| Province | Subbasin | % |
|---|---|---|
| Mountain Snake | Salmon | 100.00% |
| Previous: | Next: |
|---|---|
| 76296: 2007-127-00 EXP SOUTH FORK SALMON PASSAGE RESTORATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | B: 119. Project Management, Coordination, and Administration | 03/31/2019 | 03/14/2019 | |
| Provide Environmental Compliance Documentation to BPA | C: 165. Provide Environmental Compliance Documentation to BPA | 10/31/2018 | 09/30/2018 | |
| Watershed and Habitat Restoration Outreach and Education | D: 99. Public outreach and education | 03/31/2019 | 03/14/2019 | |
| Maintain riparian plantings at Wapiti and Burgdorf Meadows | E: 198. Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 10/31/2018 | 10/31/2018 | |
| Remove reed canary grass at Wapiti Meadows | F: 199. Remove Reed Canary Grass | 11/30/2018 | 10/31/2018 | |
| Improving a road failure on the old SFSR road | G: 38. Improving road failure on the old SFSR road | 01/10/2019 | ||
| Decommission 14-16 Miles of Forest Roads on the Boise National Forest | H: 33. Dollar Creek Road Decommission 14-16 Miles of Forest Roads | 11/30/2018 | 11/30/2018 | |
| Repair a road failure on Dollar Creek (495) that is delivering sediment to Dollar Creek | I: 38. Dollar Creek road (495) failure repair | 10/31/2018 | 09/30/2018 | |
| Ice Hole Campground Road Restoration | J: 38. Ice Hole Campground Restoration | 11/30/2018 | 11/30/2018 | |
| Decommission 2 miles of road in the Big Creek Watershed | K: 33. Big Creek Road Decomissioning | 10/31/2018 | 10/31/2018 | |
| 3 miles of Big Creek Road Improvements | L: 38. Big Creek Road Improvement | 10/31/2018 | 10/31/2018 | |
| GRAIP Road Surveys complete | M: 115. GRAIP road inventory surveys | 11/30/2018 | 11/30/2018 | |
| FY 2018 Progress Report | N: 132. Submit Progress Report for the period 4/17 thru 3/18 | 03/31/2019 | 03/07/2019 | |
| List of Selected FY2019 Restoration Implementation Projects | O: 114. Identify and Select FY19 Restoration Projects | 03/31/2019 | 02/14/2019 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | 04/01/2018 | ||||||
| B | 119 | Project Management, Coordination, and Administration | 04/01/2018 | ||||||
| C | 165 | Provide Environmental Compliance Documentation to BPA | 04/01/2018 | ||||||
| D | 99 | Public outreach and education | 04/01/2018 | ||||||
| E | 198 | Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 06/01/2018 | ||||||
| F | 199 | Remove Reed Canary Grass | 06/01/2018 | ||||||
| G | 38 | Improving road failure on the old SFSR road | 06/01/2018 | ||||||
| H | 33 | Dollar Creek Road Decommission 14-16 Miles of Forest Roads | 07/20/2018 | ||||||
| I | 38 | Dollar Creek road (495) failure repair | 07/19/2018 | ||||||
| J | 38 | Ice Hole Campground Restoration | 07/20/2018 | ||||||
| K | 33 | Big Creek Road Decomissioning | 06/01/2018 | ||||||
| L | 38 | Big Creek Road Improvement | 06/01/2018 | ||||||
| M | 115 | GRAIP road inventory surveys | 03/21/2018 | ||||||
| N | 132 | Submit Progress Report for the period 4/17 thru 3/18 | 04/01/2018 | ||||||
| O | 114 | Identify and Select FY19 Restoration Projects | 04/01/2018 |