| Province | Subbasin | % |
|---|---|---|
| Columbia Cascade | Okanogan | 100.00% |
| Previous: | Next: |
|---|---|
| 67596: 1996-094-01 EXP SCOTCH CREEK WILDLIFE AREA: O&M (ENHANCEMENTS) |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | A: 119. Project implementation management and contract administration | 06/30/2017 | 06/29/2017 | |
| Documentation and assistance for environmental and cultural resource clearances | B: 165. Environmental Compliance Documentation and Clearance | 06/30/2017 | 06/29/2017 | |
| Coordinate Wildlife Area Advisory Committee meetings | C: 99. Coordinate Wildlife Area Advisory Committee meetings | 06/30/2017 | 09/30/2016 | |
| Wildlife Area Management Plan | D: 193. Continue efforts to produce a new operating management plan | 06/30/2017 | 06/29/2017 | |
| Maintain fire protection actions and assure fire response capability | E: 186. Wildfire Protection: Payments for protection agreements, Fire wise protections | 07/31/2016 | 09/30/2016 | |
| GIS inventory of infrastructure on all units. | F: 115. Produce a comprehensive GIS project to inventory infrastructure on all units | 06/30/2017 | 06/29/2017 | |
| Maintain facilities, site infrastructure, and equipment | G: 186. Maintain facilities and project equipment | 06/30/2017 | 06/29/2017 | |
| Construct 2 new buildings for equipment storage | H: 201. Equipment storage buildings (sheds) at the Scotch Creek HQ baseyard | 06/30/2017 | 06/29/2017 | |
| Boundary fence maintenance; repair, replacement or removal as needed | I: 186. Maintain boundary fence: Repair, Replacement or Removal | 06/30/2017 | 06/29/2017 | |
| Improved access roads, public parking areas and maintained informational and regulatory signs. | J: 188. Maintain access roads, parking areas, regulatory signs and reader boards | 06/30/2017 | 06/29/2017 | |
| Improved public access to the Chesaw unit | K: 188. Upgrade public access parking: Chesaw unit | 06/30/2017 | 06/29/2017 | |
| Noxious weed control | L: 199. Weed Control | 06/30/2017 | 06/29/2017 | |
| Continue to restore riparian zone habitats: Scotch Creek Wildlife Management Area's | O: 198. Continue to Restore Riparian Habitats on various WMA's: maintain Trees and Shrubs (re-plant) | 06/02/2017 | 06/02/2017 | |
| Construct and install nest boxes/platforms. | P: 36. Fabricate and install nest boxes/platforms | 06/30/2017 | 06/29/2017 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Project implementation management and contract administration | 07/01/2016 | ||||||
| B | 165 | Environmental Compliance Documentation and Clearance | 07/01/2016 | ||||||
| C | 99 | Coordinate Wildlife Area Advisory Committee meetings | 07/01/2016 | ||||||
| D | 193 | Continue efforts to produce a new operating management plan | |||||||
| E | 186 | Wildfire Protection: Payments for protection agreements, Fire wise protections | 07/15/2016 | ||||||
| F | 115 | Produce a comprehensive GIS project to inventory infrastructure on all units | 07/01/2016 | ||||||
| G | 186 | Maintain facilities and project equipment | 07/01/2016 | ||||||
| H | 201 | Equipment storage buildings (sheds) at the Scotch Creek HQ baseyard | 11/21/2016 | ||||||
| I | 186 | Maintain boundary fence: Repair, Replacement or Removal | 07/01/2016 | ||||||
| J | 188 | Maintain access roads, parking areas, regulatory signs and reader boards | 07/01/2016 | ||||||
| K | 188 | Upgrade public access parking: Chesaw unit | 11/21/2016 | ||||||
| L | 199 | Weed Control | 07/01/2016 | ||||||
| M | 115 | Vegetation Inventory | 07/01/2016 | ||||||
| N | 47 | Restore Native Shrub-steppe habitat: Eder unit | 11/21/2016 | ||||||
| O | 198 | Continue to Restore Riparian Habitats on various WMA's: maintain Trees and Shrubs (re-plant) | 11/21/2016 | ||||||
| P | 36 | Fabricate and install nest boxes/platforms | 07/01/2016 | ||||||
| Q | 194 | Manage and Report Revenue from Leases and Share-cropping Agreements: 2016 and 2018 (2-year) | 07/01/2016 | ||||||
| R | 185 | Periodic Status Reports for BPA | 07/01/2016 | ||||||
| S | 132 | [Deliverable due next period] Progress Report (2-year): 2016 and 2017 (01/01/2016 - 12/31/2017) | 07/01/2016 |