04/30/2018 |
04/30/2018 |
| Develop project design plan sets. |
S: 174. Develop project designs and produce plans |
|
04/30/2018 |
04/30/2018 |
| Administer Project |
T: 119. Manage and Administer CTUIR GR Subbasin Restoration Project |
|
04/30/2018 |
04/30/2018 |
| Upload 2016 Annual Report |
U: 132. 2016 Annual Report - May 2016 - April 2017 |
|
04/30/2017 |
06/30/2017 |
| Upload 2017 Annual Report |
W: 132. 2017 Annual Report - May 2017 - April 2018 |
|
04/30/2018 |
04/30/2018 |