| 74017 REL 26: 2007-127-00 EXP E FORK OF S FORK SALMON PASSAGE RESTORATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Marcie Carter | Nez Perce Tribe | Yes | Administrative Contact | marciec@nezperce.org | (208) 621-3534 |
| Desmond Gelman | Bonneville Power Administration | No | CO Assistant | dxgelman@bpa.gov | (503) 230-4960 |
| Zachary Gustafson | Bonneville Power Administration | Yes | Env. Compliance Lead | zrgustafson@bpa.gov | (503) 230-4419 |
| David Kaplowe | Bonneville Power Administration | Yes | F&W Approver | djkaplowe@bpa.gov | (503) 230-5365 |
| Wesley Keller | Nez Perce Tribe | Yes | Contract Manager | wesleyk@nezperce.org | (208) 634-3031 |
| Matthew Schwartz | Bonneville Power Administration | Yes | COR | mdschwartz@bpa.gov | (503) 230-4225 |
| Emmit Taylor, Jr. | Nez Perce Tribe | Yes | Supervisor | emmitt@nezperce.org | (208) 621-3544 |
| Karen Wolfe | Bonneville Power Administration | Yes | Contracting Officer | ktwolfe@bpa.gov | (503) 230-3448 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | B: 119. Project Management, Coordination, and Administration | 03/31/2020 | 03/01/2020 | |
| Provide Environmental Compliance Documentation to BPA | C: 165. Provide Environmental Compliance Documentation to BPA | 11/30/2019 | 08/01/2019 | |
| Watershed and Habitat Restoration Outreach and Education | D: 99. Public outreach and education | 03/31/2020 | 03/16/2020 | |
| Maintain riparian plantings at Wapiti and Burgdorf Meadows | E: 198. Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 03/31/2020 | 12/31/2019 | |
| Remove reed canary grass at Wapiti Meadows | F: 199. Remove Reed Canary Grass | 11/30/2019 | 09/30/2019 | |
| Improving a road failure on the old SFSR road | G: 38. Improving road failure on the old SFSR road | 11/30/2019 | 07/30/2019 | |
| Decommission 14-16 Miles of Forest Roads on the Boise National Forest in Dollar Creek | H: 33. Dollar Creek Road Decommission 14-16 Miles of Forest Roads | 11/30/2019 | 09/30/2019 | |
| Complete fishing trail restoration | I: 55. Fishing Trail Restoration for sediment reduction | 11/30/2019 | 09/30/2019 | |
| Construct Riparian Fence at Ice Hole Campground | J: 40. Install Riparian Fence at Ice Hole Campground | 11/30/2019 | 06/30/2019 | |
| plant riparian vegetation at Ice Hole Campground to stabilize bank | K: 47. Plant vegetation to stabilize banks at Ice Hole Campground | 11/30/2019 | 11/30/2019 | |
| 2 Educational Signs Installed along Johnson Creek | L: 188. Install 2 kiosks and signs on Johnson Creek | 11/29/2019 | 11/29/2019 | |
| Improve the Warren Wagon Road (gravel, shape, cross drains) so that sediment delivery to Long Gulch is reduced | M: 38. Long Gulch Road Improvement Project | 11/15/2019 | ||
| GRAIP Road Surveys complete | N: 115. GRAIP road inventory surveys | 11/30/2019 | 09/30/2019 | |
| Remove invasive weeds | O: 199. Remove Invasive Weeds from the SFSR and BC Watersheds | 10/31/2019 | 10/31/2019 | |
| List of Selected FY2020 Restoration Implementation Projects | P: 114. Identify and Select FY2020 Restoration Projects | 02/29/2020 | 02/29/2020 | |
| FY 2019 Progress Report | Q: 132. Submit Progress Report for 4/1/2018 - 3/31/2019 | 03/31/2020 | 03/16/2020 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | 04/01/2019 | ||||||
| B | 119 | Project Management, Coordination, and Administration | 04/01/2019 | ||||||
| C | 165 | Provide Environmental Compliance Documentation to BPA | 04/01/2019 | ||||||
| D | 99 | Public outreach and education | 04/01/2019 | ||||||
| E | 198 | Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 03/27/2019 | ||||||
| F | 199 | Remove Reed Canary Grass | 03/12/2019 | ||||||
| G | 38 | Improving road failure on the old SFSR road | 03/12/2019 | ||||||
| H | 33 | Dollar Creek Road Decommission 14-16 Miles of Forest Roads | 04/04/2019 | ||||||
| I | 55 | Fishing Trail Restoration for sediment reduction | |||||||
| J | 40 | Install Riparian Fence at Ice Hole Campground | 03/12/2019 | ||||||
| K | 47 | Plant vegetation to stabilize banks at Ice Hole Campground | 03/12/2019 | ||||||
| L | 188 | Install 2 kiosks and signs on Johnson Creek | 03/28/2019 | ||||||
| M | 38 | Long Gulch Road Improvement Project | 06/19/2019 | ||||||
| N | 115 | GRAIP road inventory surveys | 03/11/2019 | ||||||
| O | 199 | Remove Invasive Weeds from the SFSR and BC Watersheds | 06/20/2019 | ||||||
| P | 114 | Identify and Select FY2020 Restoration Projects | 04/01/2019 | ||||||
| Q | 132 | Submit Progress Report for 4/1/2018 - 3/31/2019 | 04/01/2019 |