Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74313 REL 78: 2007-404-00 EXP CAPTIVE BROOD FACILITY O&M
Project Number:
Title:
Spring Chinook Captive Propagation-Oregon
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
74313 REL 78
Contract Title:
2007-404-00 EXP CAPTIVE BROOD FACILITY O&M
Contract Continuation:
Previous: Next:
74313 REL 58: 2007-404-00 EXP CAPTIVE BROOD FACILITY O&M
  • 84041 REL 3: 2007-404-00 EXP CAPTIVE BROOD FACILITY O&M
Contract Status:
Closed
Contract Description:
The Bonneville Captive Brood facility was constructed in the mid-1990s near the Bonneville Hatchery and was fully funded by BPA.  BPA owns the facility and all associated fish rearing equipment and continues to funds the maintenance of the facility even when fish are not being reared.

The Bonneville Captive Brood facility has been identified as a “Rapid Response/Safety Net Facility" which can be used when an ESA listed stock has been identified as being at risk of going extinct.  The facility is used as a captive brood facility where fish are kept until mature and spawned within the facility.  Eggs produced at the facility are then be shipped to various hatcheries throughout the Columbia Basin for typical fish rearing and eventual release into the natural environment. Some of these fish may be sent back to this facility for the next cycle of captive brood fish rearing.

BPA must maintain this facility in proper working condition in the event that another ESA listed stock was crashing and a Safety Net program was needed. Roof replacement on facility was completed in 2018. Composite and flat roof replacement with a 30 year warranty.

The facility may be used for the rearing of non-ESA listed species or other programs with the permission from BPA.
Account Type(s):
Expense
Contract Start Date:
10/01/2020
Contract End Date:
09/30/2021
Current Contract Value:
$62,528
Expenditures:
$62,528

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
NEPA Clearance and Permits A: 165. NEPA Clearance and Permits 12/31/2020 12/31/2020
Facility Maintenance B: 61. Maintain Safety Net Rearing Facilities at Bonneville Fish Hatchery 09/30/2021 09/30/2021
Not Applicable C: 174. Not Applicable 10/01/2020 10/01/2020
Manage Project and Submit Contract Package F: 119. Manage Project and Prepare Contract Package 09/30/2021 09/30/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 NEPA Clearance and Permits
B 61 Maintain Safety Net Rearing Facilities at Bonneville Fish Hatchery 09/09/2020
C 174 Not Applicable 07/22/2020
D 132 No Annual Report Required
E 185 Periodic Status Reports for BPA
F 119 Manage Project and Prepare Contract Package