Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74017 REL 48: 2007-127-00 EXP E FORK OF S FORK SALMON PASSAGE RESTORATION
Project Number:
Title:
East Fork of South Fork Salmon River Passage Restoration
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
74017 REL 48
Contract Title:
2007-127-00 EXP E FORK OF S FORK SALMON PASSAGE RESTORATION
Contract Continuation:
Previous: Next:
74017 REL 26: 2007-127-00 EXP E FORK OF S FORK SALMON PASSAGE RESTORATION
  • 74017 REL 68: 2007-127-00 EXP E FORK OF S FORK SALMON PASSAGE RESTORATION
Contract Status:
Closed
Contract Description:
The watershed restoration work elements described in this project area, the South Fork Salmon River and Big Creek Watersheds, follow the watershed restoration approach adopted by the Nez Perce Tribe (NPT) Department of Fisheries Resource Management (DFRM) - Watershed Division. The mission of the Nez Perce Tribe Watershed Division (NPT-WD) is to protect and restore aquatic ecosystems using a holistic approach encompassing entire watersheds from ridge-top to ridge-top throughout the Nez Perce Tribe Ceded Territory. This restoration work has its roots in exercising Tribal sovereignty and protecting rights reserved under the Nez Perce Treaty of 1855 with the United States Federal Government. Specifically, our mission is to:
•Be a leader in holistic aquatic ecosystem restoration;
•Ensure and facilitate the protection of currently healthy and properly functioning aquatic ecosystems;
•Aggressively restore degraded aquatic ecosystems by any and all means necessary;
•Ensure our efforts focus on restoring the functions that support healthy ecosystems, such as natural stream flows, appropriate sediment loads, floodplain connectivity, and appropriately vegetated riparian corridors;
•Develop clear and quantitatively defined goals and standards for healthy aquatic ecosystems, as well as the protocols to monitor the success and status of recovery efforts and facilitate adaptive management strategies;
•Coordinate and collaborate with appropriate individuals and/or entities with land management authority to ensure plans and activities are protective and respectful of aquatic ecosystems;
•Provide educational opportunities and outreach materials for all age groups, other agencies, and the public on environmental issues and ethics;
•Maintain a workforce which possesses the highest level of integrity and professionalism, and is well organized, passionate, creative, and connected to the land and resources, and;
•Work within and implement the integrated management strategies of the Department of Fisheries Resource Management.
The NPT DFRM - Watershed Division is working in partnership with the Payette and Boise National Forests; Valley and Idaho Counties; Idaho's Department of Environmental Quality; Idaho's Department of Fish and Game; Idaho's Office of Species Conservation; NOAA; USFWS; and private landowners to achieve restoration goals.

PROJECT GOAL:
The primary goal of this project is to restore the aquatic ecosystems of Big Creek and the South Fork Salmon River, addressing all limiting factors, so that the physical habitat within these watersheds no longer limits recovery of ESA Threatened summer Chinook and steelhead populations. Habitat improvement projects proposed by the Nez Perce Tribe (Tribe) in partnership with the Boise and Payette National Forests (Forests), aim to increase the productivity and viability of these threatened fish.
PROJECT SUMMARY:
The Tribe proposes a suite of restoration projects to address the primary factors limiting the abundance and productivity of these focal fish species. The Tribe and Forests prioritized projects based on the Salmon Subbasin Plan, NMFS Draft Recovery Plan, current watershed surveys, and the SFSR and Big Creek Expert Panel process.

Objectives of this proposal include:
OBJ-1: Reduce the number of fish passage barriers so that none exist within the SFSR/BC Watersheds
OBJ-2: Reduce chronic and acute sediment inputs (fines) and reduce road densities within the SFSR/BC Watersheds.
OBJ-3: Protect and Restore Riparian Habitats through conservations easements, livestock fencing and planting of riparian plants so they can perform critical ecological functions.
OBJ-4: Reduce the Impact of Mining Activities on Focal Species by reducing road density, restoring vegetation, creating sediment traps and improving water quality so affected streams are no longer 303d listed.
OBJ-5: Increase Habitat Quality for Focal Species through reduced water temperatures and quality, increased large woody debris and reduced sediment fines.  
Account Type(s):
Expense
Contract Start Date:
04/01/2019
Contract End Date:
03/31/2020
Current Contract Value:
$680,623
Expenditures:
$680,623

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Marcie Carter Nez Perce Tribe Yes Administrative Contact marciec@nezperce.org (208) 621-3534
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Zachary Gustafson Bonneville Power Administration Yes Env. Compliance Lead zrgustafson@bpa.gov (503) 230-4419
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Wesley Keller Nez Perce Tribe Yes Contract Manager wesleyk@nezperce.org (208) 634-3031
Matthew Schwartz Bonneville Power Administration Yes COR mdschwartz@bpa.gov (503) 230-4225
Emmit Taylor, Jr. Nez Perce Tribe Yes Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Project Management, Coordination, and Administration 03/31/2020 03/01/2020
Provide Environmental Compliance Documentation to BPA C: 165. Provide Environmental Compliance Documentation to BPA 11/30/2019 08/01/2019
Watershed and Habitat Restoration Outreach and Education D: 99. Public outreach and education 03/31/2020 03/16/2020
Maintain riparian plantings at Wapiti and Burgdorf Meadows E: 198. Maintain Riparian plantings at Wapiti and Burgdorf Meadows 03/31/2020 12/31/2019
Remove reed canary grass at Wapiti Meadows F: 199. Remove Reed Canary Grass 11/30/2019 09/30/2019
Improving a road failure on the old SFSR road G: 38. Improving road failure on the old SFSR road 11/30/2019 07/30/2019
Decommission 14-16 Miles of Forest Roads on the Boise National Forest in Dollar Creek H: 33. Dollar Creek Road Decommission 14-16 Miles of Forest Roads 11/30/2019 09/30/2019
Complete fishing trail restoration I: 55. Fishing Trail Restoration for sediment reduction 11/30/2019 09/30/2019
Construct Riparian Fence at Ice Hole Campground J: 40. Install Riparian Fence at Ice Hole Campground 11/30/2019 06/30/2019
plant riparian vegetation at Ice Hole Campground to stabilize bank K: 47. Plant vegetation to stabilize banks at Ice Hole Campground 11/30/2019 11/30/2019
2 Educational Signs Installed along Johnson Creek L: 188. Install 2 kiosks and signs on Johnson Creek 11/29/2019 11/29/2019
Improve the Warren Wagon Road (gravel, shape, cross drains) so that sediment delivery to Long Gulch is reduced M: 38. Long Gulch Road Improvement Project 11/15/2019
GRAIP Road Surveys complete N: 115. GRAIP road inventory surveys 11/30/2019 09/30/2019
Remove invasive weeds O: 199. Remove Invasive Weeds from the SFSR and BC Watersheds 10/31/2019 10/31/2019
List of Selected FY2020 Restoration Implementation Projects P: 114. Identify and Select FY2020 Restoration Projects 02/29/2020 02/29/2020
FY 2019 Progress Report Q: 132. Submit Progress Report for 4/1/2018 - 3/31/2019 03/31/2020 03/16/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 199 Remove Vegetation
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 2 instances of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 199 Remove Vegetation
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 2 instances of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 04/01/2019
B 119 Project Management, Coordination, and Administration 04/01/2019
C 165 Provide Environmental Compliance Documentation to BPA 04/01/2019
D 99 Public outreach and education 04/01/2019
E 198 Maintain Riparian plantings at Wapiti and Burgdorf Meadows 03/27/2019
F 199 Remove Reed Canary Grass 03/12/2019
G 38 Improving road failure on the old SFSR road 03/12/2019
H 33 Dollar Creek Road Decommission 14-16 Miles of Forest Roads 04/04/2019
I 55 Fishing Trail Restoration for sediment reduction
J 40 Install Riparian Fence at Ice Hole Campground 03/12/2019
K 47 Plant vegetation to stabilize banks at Ice Hole Campground 03/12/2019
L 188 Install 2 kiosks and signs on Johnson Creek 03/28/2019
M 38 Long Gulch Road Improvement Project 06/19/2019
N 115 GRAIP road inventory surveys 03/11/2019
O 199 Remove Invasive Weeds from the SFSR and BC Watersheds 06/20/2019
P 114 Identify and Select FY2020 Restoration Projects 04/01/2019
Q 132 Submit Progress Report for 4/1/2018 - 3/31/2019 04/01/2019